Close-up of the lotus-shaped lighting roof system at Long Thanh airport terminal

HÀ ANH CHIẾN |

Dong Nai - Long Thanh airport passenger terminal center with a lotus-shaped light-taking roof system is gradually being completed, creating a unique architectural highlight.

On July 20, according to Vietnam Airports Corporation (ACV), package No. 5, 10 - Construction and installation of equipment for the Long Thanh airport passenger terminal has reached a volume of about 67.08% compared to the contract value.

In which, the reinforced concrete structure of the underground part, 1st, 2nd, 3rd and 4th floors; steel roof structure (central roof area, wings area, telescopic bridge area, elevation support frame, maintenance frame, roof frame support frame...) and the roof layers of the terminal - have been completed.

The highlight is that in the central area of Long Thanh airport passenger terminal, the aluminum ceiling system for taking light is gradually being completed, creating a unique architectural highlight.

According to ACV, the roof of Long Thanh airport passenger terminal is designed with soft, elegant lines, recreating the image of a blooming lotus.

When completed, the lotus-shaped light-taking roof system will not only contribute to creating a modern, airy and naturally lit architectural space, but also become an identity mark imbued with Vietnamese identity of Long Thanh airport passenger terminal.

Lotus flower imprint on the roof system illuminating the center of Long Thanh airport passenger terminal:

Hệ trần nhôm áp mái lấy sáng nhà ga hành khách sân bay Long Thành đang dần hoàn thiện. Ảnh:
The aluminum ceiling roof system for lighting the Long Thanh airport passenger terminal is gradually being completed. Photo: Airports Corporation of Vietnam (ACV)
Phối cảnh hệ trần nhôm áp mái lấy sáng nhà ga hành khách sân bay Long Thành sau khi hoàn thiện. Ảnh: ACV
Perspective of the aluminum ceiling roof system to illuminate Long Thanh airport passenger terminal after completion. Photo: Airports Corporation of Vietnam (ACV)
Không chỉ đưa ánh sáng tự nhiên lan tỏa vào không gian bên trong nhà ga, công trình còn góp phần tạo nên bầu không khí thông thoáng, dễ chịu, mang đến trải nghiệm thoải mái hơn cho hành khách trong suốt hành trình.
Not only bringing natural light to the space inside the terminal, the project also contributes to creating a fresh, pleasant atmosphere, bringing a more comfortable experience to passengers throughout the journey. Photo: Airports Corporation of Vietnam (ACV)
Hiện nay, các đơn vị thi công đang tập trung hoàn thiện công tác định vị, liên kết và xử lý những chi tiết cuối cùng trước khi hoàn chỉnh toàn bộ hệ mái.
Currently, construction units are focusing on completing positioning, linking and handling the final details before completing the entire roof system. Photo: Airports Corporation of Vietnam (ACV)
Với tổng diện tích gần 10.000 m², hệ trần gồm 345 cấu kiện có hình dáng và kết cấu phức tạp, được lắp ghép tỉ mỉ để tạo hình hoa sen tại khu vực trung tâm nhà ga.
With a total area of nearly 10,000 m2, the ceiling system consists of 345 components with complex shapes and structures, meticulously assembled to create lotus shapes in the central area of the terminal. Photo: Airports Corporation of Vietnam (ACV)
Công tác thi công được triển khai ở độ cao hơn 20m, sử dụng hệ giàn giáo gantry kết hợp với nhiều thiết bị nâng chuyên dụng, đòi hỏi sự phối hợp chặt chẽ, chính xác và tuân thủ nghiêm ngặt các yêu cầu về kỹ thuật, chất lượng cũng như an toàn lao động.
Construction work is deployed at an altitude of over 20m, using gantry scaffolding combined with many specialized lift equipment, requiring close coordination, accuracy and strict compliance with technical requirements, quality as well as labor safety. Photo: Airports Corporation of Vietnam (ACV)
Gói thầu số 5.10 - Thi công xây dựng và lắp đặt thiết bị công trình nhà ga hành khách sân bay Long Thành đã đạt khối lượng khoảng 67,08% so với giá trị hợp đồng.
Officials, engineers, and workers are working urgently, counting down every day the project is completed. Photo: Airports Corporation of Vietnam (ACV)
Ngoài ra, cũng tại gói thầu 5.10, thi công lắp đặt các hạng mục cơ điện đạt khoảng 92%, công tác lắp đặt hệ thống thiết bị nhà ga, đạt khoảng 62,1%.
At package 5.10, the construction and installation of electromechanical items reached about 92%, and the installation of terminal equipment system reached about 62.1%. Photo: Airports Corporation of Vietnam (ACV)
Toàn cảnh dự án sân bay Long Thành sẽ đưa vào vận hành khai thác thương mại vào tháng 12.2026. Ảnh: Tổng Công ty Cảng hàng không Việt Nam (ACV)
Long Thanh Airport will be put into commercial operation in December 2026. Photo: Airports Corporation of Vietnam (ACV)

According to the schedule, package 5.10 will basically complete all items and put into trial operation phases from September 2026 and commercial operation in December 2026.

HÀ ANH CHIẾN
RELATED NEWS

Ho Chi Minh City accelerates land acquisition to extend Metro Line 1 to Long Thanh airport

|

Ho Chi Minh City urgently recovers land to implement the project to extend Metro Line 1 to Dong Nai City and Long Thanh airport, with a total capital of more than 65,500 billion VND.

Perspective of the road connecting Long Thanh airport passing through 9 communes and wards in Dong Nai

|

Dong Nai - The DT. 770B road construction project, more than 42km long, is a key traffic project of the city, connecting Long Thanh airport.

3 roads connecting Long Thanh airport to complete site clearance before September 30th

|

Dong Nai - Projects of DT. 769 road, DT. 773 road and DT. 770B road connecting Long Thanh airport to complete site clearance (GPMB) before September 30.

Dong Nai expands 2 traffic routes connecting Long Thanh airport to 4-8 lanes

|

Dong Nai - On July 10, the City (TP) organized the groundbreaking ceremony for the investment project to upgrade and expand 2 roads DT. 769 and DT. 773.

Workers hope for wage increase and price restraint

|

Hanoi - Workers are excited when the regional minimum wage for 2027 is proposed to increase by 7.8%, but also hope to restrain the price increase of essential goods.

Parking lot fire in Nam Nha Trang, many cars burned down in the night

|

Khanh Hoa - A fire occurred at a parking lot in Nam Nha Trang ward at night, causing damage to many cars.

Ho Chi Minh City accelerates land acquisition to extend Metro Line 1 to Long Thanh airport

MINH QUÂN |

Ho Chi Minh City urgently recovers land to implement the project to extend Metro Line 1 to Dong Nai City and Long Thanh airport, with a total capital of more than 65,500 billion VND.

Perspective of the road connecting Long Thanh airport passing through 9 communes and wards in Dong Nai

HÀ ANH CHIẾN |

Dong Nai - The DT. 770B road construction project, more than 42km long, is a key traffic project of the city, connecting Long Thanh airport.

3 roads connecting Long Thanh airport to complete site clearance before September 30th

HÀ ANH CHIẾN |

Dong Nai - Projects of DT. 769 road, DT. 773 road and DT. 770B road connecting Long Thanh airport to complete site clearance (GPMB) before September 30.

Dong Nai expands 2 traffic routes connecting Long Thanh airport to 4-8 lanes

HÀ ANH CHIẾN |

Dong Nai - On July 10, the City (TP) organized the groundbreaking ceremony for the investment project to upgrade and expand 2 roads DT. 769 and DT. 773.