Thu Thiem 4 bridge worth more than 5,000 billion VND is about to start construction, Ho Chi Minh City design competition

MINH QUÂN |

Ho Chi Minh City - Thu Thiem 4 bridge, more than 2 km long, 8 lanes wide across the Saigon River, connecting the South and East, will be started in the third quarter of this year, and is currently under design competition.

Ho Chi Minh City People's Committee has just issued a decision approving the "Architectural Plan for Thu Thiem 4 Bridge" competition plan, belonging to component project 2 of the Thu Thiem 4 Bridge construction project.

The Thu Thiem 4 bridge project spans the Saigon River with 8 lanes, including 6 motorized lanes and 2 mixed lanes. The total length of the entire route is about 2.16 km, of which the main bridge section is about 1.635 km long, with a navigation clearance of 15 m.

Phối cảnh cầu Thủ Thiêm 4 rộng 8 làn xe.  Ảnh: Sở Xây dựng TPHCM
Perspective of Thu Thiem 4 bridge with 8 lanes. Photo: Ho Chi Minh City Department of Construction

The starting point of the project is Nguyen Van Linh street (near Tan Thuan 2 bridge), the ending point connects Nguyen Co Thach street in Thu Thiem New Urban Area.

Thu Thiem 4 Bridge is expected to start construction in the third quarter of 2026 and be completed in the fourth quarter of 2028.

Vị trí xây cầu Thủ Thiêm 4. Ảnh: Anh Tú
Location of Thu Thiem bridge construction 4. Photo: Anh Tu
Hướng tuyến cầu Thủ Thiêm 4. Ảnh: Sở Xây dựng TPHCM
Direction of Thu Thiem bridge route 4. Photo: Ho Chi Minh City Department of Construction

The goal of the competition is to find architectural options with high feasibility, modernity, and uniqueness, creating landscape highlights on the traffic axis connecting Thu Thiem New Urban Area with the Southern area of Ho Chi Minh City.

The project is expected not only to relieve traffic pressure in the southern gateway area but also create strong development momentum for both the South and the East, especially the Thu Thiem New Urban Area - where the Vietnam International Finance Center is located.

The competition is expanded to design consulting units at home and abroad, or joint ventures with sufficient capacity and experience in the fields of architecture, planning and bridges and roads. The expected competition time is about 85 days, from March 17, 2026.

Một phối cảnh khác của cầu Thủ Thiêm 4.  Ảnh: Sở Xây dựng TPHCM
Another perspective of Thu Thiem bridge 4. Photo: Ho Chi Minh City Department of Construction

The Thu Thiem 4 bridge project has been approved for investment policy by the Ho Chi Minh City People's Council since February 2026 with a total capital of more than 5,603 billion VND, divided into two component projects.

Component project 1 serves compensation, support and resettlement work with a total investment of about 1,385 billion VND. Component project 2 is the bridge construction part with a total investment of about 3,678 billion VND.

To ensure progress, the Ho Chi Minh City People's Committee has also issued a document requesting departments, branches and related localities to urgently and synchronously deploy the work.

The Ho Chi Minh City Traffic Construction Investment Project Management Board (the investor) proactively coordinates with localities to review planning, organize architectural design competitions and develop detailed implementation plans.

According to the plan, the project will recover about 16.7 hectares of land, affecting 136 cases, of which 73 cases must be completely cleared. The city requires compensation, support and resettlement to ensure that people's living conditions are equal to or better than their old residence.

Cầu Thủ Thiêm 4 khi hoàn thành giúp giảm kẹt xe cửa ngõ phía Nam TPHCM.  Ảnh: Anh Tú
Thu Thiem 4 bridge when completed helps reduce traffic jams at the southern gateway of Ho Chi Minh City. Photo: Anh Tu

The Department of Construction is assigned to preside over guiding, inspecting and supervising the implementation process; the Department of Agriculture and Environment is responsible for guiding compensation and resettlement work; the Department of Planning and Architecture guides architectural design competitions and reviews and adjusts zoning planning when necessary.

The People's Committees of Tan Thuan and An Khanh wards are responsible for coordinating the implementation of compensation, support, resettlement and site clearance, ensuring project progress.

MINH QUÂN
RELATED NEWS

Can Gio bridge is expected to be joined at the end of 2028, operation from June 2029

|

Ho Chi Minh City - Can Gio bridge after the groundbreaking ceremony is being accelerated with procedures to start construction in June, close at the end of 2028 and put into operation in June 2029.

HCMC proposes 5 options to build Thu Thiem 4 bridge but has not yet finalized

|

HCMC The Thu Thiem 4 bridge project across the Saigon River, connecting the Thu Thiem urban area, has not yet been able to finalize the construction plan because the clearance has not been determined.

Current status of Duc Giang chemical plant after a series of leaders were prosecuted

|

Lao Cai - Recording the current status of the factory after initiating a case at Duc Giang Chemical Group shows that the units are still operating, and workers are working normally.

Black wastewater from illegal discharge culverts flows directly into Nha Trang sea

|

Khanh Hoa - Functional agencies are verifying the source of illegal discharge, after a stream of black, cloudy, and smelly wastewater appeared flowing directly into Nha Trang sea.

Land plot prices increase sharply, real homebuyers cautiously spend money

|

Land plot prices have increased sharply in many areas, leading to a cautious and reserved mentality among real homebuyers.

"What if the whole life isn't brilliant?"

|

A seemingly simple question that makes many young people ponder: is a life that is not too prominent regrettable?

El Nino 2026 may be more severe, Southeast Asian weather is strongly affected

|

Southeast Asia may face stronger El Nino, the risk of prolonged heat and drought.

Reasons why My Tam is criticized and Van Mai Huong is praised when venturing into film

|

With roles already in movies, My Tam shows that the female singer seems to only consider movies as a media channel to further promote her image.

Can Gio bridge is expected to be joined at the end of 2028, operation from June 2029

MINH QUÂN |

Ho Chi Minh City - Can Gio bridge after the groundbreaking ceremony is being accelerated with procedures to start construction in June, close at the end of 2028 and put into operation in June 2029.

HCMC proposes 5 options to build Thu Thiem 4 bridge but has not yet finalized

MINH QUÂN |

HCMC The Thu Thiem 4 bridge project across the Saigon River, connecting the Thu Thiem urban area, has not yet been able to finalize the construction plan because the clearance has not been determined.

Hình ảnh vị trí dự kiến xây cầu Thủ Thiêm 4 nối TP Thủ Đức và Quận 7

Anh Tú - Ngọc Ánh |

Theo Sở GTVT TPHCM, Cầu Thủ Thiêm 4 (bắc qua sông Sài Gòn, nối TP Thủ Đức và Quận 7) được xác định là một trong các công trình hạ tầng giao thông quan trọng, cần ưu tiên đầu tư để từng bước hoàn chỉnh đồng bộ hệ thống hạ tầng kỹ thuật chung toàn khu vực.