Regarding the National Highway 6 expansion project, Ba La - Xuan Mai section, to date, many localities have completed site clearance and handed it over to construction units to implement the project. Some communes and wards that have not been completed are urgently speeding up progress.
In Chuong My ward, as of July 6, the locality has completed site clearance and handed over 21.05 hectares to the investor, reaching 99.8% of the total recovered area to implement the project of renovating and upgrading National Highway 6, Ba La - Xuan Mai section.
For the remaining cases, the Steering Committee, working groups and related forces continue to closely monitor the area, strengthen propaganda, mobilization, and dialogue to remove each difficulty and obstacle, striving to complete the site clearance work as soon as possible.

In Xuan Mai commune, the total area of land recovered for project implementation is 38.58 ha with 1,804 land plots, related to about 1,376 households and individuals.
The commune government is continuing to propagate, mobilize, and dialogue to help people better understand the mechanisms and policies for compensation and support for land, assets on land and resettlement, thereby contributing to strengthening consensus among the people, creating favorable conditions to accelerate the progress of site clearance, serving the implementation of the project to renovate and upgrade National Highway 6 according to the set plan.

At the Co Linh intersection underpass construction investment project, after nearly 9 months from the commencement date, the project has achieved over 75% of the workload.
According to the contract, the project will be completed in December 2027. However, the city has requested to shorten the progress, striving to open to traffic before the Dinh Mui Lunar New Year and complete the entire project in April 2027.

For the National Highway 21B expansion project, currently, 6.25km of the entire route has been completed and put into operation; 16.64km is being invested, including the section from provincial road 427 to Kim Bai town, 2.7km long, invested by Thanh Oai Commune People's Committee.
The project has a total investment of about 345.5 billion VND, implemented in the period 2020 - 2026.
The biggest bottleneck that the project has encountered for a long time is site clearance work, including a section of about 310m through Ba Hang Mai area (My Thuong village) and a section of about 320m through Cau Chuong hamlet (Tan Kieu village), involving more than 120 households and individuals.
Identifying site clearance as a key political task, Thanh Oai commune has mobilized the involvement of the entire political system; strengthened propaganda, dialogue, and mobilization of the people.

During the peak campaign, 90 households and individuals in the Ba Hang Mai area (My Thuong village) handed over the site, coordinated to complete the dismantling of 96 works, houses and assets on land; 28 households and individuals in the Cau Chuong hamlet area (Tan Kieu village) have handed over the site, functional forces are continuing to dismantle 32 works according to the plan.
Meanwhile, in Dan Hoa commune, the project to expand National Highway 21B through the area is about 2km long.
Mr. Mai Xuan Truong - Secretary of the Party Committee, Chairman of the People's Council of Dan Hoa commune - requested functional forces to closely monitor the area, strengthen propaganda, mobilization, and direct dialogue with the people to create consensus. At the same time, it is necessary to ensure the legitimate and lawful rights and interests of the people in accordance with the law.
Mr. Truong also requested the Investment - Infrastructure Project Management Board of the commune to urgently coordinate with the People's Committee of Binh Minh commune to carry out capital allocation procedures, and soon organize the payment of compensation and support money to households that have had approval decisions.