April 30th on two large construction sites worth more than 48,000 billion VND in the Mekong Delta

Tạ Quang |

Can Tho - On the construction site of the Chau Doc - Can Tho - Soc Trang expressway and Dai Ngai 1 bridge, many engineers and workers are still diligently working during the April 30th and May 1st holidays.

Workers go through the ceremony to "keep the fire" of the expressway worth more than 44,000 billion VND

The Chau Doc - Can Tho - Soc Trang expressway project (phase 1) is 188.2km long, with a total investment of more than 44,691 billion VND, with 4 component projects. Of which, the section through An Giang province is more than 57km, and the rest belongs to Can Tho City, about 132km.

Cao tốc Châu Đốc - Cần Thơ - Sóc Trăng giao nhau với cao tốc Cần Thơ - Cà Mau. Ảnh: Tạ Quang
Chau Doc - Can Tho - Soc Trang expressway intersects with Can Tho - Ca Mau expressway. Photo: Ta Quang

Recorded by Lao Dong Newspaper reporters at construction package No. 2 of component project 3 (Can Tho section), during the holidays, the unit maintained construction throughout the holidays, mobilizing a lot of manpower and equipment to simultaneously deploy items.

Mr. Nguyen Van Toan - Representative of a construction unit said that to date, the bidding package under the unit's responsibility has reached about 53% of the volume, mobilizing 20 construction teams with about 450 officials, engineers, and workers working at the construction site. The goal is to basically complete the sand filling loading work in each segment by June 30, 2026.

Công nhân thi công tại gói thầu xây lắp số 2 thuộc dự án thành phần 3. Ảnh: Tạ Quang
Construction workers at construction package No. 2 of component project 3. Photo: Ta Quang

Worker Luong Van Ngan (former Binh Dinh province) shared that for him, the progress of the project is always put first, because every day of sticking to the construction site is another step to bring the project to the finish line on schedule. Teams maintain continuous construction, arranging many shifts to ensure the progress of items, especially tasks such as pouring and installing bridge railing.

Worker Duong Van Thang said that not only during the April 30th holiday, but also during the past time, contractors have maintained construction throughout Tet and weekends to closely monitor progress, while ensuring full benefits for workers.

Điểm đầu dự án cao tốc Châu Đốc - Cần Thơ - Sóc Trăng tại An Giang. Ảnh: Tạ Quang
The starting point of the Chau Doc - Can Tho - Soc Trang expressway project in An Giang. Photo: Ta Quang

Mr. Vang Dac Duy Tan - Deputy Director of the Can Tho City Traffic and Agricultural Construction Investment Project Management Board (project investor) informed that currently, the bridge section on the route has been basically completed; for the road section, some sections have met the load discharge conditions. On that basis, the investor directed contractors to focus on constructing foundations and road surfaces, and at the same time complete the overloading work at the remaining sections.

The starting point of the expressway project in An Giang, under the scorching sun, dozens of workers and engineers of the Truong Son 11 Management Board are still urgently paving every meter of asphalt.

Công nhân thảm nhựa dưới thời tiết oi bức. Ảnh: Tạ Quang
Workers paving asphalt in hot weather. Photo: Ta Quang

After finishing the C19 and C16 asphalt layers, then completing the traffic safety system, lighting, taluy, median strip... these tasks will be implemented in a rolling manner.

Talking to reporters, Mr. Tran Minh Thanh - Deputy Head of the Steering Committee of Truong Son 11 said that the unit in charge of construction in package 42, the progress has been over 76%, exceeding 0.11% compared to the plan.

Công nhân thi công nhiều vị trí trên cao tốc. Ảnh: Tạ Quang
Workers constructing many positions on the expressway. Photo: Ta Quang

According to the contractor, there are more than 180 machinery and equipment on the construction site, over 220 technical staff, workers, and laborers working throughout the holiday to meet the items being implemented such as load removal, crushed stone base, asphalt concrete paving...

No vacation at Dai Ngai 1 bridge construction site

During the holiday, construction continues to be recorded at Dai Ngai 1 bridge, located on National Highway 60, across the Hau River estuary, connecting Can Tho with Vinh Long. The bridge has an investment of nearly 4,000 billion VND.

