Peak of site clearance for Gia Binh International Airport project

Vân Trường |

Bac Ninh - The peak period in the next 1.5 months will be to pay compensation to people subject to land acquisition to serve the Gia Binh International Airport project.

Minister of Construction Tran Hong Minh has just had a working session in Bac Ninh to resolve a number of provincial recommendations on the fields of the industry.

At the meeting, the Chairman of the People's Committee of Bac Ninh province affirmed the goal of Bac Ninh province to become a centrally-governed city by 2028 at the latest.

To achieve that goal, the province has positioned 11 contents for development in the new era, creating a breakthrough in development space.

In particular, the focus is on the Gia Binh International Airport project, Bac Ninh province is determined to implement the tasks assigned by the Government.

The province has launched an emulation movement to strive for 60 - 80 days and nights to focus on completing the site clearance (GPMB) of the entire agricultural land area; in parallel, resettlement work is being carried out with over 82,000 households.

Strive to receive the site to stabilize the house by 5-6 months at the latest; within 6 months from the date of site acquisition, the social infrastructure system will be completed.

At the peak in the next 1.5 months, compensation will be paid to the people.

To implement the adjustment of urban master planning, the Chairman of the Provincial People's Committee recommended that the Minister of Construction pay attention to promptly submitting to the Government to advise the National Assembly to issue a Resolution on urban classification. This is an important basis for the province to review and complete the criteria to become a centrally-governed city as soon as possible.

To implement the adjustment of urban master planning, the Chairman of the Provincial People's Committee recommended that the Minister of Construction pay attention to promptly submitting to the Government to advise the National Assembly to issue a Resolution on urban classification.

This is an important basis for the province to review and complete the criteria to become a centrally-governed city as soon as possible.

In the field of transportation, the Chairman of the Provincial People's Committee hopes that the Minister of Construction will pay attention to and direct the removal of difficulties in the Hanoi - Lang Son National Highway 1 project.

Directly discussing and answering the province's proposals and recommendations, Minister of Construction Tran Hong Minh agreed on 3 planning contents and will report to the Government on Rural Urban Planning; assigned the Department of Planning and Architecture to coordinate with localities to implement with a long-term vision, creating development momentum for the province.

Regarding urban development, the Minister of Construction also agreed with the locality and reported to the Government to advise the National Assembly to issue a Resolution on urban classification.

At the same time, he emphasized that in order to strive to meet the criteria of urban area I and become a centrally-governed city, Bac Ninh province needs to make efforts, try to review and focus on investing in each criterion.

Agreeing with the investment policy to expand the Hanoi - Bac Giang expressway, the Minister of Construction requested the Deputy Minister of Construction to direct agencies to coordinate with the province and investors to propose an investment plan, striving to start construction on December 19, 2025 or before the National Party Congress.

About 40 km from Hanoi, Gia Binh International Airport (Bac Ninh) started construction in December 2024 with a total area of nearly 1,900 hectares.

According to the plan, the airport will be basically completed and initially put into operation from the end of 2026 to serve the 2027 APEC Summit.

By 2050, the airport's capacity will reach about 50 million passengers/year and 2.5 million tons of cargo/year.

Vân Trường
RELATED NEWS

Standing team 24/24 deploys Gia Binh International Airport project

|

Bac Ninh - The locality established a 24/7 Standing Group to implement the Gia Binh International Airport Project and related projects.

Planning the airport urban area near Gia Binh International Airport

|

Bac Ninh - Nam Song Duong is positioned as a multi-functional airport urban area of international stature.

Put Gia Binh International Airport into operation in 2026

|

Bac Ninh - The locality aims to put Gia Binh International Airport and related routes into operation in 2026.

Officials are absolutely not required to present integrated documents on VNeID

|

Officials, civil servants and public employees are absolutely not required to submit or present documents integrated on VNeID or in a connected database.

Motorcycle collides with tanker truck crossing the road in Lam Dong, killing 2 people

|

Lam Dong - A motorbike collided with a tanker truck crossing the road on National Highway 1, causing 2 motorcyclists to die on the spot.

Mr. Trump issued a letter to NATO on resolving the Russia-Ukraine conflict

|

Mr. Trump said the US would only impose major sanctions on Russia if all of NATO followed suit and ended Russian oil imports.

Standing team 24/24 deploys Gia Binh International Airport project

Vân Trường |

Bac Ninh - The locality established a 24/7 Standing Group to implement the Gia Binh International Airport Project and related projects.

Planning the airport urban area near Gia Binh International Airport

Trần Tuấn |

Bac Ninh - Nam Song Duong is positioned as a multi-functional airport urban area of international stature.

Put Gia Binh International Airport into operation in 2026

Trần Tuấn |

Bac Ninh - The locality aims to put Gia Binh International Airport and related routes into operation in 2026.