Road and underpass expansion projects in Hanoi to be completed in 2027

SÓNG HỮU |

Hanoi - The project to expand National Highway 6, Ba La - Xuan Mai section, and the Co Linh intersection underpass project will be completed in 2027.

Regarding the National Highway 6 expansion project, Ba La - Xuan Mai section, to date, many localities have completed site clearance and handed it over to construction units to implement the project. Some communes and wards that have not been completed are urgently speeding up progress.

In Chuong My ward, as of July 6, the locality has completed site clearance and handed over 21.05 hectares to the investor, reaching 99.8% of the total recovered area to implement the project of renovating and upgrading National Highway 6, Ba La - Xuan Mai section.

For the remaining cases, the Steering Committee, working groups and related forces continue to closely monitor the area, strengthen propaganda, mobilization, and dialogue to remove each difficulty and obstacle, striving to complete the site clearance work as soon as possible.

s
Information about the project to expand National Highway 6, Ba La - Xuan Mai section. Graphics: AI

In Xuan Mai commune, the total area of land recovered for project implementation is 38.58 ha with 1,804 land plots, related to about 1,376 households and individuals.

The commune government is continuing to propagate, mobilize, and dialogue to help people better understand the mechanisms and policies for compensation and support for land, assets on land and resettlement, thereby contributing to strengthening consensus among the people, creating favorable conditions to accelerate the progress of site clearance, serving the implementation of the project to renovate and upgrade National Highway 6 according to the set plan.

Cầu Mai Lĩnh trên tuyến Quốc lộ 6 đang được xây dựng. Ảnh: Sóng Hữu
Mai Linh bridge on National Highway 6 is under construction. Photo: Song Huu

At the Co Linh intersection underpass construction investment project, after nearly 9 months from the commencement date, the project has achieved over 75% of the workload.

According to the contract, the project will be completed in December 2027. However, the city has requested to shorten the progress, striving to open to traffic before the Dinh Mui Lunar New Year and complete the entire project in April 2027.

s
Overview of the Co Linh intersection underpass project. Graphics: AI

For the National Highway 21B expansion project, currently, 6.25km of the entire route has been completed and put into operation; 16.64km is being invested, including the section from provincial road 427 to Kim Bai town, 2.7km long, invested by Thanh Oai Commune People's Committee.

The project has a total investment of about 345.5 billion VND, implemented in the period 2020 - 2026.

The biggest bottleneck that the project has encountered for a long time is site clearance work, including a section of about 310m through Ba Hang Mai area (My Thuong village) and a section of about 320m through Cau Chuong hamlet (Tan Kieu village), involving more than 120 households and individuals.

Identifying site clearance as a key political task, Thanh Oai commune has mobilized the involvement of the entire political system; strengthened propaganda, dialogue, and mobilization of the people.

Khu vực Ba Hàng Mai (xã Thanh Oai) đã được giải phóng mặt bằng. Ảnh: Trang tin điện tử xã Thanh Oai
Ba Hang Mai area (Thanh Oai commune) has been cleared. Photo: Thanh Oai commune electronic information page

During the peak campaign, 90 households and individuals in the Ba Hang Mai area (My Thuong village) handed over the site, coordinated to complete the dismantling of 96 works, houses and assets on land; 28 households and individuals in the Cau Chuong hamlet area (Tan Kieu village) have handed over the site, functional forces are continuing to dismantle 32 works according to the plan.

Meanwhile, in Dan Hoa commune, the project to expand National Highway 21B through the area is about 2km long.

Mr. Mai Xuan Truong - Secretary of the Party Committee, Chairman of the People's Council of Dan Hoa commune - requested functional forces to closely monitor the area, strengthen propaganda, mobilization, and direct dialogue with the people to create consensus. At the same time, it is necessary to ensure the legitimate and lawful rights and interests of the people in accordance with the law.

Mr. Truong also requested the Investment - Infrastructure Project Management Board of the commune to urgently coordinate with the People's Committee of Binh Minh commune to carry out capital allocation procedures, and soon organize the payment of compensation and support money to households that have had approval decisions.

SÓNG HỮU
RELATED NEWS

Complete site clearance for the most complex area of the 345.5 billion VND project in Hanoi

|

Hanoi - Thanh Oai commune has completed site clearance for the National Highway 21B expansion project, with a total investment of about 345.5 billion VND.

Complete site clearance, urgently construct a 795-billion VND intersection in Hanoi

|

Hanoi - The Pham Tu - Road 70 intersection project has completed site clearance after many years of obstacles, and construction work is being accelerated by the contractor.

Final sprint for site clearance of National Highway 6 project, coercion will be applied in cases of non-compliance with land allocation

|

Hanoi - Phu Nghia commune is accelerating the progress of land recovery for the National Highway 6 expansion project, and will enforce cases of intentionally failing to comply with site handover.

benchmark scores for History Pedagogy in the past two years

|

The benchmark scores for History Pedagogy majors at universities have fluctuated sharply in the past two years.

Ministry of Construction clarifies the validity of social housing purchase income confirmation paper

|

The Ministry of Construction has just clarified the regulations on income confirmation papers for workers transferring jobs before the time of submitting applications to register to buy social housing.

Gasoline and oil prices decrease but commodity and service prices remain unchanged

|

Gasoline and oil prices have been continuously adjusted down in recent times, but the prices of many goods and services in Hanoi have not shown signs of cooling down.

Tears of the CEO behind The Brother Who Overcame Thousands of Thorns

|

After only 2 episodes of season 2, the hot debates of the audience have brought "Anh Trai Vuot Ngan Chong Gai" into an unprecedented crisis.

Fire in Con market in Quang Tri, fire spreads to 4 goods kiosks

|

Quang Tri - Cho Con market in Dong Son ward caught fire, functional forces quickly controlled it, 4 goods kiosks were burned.

Complete site clearance for the most complex area of the 345.5 billion VND project in Hanoi

SÓNG HỮU |

Hanoi - Thanh Oai commune has completed site clearance for the National Highway 21B expansion project, with a total investment of about 345.5 billion VND.

Complete site clearance, urgently construct a 795-billion VND intersection in Hanoi

SÓNG HỮU |

Hanoi - The Pham Tu - Road 70 intersection project has completed site clearance after many years of obstacles, and construction work is being accelerated by the contractor.

Final sprint for site clearance of National Highway 6 project, coercion will be applied in cases of non-compliance with land allocation

SÓNG HỮU |

Hanoi - Phu Nghia commune is accelerating the progress of land recovery for the National Highway 6 expansion project, and will enforce cases of intentionally failing to comply with site handover.