Cầu Đại Ngãi 1 nối Cần Thơ với Vĩnh Long. Ảnh: Tạ Quang
Dai Ngai 1 bridge connecting Can Tho with Vinh Long. Photo: Ta Quang

The project started on October 2023 and will be completed in June 2028. To date, the project progress has reached nearly 70% of the contract value. Currently, the investor and the construction unit have simultaneously deployed 33 construction fronts including Dai Ngai 1 bridge, roadbed and route works. The total number of personnel mobilized is over 350 people and 122 locomotives and equipment.

Mr. Nguyen Thanh Sang - a construction worker at the bridge pier shared that when seeing everyone resting during the holiday, he also could not avoid feeling sad. However, above all, it is still pride to contribute to a key project in the area.

Công nhân thi công cầu Đại Ngãi 1. Ảnh: Tạ Quang
Construction workers of Dai Ngai 1 bridge. Photo: Ta Quang

For me, every working day during the holidays is of special significance, because it is not only an effort for the collective but also a practical contribution to the future development of transport infrastructure," said Mr. Thanh Sang.

Representatives of the contractor consortium informed that package No. 15-XL has a total of 24 construction teams, including: 8 teams constructing platforms, pillars, beams, reinforced concrete slabs and embankments; 2 teams constructing bridgehead roads (routes); 4 teams constructing beams, steel beams and cable-stayed cables; 7 teams constructing the main bridge pillar base. Participating forces include 47 technical staff, 253 workers and 77 machines and equipment. To date, the accumulated construction output of package No. 15-XL has reached 61.98%.

Tạ Quang
RELATED NEWS

Workers stick to the construction site during holidays, keeping pace with Ring Road 1 progress

|

Hanoi - During the holidays, the construction site of Ring Road 1 Hoang Cau - Voi Phuc still resonates with the sound of machinery, constructing day and night, determined to maintain project progress.

Morning of the Mekong Delta 30. 4: Officially open to traffic the entire Can Tho - Ca Mau expressway

|

Morning of the Mekong Delta 30. 4: Officially open to traffic the entire Can Tho - Ca Mau expressway; Phu Quoc is ready to serve tourists during major holidays;...

Can Tho - Ca Mau expressway opens to traffic on the entire route from 11:30 am on April 29, tolls are not yet collected immediately

|

Can Tho - In the initial phase, the expressway will not collect tolls, vehicles are allowed to circulate normally.

Workers' Month - Trade Union levels will strongly shift from movements to practical results

|

Implementing the policy of the Secretariat of the Party Central Committee to take May every year as Workers' Month, after 15 years of implementation, every year, activities in Workers' Month are innovated with many practical models, meeting the needs and desires of workers.

Standing Deputy Prime Minister gives gifts to workers and policy families in Quang Ninh

|

Quang Ninh - On April 30, Standing Deputy Prime Minister Pham Gia Tuc visited and presented gifts to policy families and workers in difficult circumstances in Quang Ninh.

Hanoi people are excited to take free buses and trains during the April 30 - May 1 holiday

|

Hanoi - During the April 30 - May 1 holiday, Hanoi continues to exempt subsidized public passenger transport vehicles to reduce congestion and pollution.

Hanoi Zoo crowded with people on the first day of the 30th holiday

|

Hanoi - April 30, favorable weather made Hanoi Zoo (Thu Le Park) attract a large number of people and tourists to visit and play.

More than 1,300 delegates will attend the 11th Congress of the Vietnam Fatherland Front

|

The 11th Congress of the Vietnam Fatherland Front, term 2026-2031, will be held from May 11-13 at the National Convention Center, Hanoi Capital.

Workers stick to the construction site during holidays, keeping pace with Ring Road 1 progress

Hữu Vũ - Thiện Nhân |

Hanoi - During the holidays, the construction site of Ring Road 1 Hoang Cau - Voi Phuc still resonates with the sound of machinery, constructing day and night, determined to maintain project progress.

Morning of the Mekong Delta 30. 4: Officially open to traffic the entire Can Tho - Ca Mau expressway

Nhóm PV |

Morning of the Mekong Delta 30. 4: Officially open to traffic the entire Can Tho - Ca Mau expressway; Phu Quoc is ready to serve tourists during major holidays;...

Can Tho - Ca Mau expressway opens to traffic on the entire route from 11:30 am on April 29, tolls are not yet collected immediately

Tạ Quang |

Can Tho - In the initial phase, the expressway will not collect tolls, vehicles are allowed to circulate normally.