Billion-dollar bridge completed but no access road due to site clearance problems

NGUYỄN LUÂN |

Quang Tri - Nhat Le 3 bridge has been basically completed but still has to "wait" when many households have not handed over the site to construct the access road to the bridge.

Waiting for land for 17 households

As of now, Nhat Le 3 bridge (Quang Tri province) has completed about 95% of the volume. Key items such as the ground, steel arches, cable system and railings are basically completed. At the construction site, construction units are focusing efforts on completing the lighting system, sidewalks and auxiliary items, mainly concentrated at the bridgehead in Quang Ninh commune.

Although the bridge section is almost completed and the lighting system has been operating, the project has not yet been able to reach the finish line due to problems in site clearance (GPMB) in the access road section from the old Bao Ninh commune (now Dong Hoi ward).

Hiện trạng cầu Nhật Lệ 3 đoạn đường dẫn phía xã Quảng Ninh. Ảnh: Nguyễn Luân
The access road to the bridge in Quang Ninh commune has been basically completed. Photo: Nguyen Luan

At the construction site in Quang Ninh commune, workers are constructing sidewalks, installing traffic lights, lighting poles and auxiliary items. On the contrary, the foot of the bridge in Dong Hoi ward is almost "motionless" due to the lack of clean ground.

Answering Lao Dong Newspaper, a representative of the Quang Tri Provincial Department of Finance said that the reason for the delay stems from the fact that some households have not agreed on boundaries and land origin, requesting re-measurement. Out of a total of 17 households still facing difficulties, 11 households are subject to resettlement and 6 households are compensated with land.

The bridge section is basically completed. The coastal road section has been constructed for about 1.8 - 2.2km. Currently, only 17 households near the riverbank are stuck. The goal is to complete the relocation in June 2026 to deploy construction, ensuring the completion of the entire project before December 31, 2026," said a representative of the Department of Finance.

Điểm nghẽn mặt bằng phía phường Đồng Hới khiến công tác thi công đường dẫn lên cầu bị đình trệ. Ảnh: Nguyễn Luân
The site congestion in Dong Hoi ward caused the construction of the access road to the bridge to be stalled. Photo: Nguyen Luan

Currently, local authorities are strengthening mobilization of people, and at the same time speeding up procedures for applying compensation prices in order to soon hand over the site to serve the final construction phase.

Considering coercion options

Faced with the risk of slow progress due to site clearance congestion, on April 17, Quang Tri Provincial People's Committee issued an urgent directive document, requesting to speed up the completion of site clearance for the Nhat Le 3 bridge project and the bridge access road.

Công trường không có công nhân, máy móc vì chưa có mặt bằng thi công. Ảnh: Nguyễn Luân
The construction site has no workers or machinery because there is no construction site yet. Photo: Nguyen Luan

The Provincial People's Committee requests the People's Committee of Dong Hoi Ward and the Project Management Board for Investment, Construction and Development of Dong Hoi Land Fund to focus on completing relevant procedures in the shortest time. The public disclosure, appraisal and approval of compensation plans for the remaining agricultural land plots (6 cases, area of about 0.15ha) must be completed before April 27 so as not to affect the construction in the East.

For 17 cases of resettlement or land exchange, the compensation and support plan must be completed, publicized and completed in April 2026. After that, relevant units need to closely coordinate to complete legal documents and quickly implement the next steps in accordance with regulations.

Complete land recovery procedures for cases that have not agreed to receive money and hand over land in the resettlement area. Consolidate dossiers to issue decisions on land recovery coercion in April 2026.

Trên cầu, công tác rải thảm nhựa đã hoàn thành. Ảnh: Nguyễn Luân
On the bridge, the asphalt paving has been completed, only waiting for the access road. Photo: Nguyen Luan
Toàn cảnh cầu Nhật Lệ 3 bắc qua sông Nhật Lệ. Ảnh: Nguyễn Luân
Overview of Nhat Le 3 bridge across the Nhat Le River. Photo: Nguyen Luan

In addition, the Provincial People's Committee requested localities to comprehensively review the implementation process, direct land clearance consulting units to work closely, limit errors in dossiers, and avoid the situation of having to redo, causing prolonged time. Cases of delay or failure to complete tasks will be considered for responsibility according to regulations.

Nhat Le 3 bridge spans the Nhat Le River, belongs to the Coastal Road and Nhat Le 3 Bridge Project, has a total length of more than 2.8km, a total investment of about 1,300 billion VND, implemented in the period 2022 - 2026.

This is a key transport project, playing an important role in completing urban infrastructure, connecting both banks of the Nhat Le River, reducing the load on existing roads and expanding the space for coastal tourism urban development.

The bridge is designed to be permanent with steel and prestressed reinforced concrete, with modern arch structure, creating architectural highlights. The approach bridge system uses simple spans, ensuring economy and long-term durability.

The road at both ends of the bridge meets the standards of a main urban road, design speed of 60km/h, roadbed width from 23.5m to 54.5m with 4 lanes. The road surface uses asphalt concrete on a gravel-grade base, meeting long-term exploitation requirements and large load capacity.

NGUYỄN LUÂN
RELATED NEWS

Quang Ngai will start construction of the 2,200 billion VND bridge on June 30, 2026

|

Quang Ngai - Tra Khuc 1 Bridge Project with a total investment of nearly 2,200 billion VND will be started on June 30, 2026.

Ho Chi Minh City to have another bridge across the Saigon River put into use soon

|

Ho Chi Minh City - March 19, units are urgently constructing asphalt paving for Binh Goi bridge across the Saigon River connecting Thuan An ward and Binh My commune.

Live volleyball VTV Binh Dien Long An - Giang To

|

Live match between VTV Binh Dien Long An - Jiangsu at the VTV9 - Binh Dien 2026 International Women's Volleyball Tournament taking place at 8:00 PM.

Ho Chi Minh City deploys meaningful ticket ATMs, people in need can travel on Metro Line 1 for free

|

Ho Chi Minh City deploys "Gratitude ticket ATM" at Metro Line 1, supporting workers, students in difficult circumstances to travel on trains for free using socialized sources.

Proposal to expand the "Three Assistance" model for Trade Unions to accompany workers

|

Dong Thap - Workers expect the "Three Assistants" model including support - assisted reproduction - capital support to be expanded, so that the Trade Union can accompany workers.

Instructions on switching from old gasoline cars to electric cars at Green Transit Day 2026

|

On Green Transformation Day 2026, people can bring old gasoline cars to participate in the "gasoline to electricity exchange" program and directly experience new electric vehicle lines.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

Quang Ngai will start construction of the 2,200 billion VND bridge on June 30, 2026

ĐÔNG GIANG |

Quang Ngai - Tra Khuc 1 Bridge Project with a total investment of nearly 2,200 billion VND will be started on June 30, 2026.

Ho Chi Minh City to have another bridge across the Saigon River put into use soon

ĐÌNH TRỌNG |

Ho Chi Minh City - March 19, units are urgently constructing asphalt paving for Binh Goi bridge across the Saigon River connecting Thuan An ward and Binh My commune.

Bất an với nhiều cây cầu hẹp nằm trên tuyến đường rộng

TRẦN TUẤN |

Hà Tĩnh - Tại phường Hà Huy Tập có nhiều cây cầu hẹp trong khi đường hai đầu cầu rộng đã gây ảnh hưởng, bất an cho người tham gia giao thông.