On September 16, the People's Committee of Quang Tri province confirmed and urged the Quang Tri Provincial Construction Investment Project Management Board to urgently overcome the shortcomings of completed construction items of the Ba Ho - Ban Chua Irrigation System project (abbreviated as Ba Ho - Ban Chua project).
Accordingly, in May 2024, the People's Committee of Quang Tri province concluded the inspection of the acceptance of completed construction items of the above project. In which, it pointed out the shortcomings and defects in the completed construction items.
However, the project implementation unit, the Quang Tri Provincial Construction Investment Project Management Board, has been slow to implement the instructions of the Provincial People's Committee, only handing over one more project and organizing the construction of the Tan Xuan water tank at 50% of the volume.
Therefore, the People's Committee of Quang Tri province requests the Quang Tri Provincial Construction Investment Project Management Board to urgently overcome the shortcomings and defects of completed construction items to ensure compliance with the approved design documents. Next, send the project completion documents to specialized construction management departments to conduct inspection, approval and acceptance in accordance with regulations, and hand over the works for use, bringing about efficiency before September 30, 2024.
It is known that the Ba Ho - Ban Chua project has a total investment of more than 262 billion VND, implemented in Cam Lo district from 2018 - 2021 with many items such as pumping stations, lakes and intra-field canal systems, dams...
Although the project construction period has ended, only half of the works and items have been completed and handed over to the management unit. Among the completed works put into use, works such as Dau Binh 1 pumping station (Cam Tuyen commune), Quat Xa 2 pumping station (Cam Thanh commune) ... have not promoted investment efficiency and usage efficiency, causing serious consequences.
Some unfinished construction works and items, although not yet in use, have been degraded, damaged, cracked, and have had equipment stolen, causing waste of state budget funds that have been paid.
To avoid waste and put invested projects into operation, the People's Committee of Quang Tri province has agreed to extend the implementation period of the Ba Ho - Ban Chua project until June 30, 2025. For completed projects that have not been effective and have violations, the People's Committee of Quang Tri province requires correction.