Long Thanh Bridge repairs completed ahead of schedule

MINH QUÂN |

Expansion joint repair work at Long Thanh bridge on the Ho Chi Minh City - Long Thanh - Dau Giay expressway was completed 4 days ahead of schedule.

According to an announcement from Vietnam Expressway Engineering Services Joint Stock Company (VEC E), the repair of Long Thanh Bridge (from Dong Nai to Ho Chi Minh City) will take place from September 5 and be completed on September 19.

After the work was completed, from 11pm on September 19, the site was returned to allow vehicles to circulate through 2 lanes, helping to reduce traffic congestion in the area.

However, to ensure the quality of concrete at the joint between the expansion joint and the asphalt concrete surface, VEC E continues to limit the speed at the Long Thanh bridge repair location until September 23. After this time, traffic speed will be restored to normal.

Previously, from September 5, the expansion joint on Long Thanh bridge began to be repaired after discovering a broken rail.

The narrowing of the road surface while the traffic volume on the route is very large has caused congestion on the bridge and highway in Dong Nai.

The Ho Chi Minh City - Long Thanh - Dau Giay Expressway, with a total length of 55km and a scale of 4 lanes, was put into operation in 2016. Traffic volume on this expressway is continuously increasing, an average of nearly 12% per year, so traffic jams are frequent.

It is expected that by 2026, when Long Thanh airport comes into operation, traffic pressure on this highway will increase even more strongly.

In that context, the expansion of the expressway is being studied with the option of expanding the section from the Ring Road 2 intersection (Thu Duc City) to the Bien Hoa - Vung Tau expressway intersection.

Accordingly, the section from the Ring Road 2 intersection to the Ring Road 3 intersection will be invested with 8 lanes according to the plan. The section from the Ring Road 3 intersection to the Bien Hoa - Vung Tau expressway intersection will be invested with 10 lanes according to the plan.

Long Thanh Bridge will be invested in building a new bridge unit, with a scale similar to the current bridge, organizing traffic exploitation with a scale of 10 lanes (no emergency lanes will be arranged in advance, combined with traffic organization with 5 lanes on each side, 35m wide).

This expansion project has a total investment of nearly 15,000 billion VND. If approved, it will be implemented and completed by the end of 2027.

MINH QUÂN
RELATED NEWS

Iran's oil and minerals reach $27 trillion in US calculations

|

Owning oil and minerals estimated at $27 trillion makes Iran considered an important factor in US strategic calculations.

Mattress warehouse fire in Ho Chi Minh City, fire flares up again

|

Ho Chi Minh City - The fire at the mattress warehouse in Cu Chi commune suddenly flared up again after being extinguished last night, the fire fighting force promptly controlled the fire.

Vietnam Aviation Administration issues urgent directive in the face of the war situation in the Middle East

|

On March 1, the Civil Aviation Authority of Vietnam issued a directive document in the face of the war situation in the Middle East region.

Iran national team may withdraw from World Cup 2026

|

Escalating tensions between Iran and the US have raised great questions about the Iranian national team's ability to participate in the 2026 World Cup.

Near the full moon of the first lunar month, chickens holding roses at the rich market in Hanoi are deserted

|

Hanoi - Near the full moon of the first lunar month, the trading atmosphere at the market on Gia Ngu street is quieter than every year. Rose-soaked chickens are displayed eye-catchingly but few customers buy them.

Proactively handle complaints related to military officers running for National Assembly deputies

|

In the coming time, the Ministry of National Defense will proactively inspect and coordinate to resolve complaints and denunciations related to personnel of military officers who are candidates for National Assembly deputies (NA deputies).

Conflict spreads, Iranian missiles target Qatar's capital directly

|

Qatar's air defense system successfully intercepted a series of missiles from Iran aimed at the capital Doha, pushing the regional conflict to officially spread.

Transferring and appointing personnel in Lao Cai, Lai Chau, 2 ministries, 2 agencies

|

Many decisions on delegating power, receiving, transferring, and appointing personnel have been implemented in Lao Cai, Lai Chau, the Ministry of Education and Training, and the Ministry of Agriculture and Environment.

Ùn tắc kéo dài trên cầu lớn nhất cao tốc TPHCM - Long Thành

CHIẾN QUÂN |

Sáng 5.9, cầu Long Thành (thuộc cao tốc TPHCM - Long Thành - Dầu Giây) ùn tắc kéo dài theo hướng Đồng Nai về TPHCM do rào chắn một nửa mặt cầu để sửa chữa.

Sửa cầu trên cao tốc TPHCM - Long Thành, ùn tắc khó tránh

MINH QUÂN |

Từ ngày 5.9, cầu Long Thành - cây cầu lớn nhất trên tuyến cao tốc TPHCM - Long Thành - Dầu Giây sẽ bước vào giai đoạn sửa chữa kéo dài trong 18 ngày.

3 dự án nghìn tỉ giải cứu kẹt xe cao tốc TPHCM - Long Thành

MINH QUÂN |

Mở rộng tuyến chính và đường dẫn lên 8 - 10 làn, xây nút giao An Phú tổng vốn 19.400 tỉ đồng, kỳ vọng giúp cao tốc TPHCM - Long Thành - Dầu Giây thoát kẹt xe.