Dong Nai - The drainage project outside Long Thanh airport (phase 1) will complete site clearance in December 2026.

On July 16, according to the Dong Nai City Land Fund Development Center, the drainage project outside Long Thanh airport (phase 1) started the compensation and site clearance work in July 2026 and will be completed in December 2026.

The drainage project outside Long Thanh airport includes 2 component projects: The drainage project in the area outside Long Thanh airport (phase 1), invested by Area 5 Project Management Board, with a total investment of more than 836 billion VND, and the compensation, support, and resettlement project for investment and construction of drainage in the area outside Long Thanh airport (phase 1), invested by the City Land Fund Development Center - Long Thanh branch, with a total investment of more than 436 billion VND.

According to Dong Nai City People's Committee, the drainage project in the area outside Long Thanh airport will be started in October 2026. The total length of the Long Thanh airport drainage line (phase 1) is about 19km, including 2 drainage lines: Bung Mon stream about 12km long and Da Vang stream about 7km long. Regarding the scale of implementation, the project will construct dredging and reinforcing embankments, service roads, sidewalks, and green trees.

In which, Bung Mon stream is the main drainage route for regulating lakes No. 2 and No. 3; Da Vang stream is the drainage route for regulating lakes No. 4 and No. 5 of Long Thanh airport.

According to the Project Management Board of Area 5, the overall drainage plan, rainfall in the Long Thanh airport project area will be discharged into the existing surrounding drainage system (sweets, canals or rivers). Meanwhile, the area along the Long Thanh airport and on the main drainage routes in the area often experiences flooding in the rainy season, because the existing drainage works have smaller capacity than reality or are silted up and do not meet the designed operating capacity.

The drainage project in the area outside Long Thanh airport (phase 1) is being implemented, so it is very necessary, making an important contribution to the efficiency of the Long Thanh airport project. At the same time, the project contributes to strengthening the drainage capacity for the basin area of about 3,836 ha, including the Bung Mon stream basin area of about 2,698 ha and the Da Vang stream basin area of about 1,138 ha in the area along Long Thanh airport, Long Thanh ward and Long Phuoc commune.

HÀ ANH CHIẾN
RELATED NEWS

Answering questions about value-added tax calculation when compensating for site clearance

|

Readers expressed their concerns about the method of calculating value-added tax when implementing site clearance compensation.

Project of over 8,500 billion VND in Hai Phong still entangled in site clearance

|

Hai Phong - The investment project to build Ring Road 2 section Tan Vu - Hung Dao - Bui Vien road is still facing problems with site clearance.

Dong Nai: Units that delay site clearance will be evaluated by KPI

|

Answering about the progress of site clearance for key projects, Vice Chairman of Dong Nai City People's Committee Ho Van Ha said that units that are slow will be evaluated by KPI.

Main complaints regarding land, compensation, and site clearance support

|

Gia Lai - Areas prone to lawsuits such as planning, land acquisition, compensation, support, resettlement...

Vietnam Social Security requests review of cases of late payment of pensions and allowances over 6 months

|

Vietnam Social Security has just requested a review of cases of late payment of pensions and allowances for more than 6 months, after Lao Dong Newspaper reflected on an old woman who has not received allowances for 5 years.

Fining driver of blue license plate car for reckless overtaking in Son La after reflection on social networks

|

Son La - A driver driving a blue license plate car has been fined after reflecting reckless overtaking on social networks.

US attacks, blocks oil tankers from entering Iranian port

|

The US military announced that it had neutralized a tanker after accusing the ship of repeatedly ignoring warnings and trying to enter an Iranian port.

Lao Cai connects businesses, opens up development space from investment promotion conference

|

Lao Cai - Preparations for the Investment Promotion Conference have been completed, ready to welcome thousands of delegates and businesses seeking cooperation and investment opportunities.