Expressway worth more than 9,700 billion VND through Can Tho has not identified the source of 0.62 million m3 of stone

Tạ Quang |

Can Tho - Chau Doc - Can Tho - Soc Trang expressway through Can Tho reached 61.38%, but still lacks 1.443 million m3 of sand and has not identified the source of 0.62 million m3 of stone.

On August 22, Mr. Le Cong Ly - Standing Vice Chairman of Can Tho City People's Committee led a working delegation to inspect the Chau Doc - Can Tho - Soc Trang expressway construction investment project phase 1, component project 2 section passing through Can Tho City.

Dự án đầu tư xây dựng đường bộ cao tốc Châu Đốc - Cần Thơ - Sóc Trăng giai đoạn 1, dự án thành phần 2 đoạn qua địa bàn TP Cần Thơ. Ảnh: Tạ Quang
Project to invest in the construction of Chau Doc - Can Tho - Soc Trang expressway phase 1, component project 2 section passing through Can Tho City. Photo: Ta Quang

Mr. Phan Minh Tri - Deputy Director of the Project Management Board for Investment in Construction of Transport and Agricultural Works of Can Tho City (Project Management Board) said that the total value of 4 main construction packages and 1 construction package of the traffic safety system is 3,835,988/6,249,638 billion VND, reaching a rate of 61.38%.

The total demand for sand filling and leveling materials according to the construction contract is about 5.121 million m3 of loose sand blocks. The source has been identified at about 5.279 million m3. Currently, about 3.305 million m3 is being exploited for the project.

Đoàn công tác kiểm tra tiến độ dự án cao tốc. Ảnh: Tạ Quang
The working delegation inspects the progress of the expressway project. Photo: Ta Quang

Currently, the project is receiving sand at Hoa Hung 4 mines, Tan Phong mine in Dong Thap province and NTSH mine. 10a in Vinh Long province. The remaining sand demand to complete the load is about 1.443 million m3. Phase 1 load is expected to be completed in October - November 2026.

For the demand for stone material for construction, it is about 1.041 million m3; of which, about 0.282 million m3 has been gathered for the project and has been used. The volume of stone that has identified the source is 0.353 million m3, which is committed to support by An Giang province, and the remaining volume that has not yet identified the source is about 0.62 million m3.

Nhiều công nhân thi công trên công trường dưới thời tiết nắng nóng. Ảnh: Tạ Quang
Many workers are working at the construction site in hot weather. Photo: Ta Quang

Mr. Nguyen Dang Son - Deputy Director of Ngoc Bao Trading Construction Co., Ltd. - the construction unit of Package No. 1 of the Chau Doc - Can Tho - Soc Trang Expressway Project informed that the unit is focusing on loading, and at the same time preparing the necessary conditions to construct the next items.

According to Mr. Nguyen Dang Son, in the process of implementation, the biggest difficulty before was the source of sand materials. Because Can Tho City does not have sand sources to meet project needs, contractors have to mobilize materials from neighboring provinces. Up to now, sand sources have been basically supplied, helping contractors have conditions to accelerate the loading on the route.

Máy móc được huy động tối đa để thi công. Ảnh: Tạ Quang
Machinery is mobilized to the maximum for construction. Photo: Ta Quang

Standing Vice Chairman of Can Tho City People's Committee Le Cong Ly requested the Project Management Board to continue to focus on directing and operating, closely follow the project implementation progress; proactively coordinate with departments, branches, localities and related units to urgently remove difficulties and obstacles, especially regarding the source of sand and stone materials for construction, ensuring to meet the demand for materials according to the project progress.

In addition, it is necessary to urgently mobilize human resources, machinery, and equipment to accelerate construction and compensate for the delayed volume.

The Chau Doc - Can Tho - Soc Trang expressway construction investment project phase 1, component project 2 section passing through Can Tho City has a total investment of 9,725.097 billion VND, implementation time from 2022 - 2027, with a total length of about 37.42 km.

The investment project to build the Chau Doc - Can Tho - Soc Trang expressway phase 1 has a length of more than 188 km, a scale of 4 lanes, with a total investment of 44,600 billion VND.

Tạ Quang
RELATED NEWS

Can Tho studies commercial sand purchase for Chau Doc - Can Tho - Soc Trang expressway project

|

Can Tho - Faced with the shortage of filling sand, the investor is considering a commercial sand purchase plan for the expressway project worth more than 31,000 billion VND.

Chau Doc - Can Tho - Soc Trang expressway, beware of delays due to lack of sand

|

The Chau Doc - Can Tho - Soc Trang expressway project is facing a shortage of materials as the amount of sand brought to the construction site does not meet construction needs.

Nearly 1,000 officials and soldiers in Lang Son help people cope with floods

|

Lang Son - The provincial armed forces have mobilized nearly 1,000 officers and soldiers to evacuate nearly 100 households and move property to safe places during floods.

Chairman of Nha Trang ward directs inspection of the case of an elderly woman kneeling in the middle of the road

|

Khanh Hoa - The Chairman of Nha Trang Ward has assigned the Police to inspect the case of an elderly woman kneeling in the middle of the road, begging after a traffic collision.

Small traders at Gieng Vuong market: "The flood is rising too quickly, almost everything is lost

|

Lang Son - Heavy rain caused Gieng Vuong market to be widely flooded, hundreds of officers and soldiers were mobilized to support small traders in moving goods.

Buying and selling, creating artificial scarcity is pushing house prices up

|

According to the Minister of Construction, the shortage of commercial housing in the mid- and low segments leads to speculation, buying and selling, pushing house prices up.

Cảnh xuống cấp, hoang hóa tại Khu văn hóa Hồ Nước Ngọt ở Cần Thơ

Tạ Quang |

Cần Thơ - Từng là điểm vui chơi, sinh hoạt cộng đồng quen thuộc, Khu văn hóa Hồ Nước Ngọt nay xuống cấp, hoang hóa và vắng người.

Can Tho studies commercial sand purchase for Chau Doc - Can Tho - Soc Trang expressway project

Tạ Quang |

Can Tho - Faced with the shortage of filling sand, the investor is considering a commercial sand purchase plan for the expressway project worth more than 31,000 billion VND.

Chau Doc - Can Tho - Soc Trang expressway, beware of delays due to lack of sand

Lê Thanh Phong |

The Chau Doc - Can Tho - Soc Trang expressway project is facing a shortage of materials as the amount of sand brought to the construction site does not meet construction needs.