Lao Dong Newspaper warns of capital increase for coastal road project before inspection conclusion

HƯNG THƠ |

Quang Tri - Before the Government Inspectorate pointed out violations, Lao Dong Newspaper reported abnormalities in the proposal to adjust and increase capital in the coastal road project.

Lao Dong Newspaper points out early abnormalities

According to Inspection Conclusion Notice No. 3436/TB-TTCP dated December 26, 2025, the Government Inspectorate determined that the coastal road project connecting the East-West economic corridor in Quang Tri was behind schedule, violated the Bidding Law and revealed many shortcomings in the preparation, appraisal, approval as well as adjustment of investment policies and total investment.

The project has a total length of nearly 55km, of which phase 1 is more than 48km long. The initial approved total investment is 2,060 billion VND. However, after the implementation process, the project was adjusted to increase to 2,731 billion VND, an increase of more than 671 billion VND, while extending the implementation time to 2027. The Government Inspectorate assessed that this adjustment is not sufficient basis, especially in the context of difficult balancing of medium-term public investment capital in the 2026-2030 period.

Notably, more than a year before the inspection conclusion, in October 2024, Lao Dong Newspaper published an article "Proposal to increase 570 billion VND for the traffic road project, very difficult". The article clearly stated that the Investment and Construction Project Management Board of Quang Tri province proposed to adjust the total investment of the project to more than 2,630 billion VND, an increase of more than 570 billion VND compared to the initial approval, with the reason that many incurred costs are higher than the estimate.

Du an dang day nhanh tien do thi cong va khac phuc cac sai pham. Anh: Hung Tho
The project is accelerating construction progress and overcoming violations. Photo: Hung Tho

Right at that time, the Provincial Department of Planning and Investment (now the Department of Finance) expressed a cautious view, saying that the increased capital level was very large, putting pressure on the local budget balance.

After the inspection conclusion, the project is accelerated.

The Construction Investment Project Management Board of Quang Tri province said that it is focusing on accelerating the construction progress and overcoming the existing problems that have been pointed out.

Currently, all 4 construction packages have been implemented simultaneously. The total value of implementation reached more than 676 billion VND out of a total of 1,616 billion VND of construction value, equivalent to about 41.8%. Land clearance work has handed over more than 42km out of a total of 48km, reaching about 88%. The remaining area is expected to be completed in the first quarter of 2026.

Khu tai dinh cu Trieu Do phuc vu du an duong ven bien gan hoan thien. Anh: Hung Tho
Trieu Do resettlement area serving the near-completed coastal road project. Photo: Hung Tho

One of the biggest "blocks" of the project that Lao Dong Newspaper once reflected is site clearance and resettlement work. The Government Inspectorate determined that the feasibility study report did not fully determine the workload to calculate the cost of site clearance correctly and fully, leading to a lack of capital, forcing adjustments to increase the total investment. In fact, many households have to relocate and temporarily reside while resettlement areas are not completed, directly affecting the project progress.

According to the Quang Tri Provincial Construction Investment Project Management Board, so far only the resettlement area in Nam Dong Ha ward has been completed. The remaining areas are being urgently deployed, many areas reaching from 60% to 90% of the volume, expected to be completed by the end of 2025 and early 2026. The investor said that he has sent officials to closely monitor the area, coordinate with local authorities to remove obstacles regarding land origin, relocate technical infrastructure and mobilize people to hand over land.

Regarding construction, many important items such as large bridges, roadbeds, and drainage culverts are being implemented in parallel. Some bidding packages have achieved a implementation rate of over 50%, showing efforts to accelerate after a long period of delay.

It's a bit of a bit of a bit of a bit of a bit of a bit.

HƯNG THƠ
RELATED NEWS

Many violations at the Coastal Road Project connecting the East-West Economic Corridor

|

The Government Inspectorate pointed out many violations in the Coastal Road Project connecting the East-West Economic Corridor, Quang Tri province.

From piles of rubble to new roofs in Nam Tra My, Da Nang

|

Da Nang - 157 landslide points, hundreds of households affected. From the rubble after floods, new roofs are gradually appearing in Nam Tra My.

Explaining why many headquarters in Nghe An were handed over but are slow to operate

|

Nghe An - Many headquarters have been transferred to receiving units but are slow to operate because they are completing legal procedures, usage plans and functional conversion.

Trade union introduces jobs to thousands of workers at Panko Vina Company

|

The Ho Chi Minh City Trade Union is connecting businesses that need recruitment to introduce jobs to workers at Panko Vina Co., Ltd.

Expressways and ring roads race to connect Long Thanh airport

|

Dong Nai - Component 1 project of Bien Hoa - Vung Tau expressway connecting Long Thanh airport strives to technically open to traffic before the Lunar New Year 2026.

The Ministry of Finance has transferred money to localities to deploy Tet gifts

|

The Ministry of Finance said that it has transferred funds for localities to implement giving Tet Nguyen Dan Binh Ngo 2026 gifts to subjects according to regulations.

Social networks are not required to provide personal papers as an authentication factor

|

From January 1, 2026, social networks are not required to have personal papers to verify accounts and are not allowed to eavesdrop, read messages, or record without consent.

Many violations at the Coastal Road Project connecting the East-West Economic Corridor

TRÍ MINH |

The Government Inspectorate pointed out many violations in the Coastal Road Project connecting the East-West Economic Corridor, Quang Tri province.

Đề xuất tăng 570 tỉ đồng cho dự án đường giao thông, rất khó

HƯNG THƠ |

Quảng Trị - Liên quan dự án đường giao thông bỏ quên khu tái định cư, sau khi khái toán thì đề xuất tăng 570 tỉ đồng so với tổng mức đầu tư được phê duyệt.

Dự án đường giao thông ngàn tỉ bỏ quên khu tái định cư

HƯNG THƠ |

Quảng Trị - Người dân khăn gói đi tạm cư, nhường nhà và đất làm dự án đường giao thông. Nhưng hiện khu tái định cư chưa biết lấy vốn ở đâu để xây dựng.