Long Thanh Bridge repairs completed ahead of schedule

MINH QUÂN |

Expansion joint repair work at Long Thanh bridge on the Ho Chi Minh City - Long Thanh - Dau Giay expressway was completed 4 days ahead of schedule.

According to an announcement from Vietnam Expressway Engineering Services Joint Stock Company (VEC E), the repair of Long Thanh Bridge (from Dong Nai to Ho Chi Minh City) will take place from September 5 and be completed on September 19.

After the work was completed, from 11pm on September 19, the site was returned to allow vehicles to circulate through 2 lanes, helping to reduce traffic congestion in the area.

However, to ensure the quality of concrete at the joint between the expansion joint and the asphalt concrete surface, VEC E continues to limit the speed at the Long Thanh bridge repair location until September 23. After this time, traffic speed will be restored to normal.

Previously, from September 5, the expansion joint on Long Thanh bridge began to be repaired after discovering a broken rail.

The narrowing of the road surface while the traffic volume on the route is very large has caused congestion on the bridge and highway in Dong Nai.

The Ho Chi Minh City - Long Thanh - Dau Giay Expressway, with a total length of 55km and a scale of 4 lanes, was put into operation in 2016. Traffic volume on this expressway is continuously increasing, an average of nearly 12% per year, so traffic jams are frequent.

It is expected that by 2026, when Long Thanh airport comes into operation, traffic pressure on this highway will increase even more strongly.

In that context, the expansion of the expressway is being studied with the option of expanding the section from the Ring Road 2 intersection (Thu Duc City) to the Bien Hoa - Vung Tau expressway intersection.

Accordingly, the section from the Ring Road 2 intersection to the Ring Road 3 intersection will be invested with 8 lanes according to the plan. The section from the Ring Road 3 intersection to the Bien Hoa - Vung Tau expressway intersection will be invested with 10 lanes according to the plan.

Long Thanh Bridge will be invested in building a new bridge unit, with a scale similar to the current bridge, organizing traffic exploitation with a scale of 10 lanes (no emergency lanes will be arranged in advance, combined with traffic organization with 5 lanes on each side, 35m wide).

This expansion project has a total investment of nearly 15,000 billion VND. If approved, it will be implemented and completed by the end of 2027.

MINH QUÂN
RELATED NEWS

Venezuela appoints interim President after Maduro arrested by the US

|

Ms. Delcy Rodriguez was appointed interim President of Venezuela after the US military campaign to arrest Mr. Maduro.

Wanting a full Tet, many young people struggle to manage spending

|

The pressure of spending at the end of the year and preparing for Tet has caused many students and young people to fall into financial stress.

Phu Quoc quickly handles reflections of room clearance and beach garbage from tourists

|

An Giang - Leaders of Phu Quoc Special Zone have responded to tourists' complaints with quick and drastic handling measures when receiving information.

Ho Chi Minh City expands 4 gateways 2-3 times to eliminate traffic jams

|

Ho Chi Minh City - National Highway 13, National Highway 22, National Highway 1 and Nguyen Huu Tho road will be expanded 2-3 times, started in 2026 and completed in 2028.

Ministry of Health requests investigation into poisoning that killed one person in Son La

|

The Ministry of Health has just sent a document to the Son La Provincial Department of Health requesting urgent investigation and handling of a suspected food poisoning case that occurred in Kich Mang village, Muong Gion commune, Son La province.

Ring Road 2.5 accelerates, people hope to soon end pollution and dust

|

Hanoi - Ring Road 2.5 is accelerating construction, people in Dam Hong area hope to soon end the pollution and dust situation that has lasted for many years.

Bridge on Ring Road 4 receives sufficient land, construction throughout the New Year

|

Hanoi - Leaving the New Year holiday, many engineers and workers stick to the construction site, accelerating the progress of Hong Ha bridge belonging to the Ring Road 4 project in the Capital region.

Ùn tắc kéo dài trên cầu lớn nhất cao tốc TPHCM - Long Thành

CHIẾN QUÂN |

Sáng 5.9, cầu Long Thành (thuộc cao tốc TPHCM - Long Thành - Dầu Giây) ùn tắc kéo dài theo hướng Đồng Nai về TPHCM do rào chắn một nửa mặt cầu để sửa chữa.

Sửa cầu trên cao tốc TPHCM - Long Thành, ùn tắc khó tránh

MINH QUÂN |

Từ ngày 5.9, cầu Long Thành - cây cầu lớn nhất trên tuyến cao tốc TPHCM - Long Thành - Dầu Giây sẽ bước vào giai đoạn sửa chữa kéo dài trong 18 ngày.

3 dự án nghìn tỉ giải cứu kẹt xe cao tốc TPHCM - Long Thành

MINH QUÂN |

Mở rộng tuyến chính và đường dẫn lên 8 - 10 làn, xây nút giao An Phú tổng vốn 19.400 tỉ đồng, kỳ vọng giúp cao tốc TPHCM - Long Thành - Dầu Giây thoát kẹt xe.