2 belt roads connecting Ho Chi Minh City - Dong Nai are slow in some places and lack capital in others.

HÀ ANH CHIẾN |

Ring Road 3 of Ho Chi Minh City and Dong Nai is behind schedule, only handing over 71% of the land, Ring Road 4 of Ho Chi Minh City and Dong Nai is lacking capital of more than 9,200 billion VND.

The Ho Chi Minh City Ring Road 3 Project, the section passing through Dong Nai province, has a total length of 11.2 km. Of which, component project 1A is 6.26 km long and component projects 3 and 4 are 5 km long, with a total investment capital of VND 2,584 billion, of which 50% is from the central budget and 50% from the local budget. Implementation period is until 2026.

According to Dong Nai Provincial People's Committee, regarding site clearance work in component project 1A, 49 hectares of site have been handed over, reaching 100%.

As for component project 4, the compensation plan has been approved at 100%, and the site has been handed over for 46.46/65 hectares, reaching 71.47%. The locality is continuing to mobilize and organize compulsory handover for the remaining area of ​​18.5 hectares.

Regarding the implementation status of component project 3 - Construction and installation, the project has selected a construction contractor, including 3 main construction and installation packages. The accumulated disbursement to date is 88 billion VND/700 billion VND, reaching 12.69% of the capital plan.

For the Ho Chi Minh City Ring Road 4 project, which is about 200 km long, passing through Dong Nai for 45.54 km (accounting for 23%), the total project investment is 19,151 billion VND. Of which, the cost of site clearance is 7,850 billion VND, the construction cost is 8,594 billion VND, the consulting cost, reserve, and interest is 2,707 billion VND.

PPP investment form, state capital participation is about 9,205 billion VND, the rest is investor capital, toll collection period is 20 years.

According to the People's Committee of Dong Nai province, currently the province's public investment capital has been basically allocated and arranged for other projects in the medium-term public investment plan for the period 2021 - 2025, so it is very difficult to balance the capital participating in the Ho Chi Minh City Ring Road 4 project.

On March 19, the People's Committee of Dong Nai province issued a document on the implementation of the Prime Minister's direction related to important national and key projects in the transport sector and requested departments, branches and localities to urgently carry out the tasks assigned by the People's Committee of Dong Nai province, ensuring the timely implementation of the projects.

For the Ho Chi Minh City Ring Road 3 project, the People's Committee of Nhon Trach district urgently completed site clearance and handed over 100% of the area for project construction before June 30, but it has not been completed yet.

HÀ ANH CHIẾN
TIN LIÊN QUAN

Chọn đi sớm, đi xa để tránh Vành đai 3 ngày cuối nghỉ lễ

Xuyên Đông |

Ngày 3.9 là ngày cuối dịp nghỉ lễ, nhiều người dân đã chấp nhận đi từ sớm hoặc chọn cung đường xa hơn 10 - 15km tránh đi vào Vành đai 3.

Sắp trình Quốc hội xem xét dự án Vành đai 4 TPHCM dài 207km

MINH QUÂN |

Dự án Vành đai 4 dài 207km đi qua TPHCM, Long An, Bình Dương, Đồng Nai và Bà Rịa - Vũng Tàu dự kiến trình Quốc hội quyết định chủ trương đầu tư tháng 10.2024.

Vành đai 3 Hà Nội tắc 8km, tài xế bất lực trên đường về quê

Hữu Chánh |

Hà Nội - Cánh tài xế bất lực nhìn dòng phương tiện ùn tắc kéo dài trên cao tốc Vành đai 3 trong ngày đầu nghỉ lễ Quốc khánh.

Lào Cai thông tin về nhu cầu, đầu mối hỗ trợ bà con vùng lũ

Bảo Nguyên |

Tỉnh Lào Cai vừa thông tin cụ thể về nhu cầu hỗ trợ người dân vùng lũ và đầu mối tiếp nhận cứu trợ của các huyện, thị xã trên địa bàn.

Dân phố cổ Hội An chưa mặn mà đón khách thuê homestay

Hoàng Bin |

Sau hơn 4 tháng thí điểm mô hình đón khách lưu trú trải nghiệm cùng cư dân phố cổ Hội An, chỉ có 1 hộ dân đăng ký loại hình này.

Ứng phó áp thấp nhiệt đới gần Biển Đông có thể mạnh lên thành bão

Phan Anh |

Bộ Nông nghiệp và Phát triển nông thôn (NNPTNT) vừa phát đi công điện về việc ứng phó với áp thấp nhiệt đới gần Biển Đông.

Bắt nguyên Trưởng phòng Tài nguyên và Môi trường huyện Bảo Lâm

HOÀI THANH |

Cơ quan chức năng vừa bắt nguyên Trưởng phòng và một cán bộ Phòng Tài nguyên và Môi trường huyện Bảo Lâm (Lâm Đồng) để phục vụ công tác điều tra.

Bão số 3 Yagi - cơn bão khác thường mạnh nhất châu Á năm nay

Thanh Hà |

Bão Yagi gây ảnh hưởng nghiêm trọng đến nhiều quốc gia, bao gồm Philippines, Trung Quốc, Lào, Myanmar và Thái Lan, Việt Nam.