Hanoi Ring Road 2.5: Construction overnight, will be open to traffic at the end of January

SÓNG HỮU |

Hanoi - Contractors are urgently constructing day and night to complete Ring Road 2.5, Dam Hong - National Highway 1A section by the end of January 2026.

In the middle days of January, the construction site of the Ring Road 2.5 investment project, Dam Hong - National Highway 1A section, is always bustling with engine sounds, with no time to rest.

On the entire route, construction teams are deployed simultaneously, racing against time to keep up with the traffic opening schedule at the end of the month.

The project is divided into 5 bidding packages, including 3 main construction packages. Based on the volume of each item, contractors arrange suitable personnel and equipment to ensure progress according to the set plan.

a
The construction site of the Ring Road 2.5 project, Dam Hong - National Highway 1A section, is lit up, under construction all night. Photo: Song Huu
a
Items are being urgently deployed by the contractor. Photo: Song Huu

Talking to Lao Dong Newspaper, Mr. Nguyen Xuan Manh, project manager of Ring Road 2.5 (Hoang Mai Construction Investment Co., Ltd. - Hanoi) said that after the project was restarted in May 2025, contractors have mobilized maximum manpower and machinery to continuously deploy construction.

To date, the bidding packages have completed about 80-90% of the workload.

Before the requirement to complete the entire project by January 31, Mr. Manh said that contractors are focusing all their efforts on the final sprint, constructing "3 shifts, 4 teams" on the construction site.

Because there is not much time left, the investor and contractors encourage engineers and workers to stick to the construction site, with the common determination to bring the project to completion on schedule to serve the travel needs of the people, and gradually solve the traffic congestion bottlenecks of the city" - Mr. Manh said.

It is expected that after January 25, the Ring Road 2.5 section Dam Hong - National Highway 1A will be installed with a traffic sign system, painted with road markings, ready for traffic opening at the end of January.

a
Machinery works day and night on the project site. Photo: Song Huu
a
a
Workers constructing lighting items. Photo: Song Huu
a
L3 bridge over the Lu River - an important item of the project - is also being urgently constructed by the contractor. Photo: Song Huu

The Ring Road 2.5 construction project, Dam Hong - National Highway 1A section, is invested in the form of a BT contract (build - transfer) with a length of 1.6 km, with a total investment of more than 1,300 billion VND.

The project started in 2014, expected to be completed in 2017 but was delayed.

By 2020, the project was temporarily suspended when it only reached about 40% of the workload. The reason is due to problems in site clearance and extension of BT contract appendices.

After 5 years of suspension, by the end of May 2025, with the permission of the Hanoi People's Committee, Hoang Mai - Hanoi Construction Investment Co., Ltd. (the project enterprise) organized the groundbreaking ceremony for the Ring Road 2.5 construction project, Dam Hong - National Highway 1A section.

This is one of the key traffic projects, of important significance in reducing congestion, synchronizing urban transport infrastructure, contributing to promoting socio-economic development in the southern part of the city.

Hanoi Ring Road 2.5 has a total length of about 19.64km, planned width of 40-50m. Starting point in Ciputra New Urban Area, ending at the intersection with Ring Road 3 (section near Thanh Tri bridge).

To date, Ring Road 2.5 has been put into use 5/13 sections with a length of 11.28 km. The project is implementing 5 sections with a length of 6.1 km. The remaining 3 sections with a length of 2.26 km have just been approved for investment policy by Hanoi.

Regarding the Ring Road 2.5 project, Politburo Member, Secretary of the Hanoi City Party Committee Nguyen Duy Ngoc requested the Party Committee and City People's Committee to direct the City People's Committee, departments, branches, and the City Traffic Construction Investment Project Management Board; Party committees and ward authorities must clearly define political responsibilities to complete site clearance and complete the entire project in 2026.

SÓNG HỮU
RELATED NEWS

Hanoi relocates nearly 200 graves to build road connecting Ring Road 2.5 to Ring Road 3

|

Hanoi - The city implements the relocation of nearly 200 graves to build the Minh Khai - Vinh Tuy - Yen Duyen road connecting Ring Road 2.5 to Ring Road 3.

Inside the 100-year-old memorial house under relocation as Ring Road 2.5

|

Hanoi - The revolutionary memorial house of Mr. Ta Dinh Tan in Cau Giay ward is under site clearance and relocation according to the Ring Road 2.5 project plan.

Enforcement of Ring Road 2.5: Deadline for handling cases of not handing over land

|

Hanoi - It is expected that from January 25th, land recovery will be enforced for cases of not handing over land for Ring Road 2.5 construction.

3-magnitude earthquake shakes Lao Cai highlands

|

Lao Cai - An earthquake has been recorded in Thac Ba commune.

Expecting a new face for the Hoang Thi Loan Memorial Area in Hung Yen

|

Hung Yen - People in Van Noi village are placing high hopes on expanding the campus of the Memorial House of Mrs. Hoang Thi Loan.

Dozens of Japanese ships stranded as US blockades Hormuz

|

About 40 Japanese-related ships are still trapped in the Persian Gulf as the US blockades the Strait of Hormuz, increasing global transportation and energy risks.

Live volleyball VTV Binh Dien Long An vs LPB Ninh Binh

|

Live match between VTV Binh Dien Long An vs LPB Ninh Binh at the 2026 National Volleyball Championship, taking place at 5:30 PM today (April 14).

Suspension of female kindergarten teacher for impacting children's heads

|

Ha Tinh - After a clip appeared of a female teacher impacting a child's head, the teacher involved has been temporarily suspended from work to verify and clarify the incident.

Hanoi relocates nearly 200 graves to build road connecting Ring Road 2.5 to Ring Road 3

KHÁNH AN |

Hanoi - The city implements the relocation of nearly 200 graves to build the Minh Khai - Vinh Tuy - Yen Duyen road connecting Ring Road 2.5 to Ring Road 3.

Inside the 100-year-old memorial house under relocation as Ring Road 2.5

HỮU VŨ |

Hanoi - The revolutionary memorial house of Mr. Ta Dinh Tan in Cau Giay ward is under site clearance and relocation according to the Ring Road 2.5 project plan.

Enforcement of Ring Road 2.5: Deadline for handling cases of not handing over land

Cường Ngô |

Hanoi - It is expected that from January 25th, land recovery will be enforced for cases of not handing over land for Ring Road 2.5 construction.