Discussing solutions to overcome landslides at Sa Pa BOT toll station

Đinh Đại |

Lao Cai - After nearly 3 months of serious landslides in the Sa Pa BOT Toll Station area, relevant units have met to discuss solutions.

Rocks and soil are scattered after nearly 3 months of landslides

On September 22, 2023, the route connecting Noi Bai - Lao Cai Expressway to Sa Pa was officially put into operation after 5 years of construction.

The route helps shorten the journey from the old Lao Cai city to Sa Pa by about 7 km, reducing travel time by 20 minutes and avoiding many dangerous turns.

However, heavy rain lasting from the night of June 30 to the morning of July 1 caused many landslides on Provincial Road 155 (Lao Cai - Sa Pa).

In particular, the section at Km12+600, National Highway 4D - location of Lao Cai - Sa Pa BOT Toll Station - was buried by rocks and soil, causing traffic disruption and damage to many construction items.

Toan canh diem sat tai tram thu phi BOT Sa Pa. Anh: Dinh Dai
Panorama of the landslide at the Sa Pa BOT toll station. Photo: Dinh Dai

In mid-September, reporters from Lao Dong Newspaper were present at the scene to continue recording the scene of devastation when thousands of cubic meters of soil and rock spilled down to the toll station, burying the area of the operator's house, toll equipment and spilled down to National Highway 4D.

However, the clearing of soil and rocks has not been implemented due to problems in compensation for crops for people.

According to the reflection, people in Ta Phin commune believe that the cause of the landslide originated from the embankment construction process, causing the production land below to be "lost", causing landslides and buried crops.

In 2024, similar landslides occurred, but compensation has not been fully implemented. Therefore, the people are determined not to let the construction unit handle the soil and rocks until there is a clear compensation plan.

Gan 3 thang sau sat lo, dat da chua the hot don vi nguoi dan khong dong tinh. Anh: Dinh Dai
Nearly 3 months after the landslide, the rocks and soil cannot be cleared because the people do not agree. Photo: Dinh Dai

Along with that, the landslide at the toll station that has not been repaired is also the reason why Mong Sen Bridge has been temporarily suspended for many months.

The landslide not only caused property damage but also interrupted traffic to Sa Pa tourist area. Therefore, many people hope that the units will soon clear the rocks and soil so that traffic can return to normal.

Mr. Nguyen Duc Duong (driver on the Hanoi - Sa Pa route) shared: "After the landslide, drivers had to take longer and longer on National Highway 4D. Not to mention, the road below is not safe during storms because landslides can flow down from above at any time".

Cac phuong tien luu thong phia duoi Quoc lo 4D. Anh: Dinh Dai
Vehicles traveling below National Highway 4D. Photo: Dinh Dai

Land reclamation in landslide areas

Recently, after the relevant agencies held a meeting with the people, they agreed on a plan to implement landslide clearance.

Talking with Lao Dong, Mr. Vu Xuan Quy - Chairman of Ta Phin Commune People's Committee - said that after departments, local authorities and people sat down to solve the problem, they came up with a plan to reclaim land in the landslide area and compensate people to overcome the landslide.

"Currently, most people agree with the plan to reclaim land and receive compensation. Therefore, we are sending people to count, measure and count the damage and recovered land area, trying to complete before September 20 to report to Lao Cai Provincial People's Committee," said the Chairman of Ta Phin Commune People's Committee.

Tram thu phi sat lo va chua the khac phuc cung la nguyen nhan khien cac phuong tien khong the luu thong qua cau Mong Sen. Anh: Dinh Dai
The landslide toll station and cannot be repaired is also the reason why vehicles cannot travel through Mong Sen Bridge. Photo: Dinh Dai

As the unit directly exploiting the toll station, according to the leader of Lao Cai - Sa Pa BOT Investment Joint Stock Company, for nearly 3 peak months last summer when the station could not operate, while waiting for a solution, the unit lost about 6 billion VND.

"This is an impact of natural disasters and Lao Cai province has declared an emergency, so the funding source will be paid by the province, the recovered land will be handed over to the commune for management so that there will be a stable reinforcement plan later," said Mr. Nguyen Quang Luu, Deputy General Director of Lao Cai - Sa Pa BOT Investment Joint Stock Company.

Lanh dao Cong ty CP Dau tu BOT Lao Cai – Sa Pa mong muon som khac phuc sat lo de dua tram thu phi hoat dong tro lai. Anh: Dinh Dai
It is expected that by September 20, the management unit will complete the counting to proceed with landslide repair, and soon put the toll station back into operation. Photo: Dinh Dai
Đinh Đại
RELATED NEWS

Spectacular escape car in landslide at Sa Pa toll station

|

Lao Cai - Rocks and soil at Sa Pa BOT station continue to overflow onto National Highway 4D, causing traffic congestion.

Declaring a natural disaster emergency at the Sa Pa BOT station area

|

Lao Cai - The Provincial People's Committee has just announced a natural disaster emergency at the landslide site of the Sa Pa BOT toll station due to the impact of heavy rains.

Landslide at Sa Pa BOT station causes traffic disruption

|

Lao Cai - Due to prolonged heavy rain, landslides appeared in the section passing through Sa Pa BOT station, causing traffic disruption.

A80 exhibition welcomes record 8.6 million visitors

|

The 80th National Achievement Exhibition at the Vietnam Exhibition Center (Dong Anh, Hanoi) welcomed nearly 8.6 million visitors after 17 days of opening.

Proposal on asset and income verification activities when amending the Law on Anti-Corruption

|

The draft Law has new proposals on the content of asset and income verification activities to overcome many current shortcomings.

Russia declares to ensure the highest security if Mr. Zelensky arrives in Moscow

|

Russia has said it will ensure the highest level of security for Ukrainian President Volodymyr Zelensky if he accepts to Moscow to meet President Vladimir Putin.

Officials are absolutely not required to present integrated documents on VNeID

|

Officials, civil servants and public employees are absolutely not required to submit or present documents integrated on VNeID or in a connected database.

Motorcycle collides with tanker truck crossing the road in Lam Dong, killing 2 people

|

Lam Dong - A motorbike collided with a tanker truck crossing the road on National Highway 1, causing 2 motorcyclists to die on the spot.

Spectacular escape car in landslide at Sa Pa toll station

Đinh Đại |

Lao Cai - Rocks and soil at Sa Pa BOT station continue to overflow onto National Highway 4D, causing traffic congestion.

Declaring a natural disaster emergency at the Sa Pa BOT station area

Đinh Đại |

Lao Cai - The Provincial People's Committee has just announced a natural disaster emergency at the landslide site of the Sa Pa BOT toll station due to the impact of heavy rains.

Landslide at Sa Pa BOT station causes traffic disruption

Đinh Đại |

Lao Cai - Due to prolonged heavy rain, landslides appeared in the section passing through Sa Pa BOT station, causing traffic disruption.