3 roads connecting Long Thanh airport to complete site clearance before September 30th

HÀ ANH CHIẾN |

Dong Nai - Projects of DT. 769 road, DT. 773 road and DT. 770B road connecting Long Thanh airport to complete site clearance (GPMB) before September 30.

On July 16, according to the Dong Nai City Land Fund Development Center, the project to expand DT. 769 road, expand DT. 773 road and the project to build DT. 770B road started the compensation and site clearance work from March 2026, to date ensuring the set progress and will be completed before September 30, 2026.

The investment project to upgrade and expand DT. 769 road has a total length of 29.75km with a total construction investment of nearly 2,800 billion VND, passing through 3 communes and wards including: Dau Giay, Binh An, Long Thanh; is a vital traffic route serving the transportation of goods from the Northern and Central Highlands provinces to Long Thanh, Nhon Trach areas and vice versa.

The project to upgrade and expand DT. 773 route has a total infrastructure investment of more than 2,500 billion VND, with a length of about 36.6km, passing through communes and wards: Xuan Hoa, Xuan Loc, Xuan Phu, Xuan Dong, Cam My, Xuan Duong; the project creates connectivity, shortens travel time from the above-mentioned communes and wards to Long Thanh airport and Xuan Que - Song Nhan Industrial Park; reduces the load on National Highway 1.

The DT. 770B Road Construction Project passes through 9 communes and wards including: Xuan Bac, Gia Kiem, Xuan Que, Xuan Duong, Long Phuoc, Phuoc Thai, Dau Giay, Binh Loc, Xuan Lap. The project has a total length of about 42.7km, a total investment of 4,704 billion VND, connecting the northern and eastern areas of the city with National Highway 51, with expressways, industrial parks, logistics centers and especially Long Thanh airport.

Previously, on July 10, three transportation projects connecting Long Thanh airport mentioned above were started construction.

HÀ ANH CHIẾN
RELATED NEWS

Site clearance for a 19km long drainage project outside Long Thanh airport

|

Dong Nai - The drainage project outside Long Thanh airport (phase 1) will complete site clearance in December 2026.

Dong Nai expands 2 traffic routes connecting Long Thanh airport to 4-8 lanes

|

Dong Nai - On July 10, the City (TP) organized the groundbreaking ceremony for the investment project to upgrade and expand 2 roads DT. 769 and DT. 773.

Close-up of 2 traffic routes connecting Long Thanh airport under construction

|

Dong Nai - Package 6. 12 - The transportation system connecting Long Thanh airport has basically completed the main items and is focusing on completion.

Considering the option of 2 Metro lines from Ho Chi Minh City to Dong Nai and Long Thanh airport

|

Dong Nai considers the Ben Thanh - Suoi Tien Metro project to the City Administrative Center and Long Thanh airport; Thu Thiem - Long Thanh urban railway project.

Russia launches anti-UAV system to protect industrial facilities

|

The Russian state-owned technology corporation (Rostec) has launched a system to protect industrial infrastructure from UAV attacks.

Vietnam Social Security requests review of cases of late payment of pensions and allowances over 6 months

|

Vietnam Social Security has just requested a review of cases of late payment of pensions and allowances for more than 6 months, after Lao Dong Newspaper reflected on an old woman who has not received allowances for 5 years.

Fining driver of blue license plate car for reckless overtaking in Son La after reflection on social networks

|

Son La - A driver driving a blue license plate car has been fined after reflecting reckless overtaking on social networks.

Freedom of speech is not a "passport" to legitimize incitement

|

Freedom of speech is not a "passport" to legitimize acts of slandering others, fabricating information or inciting public opinion.