Can Gio bridge is expected to be joined at the end of 2028, operation from June 2029

MINH QUÂN |

Ho Chi Minh City - Can Gio bridge after the groundbreaking ceremony is being accelerated with procedures to start construction in June, close at the end of 2028 and put into operation in June 2029.

Ho Chi Minh City People's Committee has just issued a plan to implement the project to invest in the construction of Can Gio bridge according to the public-private partnership (PPP) method, BT contract (build - transfer).

The Can Gio bridge project was started on January 15, 2026. The project has a total length of more than 6.3 km (the main bridge is nearly 3 km long; the approach road and bridges on the route are more than 3.2 km long).

Can Gio bridge is designed with a scale of 6 lanes, including 4 lanes for motorized vehicles and 2 mixed lanes, with a design speed of 60 km/h.

The highlight of the project is the main cable-stayed bridge with two tower pillars, a navigation clearance of 55 m, equivalent to Binh Khanh bridge on the Ben Luc - Long Thanh expressway.

In addition to the main bridge, the project also builds three bridges on the route including: Song Cha bridge, more than 640 m long; Tac Song Cha bridge, more than 64 m long; and Rach Muong Ngang bridge (parallel road on Nha Be side) including two units, each unit 64 m long.

Cầu Cần Giờ sẽ thay phà Bình Khánh, chấm dứt cảnh “qua sông lụy phà”.  Ảnh: Anh Tú
Can Gio bridge will replace Binh Khanh ferry, ending the scene of "crossing the river with a ferry". Photo: Anh Tu

The preliminary total investment of the project is over 13,200 billion VND according to the BT contract, divided into two component projects.

In which, the compensation, support and resettlement project has capital of more than 2,533 billion VND from the Ho Chi Minh City budget; the BT contract bridge construction project has a total capital of more than 10,668 billion VND, mostly mobilized by investors.

According to the implementation plan, in April 2026, relevant units will complete the dossier to submit to the Ho Chi Minh City People's Committee for approval of the investment project. The BT project contract is expected to be signed on June 1, 2026.

Regarding site clearance, the city will hand over a part of public land and water surface area to investors before June 1st to serve the commencement of construction. The agricultural land is expected to complete site clearance in June 2026, while the scope of non-agricultural land is completed in August of the same year.

According to the set schedule, the Can Gio bridge project will start construction in June 2026, the main bridge will be closed on December 31, 2028, and inaugurated and put into operation on June 30, 2029.

Currently, Binh Khanh, Can Gio, An Thoi Dong and Thanh An communes (formerly belonging to Can Gio district) do not have direct roads connecting to the center of Ho Chi Minh City.

People mainly have to cross Binh Khanh ferry, which is often overloaded, especially on weekends and holidays, causing prolonged congestion and affecting tourism activities as well as socio-economic development of the region.

When completed, Can Gio bridge will not only solve the traffic problem but is also expected to become a new architectural symbol of the city. The travel time from the center of Ho Chi Minh City to Can Gio will be shortened to about 40-50 minutes, instead of nearly 2 hours as at present.

The project is also of special significance in the context that Can Gio is implementing a coastal urban area project with a scale of 2,870 ha, and at the same time preparing to build a sea route more than 14 km long connecting to Vung Tau.

When projects are implemented synchronously, the Can Gio area is expected to become a new driving axis, expanding Ho Chi Minh City's development space towards the sea.

MINH QUÂN
RELATED NEWS

Can Gio bridge worth more than 13,200 billion VND was grounded this morning

|

Ho Chi Minh City groundbreaking ceremony to build Can Gio bridge with a total capital of more than 13,200 billion VND. The project in the future will replace Binh Khanh ferry, connecting sea-facing traffic.

Can Gio Bridge helps Ho Chi Minh City residents escape ferry dependence, opening a way to the sea

|

Ho Chi Minh City - Can Gio Bridge was grounded on January 15, expected to be completed in 2029, replacing Binh Khanh ferry, opening up a new development space for the Can Gio area.

Ho Chi Minh City plans to build Can Gio Bridge worth over VND13,200 billion, starting construction in 2027

|

HCMC - The Can Gio bridge project has a total length of 6.3 km, a total of more than 13,200 billion VND under the BT contract, expected to start construction in 2027, replacing Binh Khanh ferry.

UAV attack, Dubai airport temporarily closed

|

A series of UAV attacks on Dubai airport in the United Arab Emirates killed 1 person.

Accelerate completion of Ring Road 2.5 section Kim Dong - Dam Hong before handover date

|

Hanoi - Ring Road 2.5 Kim Dong - Dam Hong section gradually reveals a new face when the final items are being urgently constructed before the handover time.

Rumors spread that Iran's Supreme Leader secretly went abroad for treatment

|

Iranian Supreme Leader Mojtaba Khamenei is believed to have been injured in the airstrike on February 28 and may have been taken abroad for treatment.

Starlink satellite Internet subscribers in Vietnam are expected to pay 2.2 million VND per month

|

Starlink satellite Internet service in Vietnam is expected to have a monthly subscription fee of about 2.2 million VND.

Many people slipped and fell due to mud on the road, Hanoi traffic police search for vehicles scattered

|

Hanoi - Many motorcyclists suddenly slipped and fell on the road due to mud. Traffic police quickly arrived to handle and trace the source of the vehicles dropped.

Can Gio bridge worth more than 13,200 billion VND was grounded this morning

Bảo Tú |

Ho Chi Minh City groundbreaking ceremony to build Can Gio bridge with a total capital of more than 13,200 billion VND. The project in the future will replace Binh Khanh ferry, connecting sea-facing traffic.

Can Gio Bridge helps Ho Chi Minh City residents escape ferry dependence, opening a way to the sea

MINH QUÂN |

Ho Chi Minh City - Can Gio Bridge was grounded on January 15, expected to be completed in 2029, replacing Binh Khanh ferry, opening up a new development space for the Can Gio area.

Ho Chi Minh City plans to build Can Gio Bridge worth over VND13,200 billion, starting construction in 2027

MINH QUÂN |

HCMC - The Can Gio bridge project has a total length of 6.3 km, a total of more than 13,200 billion VND under the BT contract, expected to start construction in 2027, replacing Binh Khanh ferry.