This afternoon, Long Thanh airport is expected to welcome flights from Tan Son Nhat

HÀ ANH CHIẾN |

Dong Nai - This afternoon, December 15, Long Thanh airport is expected to receive a test flight from Tan Son Nhat airport with Boeing 787.

According to the plan, this afternoon, December 15, Long Thanh airport will conduct a test technical flight from Tan Son Nhat airport to Long Thanh with Boeing 787 aircraft, preparing for the first official flight to Long Thanh airport on December 19.

Accordingly, a code E aircraft (expected to be a Boeing 787, the largest aircraft in Vietnam at present) will fly from Tan Son Nhat airport to Long Thanh airport and then return to Tan Son Nhat.

Technical flights will only have flight crews and technical staff, not carrying passengers or goods.

Vietnam Airlines will conduct technical flights.

Toan canh duong cat ha canh so 1 va nha ga hanh khach san bay Long Thanh. Anh: ACV
Panorama of runway No. 1 and Long Thanh airport passenger terminal. Photo: ACV

On December 19, Long Thanh airport will welcome the first official flight. It is expected that 3 aircraft of the 3 airlines departing from Noi Bai airport will land at Long Thanh airport one by one, then return to Noi Bai.

Mr. Nguyen Tien Viet - Deputy General Director in charge of Vietnam Airports Corporation (ACV) said that up to now, the airport's connecting transport infrastructure has been completed, the work of planting trees and completing the landscape has been basically completed.

All preparations along with equipment are ready, ensuring the first flight taking place on December 19, Mr. Viet said.

HÀ ANH CHIẾN
RELATED NEWS

Prime Minister Pham Minh Chinh inspects Long Thanh airport before the first flight

|

Dong Nai - On the afternoon of December 14, Prime Minister Pham Minh Chinh and the Central working delegation inspected Long Thanh airport before the first technical flight.

Long Thanh airport adds 1,000 more personnel to prepare for the first flight

|

Dong Nai - More than 1,000 human resources have been added to the Long Thanh airport project to prepare for the first flight on December 19.

Overview of Long Thanh airport 1 week before the first flight

|

Dong Nai - On December 19, Long Thanh airport will officially welcome the first flight after more than 2 years of construction of the passenger terminal.

Small traders worry about shortage of goods to sell, Tet peach blossom market becomes bustling soon

|

Hanoi - Small traders at Quang An market are worried about supply shortages, the Tet peach market has been bustling since early morning, while peach prices are forecast to continue to increase as Tet approaches.

People release buffaloes and crawl to the edge of the Vinh Hao - Phan Thiet expressway

|

Lam Dong - From the locations where the barbed wire fence was cut, people released buffaloes and cows into the corridor next to the Vinh Hao - Phan Thiet expressway.

It's a bit of a bit of a bit of a bit of a bit of a bit.

Vinh Chau purple onions in season, rural workers have more jobs

|

Can Tho - Vinh Chau is not only famous for its purple onion fields but also creates stable livelihoods for thousands of local workers.

US economy accelerates in 2025, opening a brighter growth period in 2026

|

The US economy recorded strong growth in 2025, GDP broke through in the third quarter and consumption maintained its momentum, creating a positive foundation for the outlook for 2026.

How Thanh Nhan deceived the U23 Korean goalkeeper

|

Striker Thanh Nhan took the decisive penalty to bring home a bronze medal for U23 Vietnam at the 2026 AFC U23 Championship.

Prime Minister Pham Minh Chinh inspects Long Thanh airport before the first flight

HÀ ANH CHIẾN |

Dong Nai - On the afternoon of December 14, Prime Minister Pham Minh Chinh and the Central working delegation inspected Long Thanh airport before the first technical flight.

Long Thanh airport adds 1,000 more personnel to prepare for the first flight

HÀ ANH CHIẾN |

Dong Nai - More than 1,000 human resources have been added to the Long Thanh airport project to prepare for the first flight on December 19.

Overview of Long Thanh airport 1 week before the first flight

HÀ ANH CHIẾN |

Dong Nai - On December 19, Long Thanh airport will officially welcome the first flight after more than 2 years of construction of the passenger terminal.