Dong Dang - Tra Linh expressway will be invested in completing emergency stop lanes

Tân Văn |

Cao Bang - Phase 2 of the expressway project will have a complete 22m roadbed invested, with emergency stop lanes on both sides.

On May 5, information from the People's Committee of Cao Bang province, the locality just held a meeting of the Appraisal Council for the feasibility study report adjusting the Dong Dang (Lang Son) - Tra Linh (Cao Bang) expressway construction investment project in the form of public-private partnership (PPP).

The meeting was chaired by Mr. Hoang Van Thach - Vice Chairman of the Provincial People's Committee, Chairman of the Appraisal Council - with the participation of council members, the Provincial Traffic Construction Investment Project Management Board, representatives of project enterprises and consulting units.

At the meeting, the consulting unit presented a feasibility study report adjusting the project. Accordingly, the scale of the road was adjusted from a roadbed width of 17m combined with emergency stops 500m/stop to a complete scale of 22m.

Một số đoạn cầu sẽ được châm chước không bố trí làn dừng khẩn cấp. Ảnh: Tân Văn
Some bridge sections that have been approved in advance will be excused from arranging emergency stop lanes. Photo: Tan Van

Specifically, the section from Km0+000 to Km93+000 (phase 2) will have the roadbed widened to 22m with 4 lanes and emergency lanes continuously on both sides.

Some locations that have been constructed according to the old scale such as taluy slopes, barriers, drainage ditches... will be accommodated, without arranging emergency stop lanes. The bridge on this section still maintains a scale of 17.5m.

For the newly built section from Km93+000 to Km123+861, the roadbed and bridge are designed to a complete scale of 22m.

In addition to adjusting the scale, phase 2 also updates some basic design contents such as adjusting the morphology of the IC06 intersection at Km93+350, the NIKKO Factory bypass, road pavement structure, bridge items from Km93+350 to Km121+060, tunnel No. 3A and tunnel No. 4, and transferring the ITS smart traffic system to phase 2.

Giai đoạn 2 dự án xây dựng cao tốc Đồng Đăng - Trà Lĩnh sẽ được đầu tư hoàn chỉnh làn đường 22m. Ảnh: Tân Văn
Phase 2 of the Dong Dang - Tra Linh expressway construction project will have a complete 22m roadbed investment. Photo: Tan Van

According to the report, the total investment of the project after adjustment is 26,184.758 billion VND, a significant increase compared to the previous plan. In which, phase 1 has a total capital of 14,331.618 billion VND, phase 2 is 12,453.140 billion VND.

Land use demand after adjustment is about 1,130.51ha, an increase of 42.91ha. Of which, Lang Son province uses about 473.83ha, Cao Bang province about 656.68ha, including the area for rest stops of about 40ha.

The project is implemented in the period 2023 - 2028. The expected toll collection time to recover capital for phase 1 is about 22 years and 4 months, phase 2 is about 32 years and 8 months.

According to the phasing plan, the project is divided into 2 phases and 2 component projects to facilitate management and implementation.

Sau điều chỉnh, tổng mức đầu tư tại dự án là hơn 26.000 tỉ đồng. Ảnh: Tân Văn
After adjustment, the total investment in the project is more than 26,000 billion VND. Photo: Tan Van

In which, component project 1 invests about 93.35km from the Tan Thanh border gate area (Lang Son) to the National Highway 3 intersection in Quang Uyen commune (Cao Bang).

Component project 2 includes the expansion section from Km0+000 to Km93+350 and the new construction section from Km93+350 to Km121+060.

Concluding the meeting, Vice Chairman of the Provincial People's Committee Hoang Van Thach unanimously approved the project adjustment dossier, and at the same time requested the Department of Construction to coordinate with the Project Management Board and consulting unit to complete the dossier in a concise, logical direction, ensuring full legal basis.

Regarding site clearance work, leaders of the Provincial People's Committee requested the Project Management Board to coordinate with the Office of the Provincial People's Committee to organize direct working sessions with the People's Committees of communes to remove difficulties and accelerate the project implementation progress.

Tân Văn
RELATED NEWS

Dong Dang - Tra Linh expressway construction site no holiday when completion deadline approaches

|

Cao Bang - Thousands of workers are constructing during the holiday at the Dong Dang - Tra Linh expressway construction site, accelerating for phase 1 to be completed on May 19.

Do not interrupt the construction of the Dong Dang - Tra Linh expressway

|

Cao Bang - Local authorities are looking for many options so that the Dong Dang - Tra Linh expressway does not have to stop construction due to rising fuel prices.

The army is mobilized to participate in the construction of the Dong Dang - Tra Linh expressway

|

Cao Bang - 107 officers and soldiers of the army are assigned to participate in the construction of the Dong Dang - Tra Linh expressway.

US - Iran: Ceasefire agreement increasingly fragile

|

The ceasefire agreement in the Middle East is facing the risk of collapse as the US and Iran continue military actions to control the Strait of Hormuz.

Fearing communication disruption, users urgently verify subscribers

|

Hanoi - Network operators are always crowded with customers when deploying subscriber authentication, many people are worried about interrupting communication if they do not standardize information in time.

2 low pressure systems move towards the Philippines, possibly strengthening into Typhoon Caloy

|

Two low pressure systems are moving towards the Philippines, one of which enters the forecast area on May 5, while the other low pressure system is strengthening.

Scene of the chain collision at the beginning of Thang Long bridge, the car was crushed

|

Hanoi - A series of accidents at the beginning of Thang Long bridge (direction to Dong Anh) caused many vehicles to be heavily damaged.

Dong Dang - Tra Linh expressway construction site no holiday when completion deadline approaches

Tân Văn |

Cao Bang - Thousands of workers are constructing during the holiday at the Dong Dang - Tra Linh expressway construction site, accelerating for phase 1 to be completed on May 19.

Do not interrupt the construction of the Dong Dang - Tra Linh expressway

Tân Văn |

Cao Bang - Local authorities are looking for many options so that the Dong Dang - Tra Linh expressway does not have to stop construction due to rising fuel prices.

The army is mobilized to participate in the construction of the Dong Dang - Tra Linh expressway

Duy Dũng |

Cao Bang - 107 officers and soldiers of the army are assigned to participate in the construction of the Dong Dang - Tra Linh expressway.