Can Tho Chairman sets 2 milestones for completing the expressway worth more than 31 trillion VND

Tạ Quang |

Can Tho - Mr. Truong Canh Tuyen requested contractors to urgently adjust the construction progress of the expressway, closely following the two completion milestones of July 30, 2027 and December 31, 2027.

In the afternoon of May 27, Mr. Truong Canh Tuyen - Chairman of Can Tho City People's Committee chaired a working session to listen to the progress report on the implementation of the Project to invest in the construction of the Chau Doc - Can Tho - Soc Trang expressway phase 1 through the city.

Expressway worth more than 31,200 billion VND faces difficulties with sand and stone

The Can Tho City Traffic and Agricultural Construction Investment Project Management Board (PMB) said that the Chau Doc - Can Tho - Soc Trang expressway construction investment project phase 1, component projects 2, 3, 4, has a length of about 132 km. Total investment is more than 31,200 billion VND.

Cao tốc Châu Đốc - Cần Thơ - Sóc Trăng giao với tuyến Lộ Tẻ - Rạch Sỏi. Ảnh: Tạ Quang
Chau Doc - Can Tho - Soc Trang expressway intersects with Lo Te - Rach Soi route. Photo: Ta Quang

The project has its starting point at Km57+200 in Thanh Quoi commune; the ending point at Km189+666.65 intersecting with the Nam Song Hau National Highway and the access road to Tran De port (Planning). The project has a total of 11 construction packages.

The total demand for sand filling materials for component projects 2, 3, 4 is about 16.649 million m3 of loose sand. To date, the volume of sand that has arrived at the project is about 10.579 million m3. The PMB is continuing to work with Vinh Long and An Giang provinces to ensure the source of sand to be brought to the project.

Khối lượng cát đã về công trình khoảng 10,579 triệu m3. Ảnh: Tạ Quang
The volume of sand that has reached the construction site is about 10.579 million m3. Photo: Ta Quang

For stone materials serving 3 component projects, about 4.176 million m3 (increased due to adjustment of road pavement structure), of which about 0.878 million m3 have been gathered for the project and have been used. The PMB and the Contractor continue to contact and register needs at stone mines in Dong Nai City, Ho Chi Minh City (old Binh Duong province) to ensure material sources.

Currently, the progress of bridge construction on the route has reached and exceeded the set schedule. However, the route section still has some sections that have not reached the required schedule due to the slow arrival of sand materials at the initial construction site, and is currently urgently filling the roadbed with sand.

No shortage of money, only lack of progress

Vice Chairman of Can Tho City People's Committee Nguyen Van Hoa clearly stated that the progress of the expressway project to date has not yet met the requirements according to general directions and set goals.

Phó Chủ tịch UBND TP Cần Thơ Nguyễn Văn Hòa phát biểu tại buổi làm việc. Ảnh: Tạ Quang
Vice Chairman of Can Tho City People's Committee Nguyen Van Hoa speaks at the working session. Photo: Ta Quang

According to Mr. Hoa, the Project Management Board needs to urgently work again with contractors and supervision consulting units to review the progress according to commitments. On that basis, closely monitor each construction stage to promptly remove arising problems.

Regarding the source of sand materials serving the project, leaders of Can Tho City requested that mines identified as special and licensed must increase exploitation capacity to ensure sufficient reserves for supply to the project.

Contractors are also required to review bidding documents and fully calculate the source of materials to ensure the correct implementation of contract commitments.

For sections of the route that have reached load-bearing elevation, it is necessary to inspect the entire route, specifically statistically count the Kms that have completed load-bearing and unloading to deploy the next construction items.

Mr. Nguyen Van Hoa informed that the capital allocated for the expressway project is currently abundant. In 2026 alone, the total allocated capital is 4,500 billion VND, but from the beginning of the year until now, only about 750 billion VND has been disbursed.

There is still a lot of capital, there is no shortage of money, but how to spend money, to spend money, there must be volume, and the volume must be accepted," Mr. Hoa said.

