132 hydropower reservoirs and dams in Lao Cai must complete the inter-reservoir operation regulations before July 30

Tân Văn |

Lao Cai - Provincial People's Committee requests completion of inter-reservoir operation regulations before July 30.

On April 5, according to PV's investigation, Lao Cai Provincial People's Committee issued a decision approving the list of 132 dam and reservoir works that must build operating coordination regulations.

The development of regulations aims to ensure the safety of works, downstream areas and improve the efficiency of water resource exploitation.

According to the decision, the whole province has 132 projects subject to regulation, including 96 hydropower projects and 36 irrigation projects, distributed on 27 river and stream routes.

The works are concentrated in many important basins such as Chay River, Ngoi Thia, Ngoi Mu, Nam Tuc, Nam Tia, Ngoi San, Nam Tha, Ngoi Bo, Nam Nhun, Ngoi Duong, Suoi Trat...

The Provincial People's Committee requests full updates of basic technical parameters such as reservoir capacity, normal water level, designed flood water level, discharge flow and form of overflow discharge.

The establishment of regulations is carried out on the basis of the 2023 Law on Water Resources and guiding decrees, which clearly stipulate the authority of the Provincial People's Committee in approving the list of lakes and dams on rivers and streams that need to be jointly operated.

According to requirements, the regulations must ensure the principles of safe operation of works, safety of downstream areas; specifically stipulate the coordination of water regulation in the rainy and flood season and dry season.

Determine the responsibilities of management and operation units as well as local functional agencies; and at the same time ensure the maintenance of minimum flow according to regulations.

The Provincial People's Committee assigned the Lao Cai Provincial Department of Agriculture and Environment to preside over and coordinate with the Lao Cai Provincial Department of Industry and Trade to guide relevant units to develop regulations.

After completion, the plans will be summarized and submitted to the Provincial People's Committee for consideration and approval.

The deadline for completing the development of operating coordination regulations for all of the above-mentioned projects is before July 30, 2026.

Along with that, the People's Committees of communes, wards and project managers are required to strengthen coordination and organize the implementation of decisions; regularly monitor and supervise the operation of lakes and dams, especially in extreme weather conditions, in order to promptly respond and ensure safety.

Tân Văn
RELATED NEWS

Two people died while constructing the IC15 connecting road of the Noi Bai - Lao Cai expressway

|

Lao Cai - An accident occurred during construction, killing 2 workers.

Donating land to open roads, creating momentum for development for Lao Cai highland villages

|

Lao Cai - People have agreed to donate land to open new roads when propagated and explained by local authorities.

Moment a school of whales jumps in front of a canoe's bow on Phu Quy Island

|

Lam Dong - A group of divers suddenly recorded the moment a school of about 100 whales swam on a canoe, jumping on the water near Phu Quy Island.

Lily flowers are in season, farmers are busy from 5 am to harvest flowers

|

Hanoi - In the early days of April, flower farmers are busy going to the fields from early morning to have time to cut and deliver fresh lilies to customers.

Gulf tensions: Essential infrastructure in Kuwait hit by new fire from Iran

|

Kuwait confirmed that drone attacks from Iran have heavily damaged government facilities and oil and gas in the capital.

Shabby and desolate scene at the hubways along Sam Son beach

|

Thanh Hoa - Before the auction of the right to exploit the hubways along Sam Son beach, many works were seriously degraded, with a messy scene.

Aptitude assessment exam attendance rate reached 98.33%, about 4,000 absent candidates

|

The first phase of the 2026 competency assessment exam of Vietnam National University, Ho Chi Minh City recorded a candidate attendance rate of 94.33%, with more than 133,000 candidates participating.

Giá đỗ tẩm độc tấn công sức khỏe cộng đồng, chuyện không chỉ ở Lào Cai

Lê Thanh Phong |

Cơ quan công an tỉnh Lào Cai phát hiện đường dây sản xuất giá đỗ ngâm hóa chất độc hại với quy mô lên tới hàng trăm tấn.

Two people died while constructing the IC15 connecting road of the Noi Bai - Lao Cai expressway

Duy Dũng |

Lao Cai - An accident occurred during construction, killing 2 workers.

Donating land to open roads, creating momentum for development for Lao Cai highland villages