Quy Nhon - Pleiku expressway is accelerating construction progress

THANH TUẤN |

Gia Lai - The Quy Nhon - Pleiku expressway project is being urgently implemented with the spirit of "handing over the site to where, construction to there".

On February 24, the Gia Lai Provincial Traffic and Civil Works Project Management Board said that the project is organized for construction throughout the Lunar New Year. Up to now, localities have handed over about 5 km of clean ground in the area at the beginning of the expressway. Where the ground is handed over, the contractor organizes construction immediately.

For component project 1 (Km0+000 – Km22+000), 13 construction teams have been arranged throughout the Binh Ngo Tet 2026. In which, package XL. 01 mobilized 8 construction teams, focusing on leveling the ground, organic excavation, roadbed construction, drilling piles for the An Nhon bridge and preparing for the construction of the North-South expressway overpass.

Package XL. 02 deploys 5 construction teams, focusing on leveling the ground at Song Kon and Ha Nhe bridges; drilling piles, installing concrete mixing stations and processing box culvert components.

Provincial functional sectors continue to accelerate site clearance according to the principle "clearance to where, construction to there"; select capable contractors, absolutely not trading quality for progress; and at the same time strictly manage material sources, avoiding fragmented construction, affecting the quality of the project.

Gia Lai province strives to basically complete compensation, support, and resettlement work in the second quarter of 2026; complete component project 1 in June 2028 and put it into operation in July 2028.

The Quy Nhon - Pleiku expressway project is about 125 km long, passing through 17 communes and wards, is a national key project with a total investment of more than 43,700 billion VND. The expressway is designed with 4 lanes, a roadbed width of 24.75 m, and a design speed of 100 km/h.

After completion, the project will contribute to promoting trade, developing logistics services, transporting agricultural products, strengthening inter-regional connectivity, creating motivation for socio-economic development for the region. Currently, Quy Nhon and Pleiku are mainly connected through National Highway 19 with a travel time of about 4 hours. When the expressway is completed, the travel time between the two cities is expected to be shortened to about 1.5 hours.

THANH TUẤN
RELATED NEWS

Huu Nghi - Chi Lang expressway rushes in spring, 2,599 personnel race for progress

|

Lang Son - In the early days of the new year, when many places are still in the spring travel atmosphere, the large construction site of the Huu Nghi - Chi Lang expressway has resounded with the sound of machines.

HCMC - Long Thanh - Dau Giay expressway congestion in the afternoon of the 6th day of Tet

|

Ho Chi Minh City - During the time when people return to Ho Chi Minh City after Tet, the Ho Chi Minh City - Long Thanh - Dau Giay expressway is falling into prolonged congestion.

16km of expressway connecting Dong Nai and Ho Chi Minh City inaugurated in May

|

Dong Nai - Component project 1 of the Bien Hoa - Vung Tau expressway, about 16km long, will be inaugurated in May 2026.

Dong Khe Campaign 2026 - completing 2 expressways in 85 days and nights

|

Prime Minister Pham Minh Chinh has given new directions for the deployment of the Huu Nghi - Chi Lang, Dong Dang - Tra Linh, Bac Kan - Cao Bang expressways.

House fire in Ho Chi Minh City on the afternoon of the 8th day of Tet, burning down many properties

|

Ho Chi Minh City - On the afternoon of the 8th day of Tet, a house on Do Xuan Hop street (Phuoc Long ward) caught fire fiercely, burning down many properties.

Thu Trang speaks out about information of discord with the "Mui Pho" film crew

|

Recently, there has been information that Thu Trang did not participate in promoting the movie "Mui pho", even disagreed with the cast in the movie.

Proposing a land fund large enough to attract Meta, Arizona State University to Hanoi

|

Hanoi - The Management Board of High-Tech Parks and Industrial Parks of the city proposes planning a land fund large enough to attract Arizona State University, Meta Group...

Continue to complete the plan to adjust the organization and staffing of the Army

|

General Phan Van Giang clearly stated the continued completion of the plan to adjust the organization and staffing of the Army in the period 2026-2030.

Huu Nghi - Chi Lang expressway rushes in spring, 2,599 personnel race for progress

Khánh Linh |

Lang Son - In the early days of the new year, when many places are still in the spring travel atmosphere, the large construction site of the Huu Nghi - Chi Lang expressway has resounded with the sound of machines.

HCMC - Long Thanh - Dau Giay expressway congestion in the afternoon of the 6th day of Tet

ÁNH TÚ |

Ho Chi Minh City - During the time when people return to Ho Chi Minh City after Tet, the Ho Chi Minh City - Long Thanh - Dau Giay expressway is falling into prolonged congestion.

16km of expressway connecting Dong Nai and Ho Chi Minh City inaugurated in May

HÀ ANH CHIẾN |

Dong Nai - Component project 1 of the Bien Hoa - Vung Tau expressway, about 16km long, will be inaugurated in May 2026.

Dong Khe Campaign 2026 - completing 2 expressways in 85 days and nights

Tân Văn |

Prime Minister Pham Minh Chinh has given new directions for the deployment of the Huu Nghi - Chi Lang, Dong Dang - Tra Linh, Bac Kan - Cao Bang expressways.