Ông Trương Cảnh Tuyên - Chủ tịch UBND TP Cần Thơ phát biểu kết luận cuộc họp. Ảnh: Tạ Quang
Mr. Truong Canh Tuyen - Chairman of Can Tho City People's Committee delivered a concluding speech at the meeting. Photo: Ta Quang

Concluding the meeting, Mr. Truong Canh Tuyen - Chairman of Can Tho City People's Committee said that the project still faces many difficulties, the biggest of which is the pressure of shortage of sand and stone materials.

Mr. Truong Canh Tuyen emphasized that despite difficulties, the city has never relaxed its responsibility. Can Tho City People's Committee has regularly worked with localities, directly signing many documents to remove difficulties and ensure material sources for the project.

Chairman of Can Tho City People's Committee requested that all units must focus on implementing the goals according to the National Assembly's Resolution, striving to basically complete the project by July 2027 and put it into official operation by the end of 2027.

Dự án thành phần 2, 3, 4 có tổng chiều dài hơn 132 km. Ảnh: Tạ Quang
Component projects 2, 3, 4 have a total length of more than 132 km. Photo: Ta Quang

Contractors urgently rebuild the construction progress according to two important milestones: July 30, 2027 and December 31, 2027; at the same time, proactively search for sand and stone sources, propose sources of material supply and increase human resources, vehicles, and equipment to serve construction.

For the Project Management Board, the Chairman of Can Tho City People's Committee requested that before May 31, it is necessary to accurately review the actual demand for sand and stone of the entire project; clearly identify the demand for sea sand; and at the same time, propose a plan to adjust the volume of materials between contractors if there is a situation of surplus in some places and shortage in others.

Tạ Quang
RELATED NEWS

Desolate and heavily degraded scene in the former "green lung" in Can Tho

|

Can Tho - The 20ha Ngoc Ngot Lake cultural area in Soc Trang ward, once a "green lung", is now seriously degraded, with many items damaged and deserted.

Bonus of millions of VND/day, workers accelerate construction of the Western expressway

|

Can Tho - Bonuses of millions of VND/day, workers at the Chau Doc - Can Tho - Soc Trang expressway construction site still stick to construction during holidays, accelerating to bring the project to completion.

Along and across the highway in the Mekong Delta

|

The Mekong Delta expressway network is gradually taking shape with clear vertical and horizontal axes, connecting from Ho Chi Minh City to Ca Mau province, from the border to the sea, opening up a new development space for the entire region.

9th Hour No. 200: Unsuccessful marriage - Part 1

|

Hour 9 - Successful but unlucky in love, the girl accepts to go to the doctor because of family pressure. Will this forced meeting spark love?

Series of material panels fall onto elevated Ring Road 3, driver fined

|

Hanoi - A series of material panels fell on the elevated Ring Road 3, functional forces have verified and handled violating drivers.

Violating construction in Quang Ngai still exists for many years

|

Quang Ngai - Construction projects covering dozens of hectares have existed for many years, but local authorities have not yet taken action to handle them, causing public outrage.

Desolate and heavily degraded scene in the former "green lung" in Can Tho

Tạ Quang |

Can Tho - The 20ha Ngoc Ngot Lake cultural area in Soc Trang ward, once a "green lung", is now seriously degraded, with many items damaged and deserted.

Bonus of millions of VND/day, workers accelerate construction of the Western expressway

Tạ Quang |

Can Tho - Bonuses of millions of VND/day, workers at the Chau Doc - Can Tho - Soc Trang expressway construction site still stick to construction during holidays, accelerating to bring the project to completion.

Along and across the highway in the Mekong Delta

Nhật Hồ - Tạ Quang |

The Mekong Delta expressway network is gradually taking shape with clear vertical and horizontal axes, connecting from Ho Chi Minh City to Ca Mau province, from the border to the sea, opening up a new development space for the entire region.