Construction of Can Tho - Ca Mau Expressway day and night during Tet

Tạ Quang - Yến Phương |

While the whole country is busy preparing for Tet, engineers and workers are still working hard day and night on the Can Tho - Ca Mau expressway.

On the days leading up to the Lunar New Year of At Ty 2025, reporters from Lao Dong Newspaper went on a field trip to Lo Da Bridge in Vi Thuy District, Hau Giang Province, where workers constructing the Can Tho - Ca Mau Expressway were still working hard, making an important contribution to the construction of traffic infrastructure.

Tai cau Lo Da thuoc huyen Vi Thuy, tinh Hau Giang, cac cong nhan thi cong duong cao toc Can Tho – Ca Mau van miet mai lam viec. Anh: Ta Quang
At Lo Da bridge in Vi Thuy district, Hau Giang province, workers constructing the Can Tho - Ca Mau expressway are still working hard. Photo: Ta Quang

Mr. Nguyen Thanh Vinh - Deputy Executive Director of Truong Son Nam Department (Truong Son Corporation) - said that the unit arranged 20 construction teams, including 15 bridge construction teams and 5 road construction teams, with about 300 employees.

Mr. Nguyen Thanh Vinh added that the construction unit of 20km of highway with 20 bridges has reached over 65% of the contract value. Currently, 18 bridges have completed the installation of girders, and all bridges will be completed by the end of March 2025 at the latest. Regarding the route, the company has filled 90% of the load and paved 500m of asphalt concrete.

Regarding the construction work during Tet, Mr. Nguyen Thanh Vinh said that the unit has 4 bridge locations that must be worked during Tet with items such as pouring concrete on the bridge deck, installing beams, and 2 locations that need to be filled with sand and loaded with rocks with a workforce of about 150 people.

"To encourage the workers' spirit, in addition to the 200% and 300% salary increase according to regulations, the unit also organizes Tet meals and gives gifts to the workers," said Mr. Vinh.

Ong Vo Van Son (46 tuoi, huyen Vi Thuy, tinh Hau Giang). Anh: Ta Quang
Mr. Vo Van Son (46 years old, Vi Thuy district, Hau Giang province). Photo: Ta Quang

As a worker who has been working on the project for more than a year, Mr. Vo Van Son (46 years old, Vi Thuy district, Hau Giang province) shared that compared to civil construction, working on the highway is much harder because of being constantly exposed to the sun and the pressure of progress. However, in return, the job here has a good salary and regular work every day, thanks to which he has more motivation to stick with the project throughout the past time.

“The Can Tho - Ca Mau expressway is expected to be completed by the end of this year, which makes me and the workers feel proud to have contributed a small part to the key project of the country in general and the Mekong Delta in particular,” Mr. Son happily said.

At IC4 intersection through Binh Thanh commune, Phung Hiep district, Hau Giang province, the construction site seems to "never sleep" because of the continuous sound of machinery operating day and night.

Tai nut giao IC4, thiet bi may moc hoat dong lien tuc. Anh: Ta Quang
At IC4 intersection, machinery and equipment operate continuously. Photo: Ta Quang

Mr. Thai Ba Trinh - technical officer of Construction Corporation No. 1 - said that the contractor responsible for construction from Km34+100 to Km38+980 is mobilizing crushed stone for loading, with about 40 workers working each shift.

On the occasion of the Lunar New Year 2025, the unit will organize 3 construction projects including gathering loaded rocks on the main route, IC4 intersection and bridges - culverts to ensure the project is completed by the end of 2025 as required.

However, Mr. Thai Ba Trinh said that the source of materials is still difficult, because the sand mining license will expire in February, at which time the unit needs to increase the amount of stone for loading.

Nhan cong nghi giai lao trong dem. Anh: Ta Quang
Workers take a break at night. Photo: Ta Quang

My Thuan Project Management Board (investor) informed that up to now, the construction output of the two component projects has reached 58%, disbursed 6,342/6,351 billion VND (reaching 99%).

Regarding the construction plan for Tet, most contractors will work throughout Tet at the construction site. However, material mines, transport units, and suppliers will be off for 3 days including December 29 and January 1-2 (Lunar calendar). In this situation, to ensure the project's progress, construction units have worked overtime, increased shifts in the days before Tet, increased the capacity of gathering materials and supplies to the staging area to carry out construction during Tet, and at the same time completed the road section not affected by the source of materials.

The Can Tho - Ca Mau Expressway was started in January 2023, with a length of more than 110km, with a total investment of more than VND 27,500 billion. The project is divided into 2 component projects including the Can Tho - Hau Giang section (more than 37km long), reaching 64% and the Hau Giang - Ca Mau section (more than 73km long), reaching 55%.

Tạ Quang - Yến Phương
TIN LIÊN QUAN

Can Tho - Ca Mau Expressway continues to be paved with asphalt concrete

|

Can Tho - On January 2-3, 2025, the Can Tho - Ca Mau expressway continued to be paved with asphalt concrete with a length of 800m.

Can Tho - Ca Mau Expressway marks 2 years since construction began

|

After 2 years of construction, Can Tho - Ca Mau expressway has reached 56% progress and has paved the first meters of asphalt concrete.

Can Tho - Ca Mau Expressway paved the first meters

|

The laying of the first meters of asphalt marks the transition from the roadbed construction phase to the road surface completion phase of the Can Tho - Ca Mau expressway.

SEA Games 33 applies the rule of only using U22 players

|

The organizing committee of the 33rd SEA Games in Thailand has proposed applying the rule of only using U22 players for men's football.

Vietnam General Confederation of Labor seeks opinions on proposed list of 95 outstanding workers who are party members

|

The Vietnam General Confederation of Labor will hold a national conference to honor 95 outstanding workers who are members of the Communist Party of Vietnam.

21 workers with pneumoconiosis were compensated 1.4 billion VND

|

Nghe An - Chau Tien Company Limited has compensated 21 workers suffering from pneumoconiosis with a total amount of nearly 1.4 billion VND.

Strong cold air, rainy days forecast next week

|

According to the meteorological agency, due to the impact of cold air, the North will have rain from the night of January 25-26 and from January 31.

National Highway 1 through Quang Binh is heavily congested at Gianh Bridge

|

Quang Binh - The continuous influx of vehicles caused the North-South Highway 1 section through Gianh Bridge to be congested for about 500m.

Can Tho - Ca Mau Expressway continues to be paved with asphalt concrete

Tạ Quang |

Can Tho - On January 2-3, 2025, the Can Tho - Ca Mau expressway continued to be paved with asphalt concrete with a length of 800m.

Can Tho - Ca Mau Expressway marks 2 years since construction began

Tạ Quang |

After 2 years of construction, Can Tho - Ca Mau expressway has reached 56% progress and has paved the first meters of asphalt concrete.

Can Tho - Ca Mau Expressway paved the first meters

Tạ Quang |

The laying of the first meters of asphalt marks the transition from the roadbed construction phase to the road surface completion phase of the Can Tho - Ca Mau expressway.