Can Tho - Ca Mau Expressway seen from above has gradually taken shape

Tạ Quang |

Can Tho - Ca Mau Expressway has completed the handover of the entire route, reaching 100%. Construction has reached about 58%.

After more than 2 years of construction (from January 1, 2023), although the Can Tho - Ca Mau expressway project encountered many difficulties, under the strong direction of the Prime Minister, Deputy Prime Minister and ministries and branches, the project has had many positive changes, currently reaching about 58% of the contract value and expected to be completed by the end of 2025.

Nha thau dung cat bien de thi cong (Anh chup tai tinh Ca Mau). Anh: Ta Quang
Contractors use sea sand to construct highways (photo taken in Ca Mau province). Photo: Ta Quang

The project required 18 million cubic meters of sand for the foundation, but river sand was scarce, causing the project to be behind schedule. In early July 2024, the contractor used sea sand for construction, basically overcoming the shortage of materials.

Thiet bi may moc lu nen cat bien (Anh chup tai tinh Ca Mau). Anh: Ta Quang
Equipment for compacting beach sand (photo taken in Ca Mau province). Photo: Ta Quang

To speed up the progress, during the Lunar New Year 2025, many construction units will work day and night, making an important contribution to the construction of traffic infrastructure.

Tai nut giao IC5 da thanh hinh. Anh: Ta Quang
At the IC5 intersection has taken shape. Photo: Ta Quang

Mr. Nguyen Thanh Vinh - Deputy Director of Truong Son Nam Board (Truong Son Corporation) - said that during Tet, 4 bridge locations were focused on completing concrete pouring, beam installation, and 2 locations for sand and rock loading with about 150 employees.

According to the My Thuan Project Management Board (investor), during Tet, there were 234 construction teams and 2,881 personnel, along with 926 pieces of machinery and equipment. The main construction items were roadbed compaction, load-bearing embankment, curb and embankment construction, pile driving, girder placement, and concrete pouring of bridge deck.

Cong nhan, ky su miet mai lam viec. Anh: Ta Quang
Workers and engineers working hard. Photo: Ta Quang

Up to now, the main route from Can Tho to Hau Giang has been paved with asphalt concrete for the first 250m. Contractor Company 492 also constructed 130m of asphalt for the Hau Giang - Ca Mau route. The asphalt paving marks the transition from roadbed construction to highway surface completion.

Nut giao IC2 o Can Tho cung da thanh hinh. Anh: Ta Quang
IC2 intersection in Can Tho has also taken shape. Photo: Ta Quang

The Can Tho – Ca Mau Expressway is divided into two component projects, including the Can Tho – Hau Giang section and the Hau Giang – Ca Mau section, invested by the My Thuan Project Management Board. The total investment is more than VND 27,500 billion, including 4 construction packages (Can Tho – Hau Giang section has 1 package, Hau Giang – Ca Mau section has 3 packages), starting on January 1, 2023, scheduled to be completed by the end of 2025.

The Can Tho - Hau Giang and Hau Giang - Ca Mau sections have a main route length of 110.85km (through Can Tho city 0.6km, Hau Giang province 63.65km, Bac Lieu province 7.7km, Kien Giang province 17km, Ca Mau province 21.9km) and 25.85km of connecting route.

Tạ Quang
TIN LIÊN QUAN

Workers work through Tet on the North-South Expressway

|

Quang Binh - Even though it was the days before and during Lunar New Year, workers still stayed at the construction site, working through the holiday to ensure the progress of the expressway project.

"Sleepless" days and nights with Can Tho - Ca Mau expressway during Tet

|

Can Tho - In the days leading up to Lunar New Year 2025, engineers and workers are still working tirelessly day and night to construct the Can Tho - Ca Mau expressway.

Construction of Can Tho - Ca Mau Expressway day and night during Tet

|

While the whole country is busy preparing for Tet, engineers and workers are still working hard day and night on the Can Tho - Ca Mau expressway.

The program "95 years - Light to guide the way" is a symphony of faith

|

On the evening of February 3, a special art program celebrating the Party, celebrating Spring, and celebrating the country's renewal with the theme "95 years - Light to guide the way" took place in Hanoi.

8pm News: Deadline for completing the arrangement of redundant officials and civil servants

|

News at 8:00 p.m. on February 3: Deadline for completing the arrangement of redundant officials and civil servants; Arrest of brother-in-law who stabbed brother-in-law to death...

The contrasting financial picture of real estate businesses

|

Many real estate businesses have overcome difficulties and achieved quite good profits in 2024. However, many cases are still sinking in losses.

Confession of Barbie Hsu's husband before his wife's death

|

Barbie Hsu's Korean husband Koo Jun Yup spoke out about his wife's death in Japan. Their marriage lasted less than 3 years.

Why is Ha Giang suddenly crowded with tourists during Tet At Ty?

|

Ha Giang - On the occasion of the Lunar New Year 2025, tourists flocked to Ha Giang, to the point that there were times when traffic jams occurred on some roads.

Workers work through Tet on the North-South Expressway

CÔNG SÁNG |

Quang Binh - Even though it was the days before and during Lunar New Year, workers still stayed at the construction site, working through the holiday to ensure the progress of the expressway project.

"Sleepless" days and nights with Can Tho - Ca Mau expressway during Tet

TẠ QUANG - YẾN PHƯƠNG |

Can Tho - In the days leading up to Lunar New Year 2025, engineers and workers are still working tirelessly day and night to construct the Can Tho - Ca Mau expressway.

Construction of Can Tho - Ca Mau Expressway day and night during Tet

Tạ Quang - Yến Phương |

While the whole country is busy preparing for Tet, engineers and workers are still working hard day and night on the Can Tho - Ca Mau expressway.