Bac Ninh names 5 projects causing great loss and waste

Trần Tuấn |

Bac Ninh - The Provincial People's Committee has just named 5 projects that are behind schedule, have long backlogs, and are ineffective, causing great loss and waste.

The People's Committee of Bac Ninh province has just issued an official dispatch on reviewing and reporting on projects and works that are behind schedule, have long-term backlogs, and are ineffective, causing great loss and waste.

Accordingly, the People's Committee of Bac Ninh province received an Official Dispatch dated March 4, 2025 from the Provincial Party Committee's Internal Affairs Committee on reporting the results of implementing the conclusions of the Central Steering Committee on preventing corruption, waste and negativity.

The Chairman of the People's Committee of Bac Ninh province assigned the Department of Construction and the Department of Agriculture and Environment to provide reporting information according to the outline in the Official Dispatch of the Provincial Party Committee's Internal Affairs Committee for projects that are behind schedule, have long-term backlogs, and are ineffective, causing great loss and waste; report to the Department of Finance no later than 9:00 a.m. on March 14, 2025.

Assign the Management Board of Industrial Parks to provide a report according to the outline in the Official Dispatch of the Provincial Party Committee's Internal Affairs Committee for investment projects in construction and business of Nhan Hoa, Phuong Lieu, and Que Vo small-scale industrial park infrastructure; report to the Department of Finance no later than 9:00 a.m. on March 14, 2025.

Assign the Tax Department of Region V to provide information on the implementation of financial obligations to the State of projects that are behind schedule, have long backlogs, and are ineffective, causing great loss and waste; report to the Department of Finance no later than 9:00 a.m. on March 14, 2025.

Assign the Department of Finance to preside over and coordinate with relevant units to review and report on works and projects that are behind schedule, have long backlogs, and are ineffective, causing great loss and waste, and public investment projects (according to the outline in the Official Dispatch of the Provincial Party Committee's Internal Affairs Committee); synthesize and report to the Provincial People's Committee and the Chairman of the Provincial People's Committee on March 14, 2025.

Accordingly, the projects that are behind schedule, have long backlogs, are ineffective, and cause loss and waste are named by the People's Committee of Bac Ninh province, including:

Automobile Service and Trading Center Project in Dong Ngo area, Dai Phuc ward, Bac Ninh city of Hai Au Trading and Finance Company Limited Branch in Bac Ninh province;

Project for Investment in Construction and Business of Infrastructure of Nhan Hoa, Phuong Lieu, Que Vo Industrial Parks and Industrial Parks of Nhan Hoa Urban Development Investment and Industrial Park Joint Stock Company;

Duc Viet General Urban and Service Area Project in Gia Dong Ward, Thuan Thanh Town of Duc Viet Group Joint Stock Company;

Investment project to build a scientific - Training complex of the Vietnam Economic Science Association; investment in building technical infrastructure for Den Dam Cultural Tourism Area, Tu Son Town under the investment form of Construction - Transfer (BT) of Solatech Investment Joint Stock Company;

The project to invest in the construction of a road along B2 canal, Tu Son town, Bac Ninh province (from the intersection with the new National Highway 3 to DT 295B), under the form of a Construction - Transfer Contract (BT).

Previously, in February 2025, Lao Dong Newspaper also published a series of articles: A series of projects behind schedule in Bac Ninh, reflecting that in addition to projects implemented on schedule, even exceeding the set schedule, in Bac Ninh province there are many projects, both public investment and private investment, that are behind schedule for a long time, not only affecting the goal of meeting the criteria of a type I urban area of the locality but also affecting the lives of many people.

Trần Tuấn
RELATED NEWS

Bac Ninh is about to celebrate the day King Ly Thai To was crowned emperor

|

Bac Ninh - The 1,015th anniversary of King Ly Thai To's coronation is scheduled to take place at 8:00 p.m. on April 11, 2025.

New direction of Bac Ninh on Gia Binh Airport project

|

Bac Ninh - The locality is coordinating to implement related procedures to serve the adjustment of the investment policy of the Gia Binh International Airport Project.

Bac Ninh, Bac Giang - the source of the quan ho flows forever

|

The ancient Kinh Bac, now Bac Ninh - Bac Giang, was divided by the Cau River. The residents on both sides of the river are famous for their rich, lyrical folk melodies.

Veterans review history on April 30

|

In the atmosphere of celebrating April 30th, veterans review memories and heroic history through wartime stories.

Cultural houses in Hanoi are packed with people sitting and listening to information about the 5,601 billion VND road project

|

Hanoi - Cultural houses in Phu Dien and Ta Thanh Oai villages (Dai Thanh commune) are crowded with people coming to hear information about land acquisition and site clearance for the Ring Road 3.5 project.

30. 4 box office: movie "Heo Nam Mong" loses top 1 position, "Trum So" exhausted

|

The Vietnamese film market during the April 30th holiday recorded vibrant developments. Among the 5 Vietnamese films released in theaters, "Heo Nam Mong" unexpectedly dropped from the top 1 box office position.

More than 1,300 delegates will attend the 11th Congress of the Vietnam Fatherland Front

|

The 11th Congress of the Vietnam Fatherland Front, term 2026-2031, will be held from May 11-13 at the National Convention Center, Hanoi Capital.

Bac Ninh is about to celebrate the day King Ly Thai To was crowned emperor

Vân Trường |

Bac Ninh - The 1,015th anniversary of King Ly Thai To's coronation is scheduled to take place at 8:00 p.m. on April 11, 2025.

New direction of Bac Ninh on Gia Binh Airport project

Vân Trường |

Bac Ninh - The locality is coordinating to implement related procedures to serve the adjustment of the investment policy of the Gia Binh International Airport Project.

Bac Ninh, Bac Giang - the source of the quan ho flows forever

Vân Trường |

The ancient Kinh Bac, now Bac Ninh - Bac Giang, was divided by the Cau River. The residents on both sides of the river are famous for their rich, lyrical folk melodies.