2 overpasses in Hanoi are expected to be put into operation at the end of 2026

SÓNG HỮU |

Hanoi - The overpass at Nguyen Chi Thanh intersection and the overpass at Lang Ha intersection belonging to the Ring Road 1 project are expected to be completed and opened to traffic at the end of 2026.

The investment project to build Ring Road 1, Hoang Cau - Voi Phuc section, has its starting point at the intersection with Cat Linh - La Thanh - Yen Lang road at Hoang Cau; the ending point at Voi Phuc traffic junction.

The total length of the route is about 2,274km, with a cross-section scale of 50m.

Total investment of more than 7,210 billion VND. Project implementation period from 2018 to 2026.

Công trường dự án đường Vành đai 1 đoạn Hoàng Cầu - Voi Phục, tháng 8.2026. Ảnh: Sóng Hữu
Construction site of Ring Road 1 project, section Hoang Cau - Voi Phuc, August 2026. Photo: Song Huu
d
Many items of the Ring Road 1 project are entering the completion phase. Photo: Song Huu

The project is invested to complete the entire route according to the plan, with the main items including: Site clearance; foundation, road surface, intersection, drainage, technical trench system, lighting, green trees, sidewalks, traffic organization and relocation of underground and above-ground works within the investment scope.

In addition, 2 overpasses will be built on the route at the Lang Ha - Giang Vo intersection and the Nguyen Chi Thanh intersection.

In which package No. 17 - construction of the overpass at Nguyen Chi Thanh intersection is more complicated because this area is simultaneously constructing the S3 underground station project of urban railway line No. 5 Van Cao - Hoa Lac invested by the Hanoi Urban Railway Management Board.

Trụ cầu vượt nút giao Nguyễn Chí Thanh. Ảnh: Sóng Hữu
The bridge pier over Nguyen Chi Thanh intersection has been formed. Photo: Song Huu
Cacsac
The contractor is implementing many items in the area of the intersection with Nguyen Chi Thanh street. Photo: Song Huu

According to the Hanoi City Civil Works Construction Investment Project Management Board (investor of Ring Road 1 project, Hoang Cau - Voi Phuc section), by early August 2026, package No. 17 - construction of the Nguyen Chi Thanh intersection overpass has completed about 24.45% of the volume.

The contractor has completed the bored piles at the abutments and pillars; and is currently deploying the construction of girder spans.

In which, burning beams S4 is an item located on the ring road of the entire project, this is also a condition for continuing to deploy beam burnings S3 and S5.

In parallel with that, the contractor is carrying out the construction of retaining walls, bridgehead roads, lighting systems and completion items. However, the progress is affected because the Hanoi Urban Railway Management Board is slow to hand over the site in the area between piers T3-T4.

s
The Nguyen Chi Thanh intersection area is being implemented with 2 projects at the same time. Photo: Song Huu

Inspecting the Ring Road 1 project on August 6, Member of the Party Central Committee, Standing Deputy Secretary of the Hanoi Party Committee Nguyen Trong Dong reminded units to focus machinery and vehicles, urgently accelerate progress to ensure that by National Day September 2, Ring Road 1 on the ground will be opened; 2 overpasses on the road must be completed before December 31, 2026.

During the construction process, ensure safety and avoid traffic congestion.

SÓNG HỮU
RELATED NEWS

Nearly 9 years without completing the 2.87km road in Hanoi

|

Hanoi - Problems in site clearance have left the road project from Pham Hung street to Le Duc Tho street unfinished for many years.

Deploying land acquisition to expand roads to 50m in Hanoi

|

Hanoi - Land recovery and site clearance for the project to renovate and upgrade road 70 section Ha Dong - Van Dien - Tu Hiep intersection are being implemented by Kien Hung ward.

The shape of overpass pillars at the nearly 786 billion VND intersection project in Hanoi

|

Hanoi - The Pham Tu - Road 70 intersection project with an investment of nearly 786 billion VND is under construction, and some overpass pillars have taken shape.

Expressway through Khanh Hoa to collect ETC tolls soon

|

Khanh Hoa - It is expected that from August 15, the Quang Ngai - Nha Trang expressway will deploy road use fees in the form of non-stop electronic collection (ETC).

Enforced recovery of 24,061m2 of land to build a 12.5km road in Hanoi

|

Hanoi - Huong Son commune has issued 6 decisions on coercive land recovery to serve site clearance for the My Dinh - Ba Sao - Bai Dinh road construction investment project.

Ho Chi Minh City socializes public services to give people more choices, not adding auxiliary doors

|

Ho Chi Minh City - Experts believe that socialization of public services is only meaningful when people have more convenient choices, not a "side door".

Vietnam national team meets Malaysia in ASEAN Cup 2026 semi-finals

|

Two semi-final matches of ASEAN Cup 2026 have been determined, in which the Vietnamese team meets Malaysia.

Nearly 9 years without completing the 2.87km road in Hanoi

SÓNG HỮU |

Hanoi - Problems in site clearance have left the road project from Pham Hung street to Le Duc Tho street unfinished for many years.

Deploying land acquisition to expand roads to 50m in Hanoi

SÓNG HỮU |

Hanoi - Land recovery and site clearance for the project to renovate and upgrade road 70 section Ha Dong - Van Dien - Tu Hiep intersection are being implemented by Kien Hung ward.

The shape of overpass pillars at the nearly 786 billion VND intersection project in Hanoi

SÓNG HỮU |

Hanoi - The Pham Tu - Road 70 intersection project with an investment of nearly 786 billion VND is under construction, and some overpass pillars have taken shape.