Long Thanh airport adds 1,000 more personnel to prepare for the first flight

HÀ ANH CHIẾN |

Dong Nai - More than 1,000 human resources have been added to the Long Thanh airport project to prepare for the first flight on December 19.

On December 13, information from Vietnam Airports Corporation (ACV) said that it had increased 1,000 more workers (compared to early November 2025), working day and night to prepare for the first technical flight to land at Long Thanh airport on December 19, bringing the total number of officers, engineers, experts, and workers on the construction site to more than 15,000 people and 3,000 machines.

In particular, focusing on completing key items such as runway No. 1, taxiway - aircraft parking lot, installing passenger terminal equipment.

With runway No. 1, the contractor is focusing on completing the drainage ditches, preventing slides, examining the expansion joints, painting the lines, and general cleaning.

On the evening of December 11, the entire flight light system and signs at runway No. 1 were successfully operated and operated stably. This is a lighting system that meets CAT II standards of ICAO (international Civil Aviation Organization).

The system is installed along the 4 km length of the runway, landing line 1 and 1.8 km of the approach area at both ends of the runway (each end is 900 m long). At the same time, the airspace medium-voltage was energized to supply the accurate runway system (ILS/DME) and the automatic meteorological monitoring system (AWOS).

Toan canh san bay Long Thanh thi cong ve dem. Anh: ACV
Panorama of Long Thanh airport under construction at night. Photo: ACV

At Long Thanh airport's passenger terminal, the construction and installation of glass walls and steel structures have been basically completed; equipment is being urgently installed. With the cable-stayed pipeline system, 26 sets of cable-stayed pipes (the entire terminal has 64 sets) have been transported to the construction site, and 16 sets are being installed.

The luggage screening equipment system has transported 53/57 checked baggage screening equipment and 145/256 hand-carried baggage screening equipment to the construction site; security screening machines and screening equipment are being installed.

The aircraft mooring system has transported 100 sets of VDGS (nearly 80%) to the construction site. The contractor is urgently constructing beams and installing equipment at many Gate locations ( gates). At the same time, speed up the installation and completion of the luggage handling system; escalators, pedestrian elevators; elevators.

The aircraft parking lot has completed the drainage system and tunnel for ground clearance equipment; basically completed the ground structure, and constructed a layer of cement concrete.

On the connecting traffic route, the contractor is rushing to plant trees, install lighting systems, and signs.

The Long Thanh International Airport Project Management Board has also deployed the work of connecting and energizing the Energy Center - a key item in providing electricity to all passenger terminals. The successful connection and energization not only creates conditions for testing and testing of electrical and technical systems, but is also an important preparation step to synchronously deploy items in the final stage.

Currently, items at Long Thanh airport such as: Inland traffic and technical infrastructure; fuel supply system; 2nd runway; installation and supply of airport management system equipment contractors are also speeding up construction, ensuring the synchronous completion of all items at Long Thanh airport in the first half of 2026.

HÀ ANH CHIẾN
RELATED NEWS

Overview of Long Thanh airport 1 week before the first flight

|

Dong Nai - On December 19, Long Thanh airport will officially welcome the first flight after more than 2 years of construction of the passenger terminal.

Long Thanh airport runway No. 1 lights up to prepare for the first flight

|

Dong Nai - Long Thanh Airport lights up to prepare for the technical flight on December 19.

Many people in Quang Ngai hospitalized due to suspected food poisoning

|

Quang Ngai - Patients hospitalized with symptoms of suspected food poisoning after eating bread at H.V. noodle shop.

Opening of TECHFEST 2025: Spreading the spirit of creative startups throughout society

|

On the evening of December 13, Prime Minister Pham Minh Chinh attended and gave a speech at the opening ceremony of TECHFEST Vietnam 2025.

Fighting escalates, Cambodia closes all border gates with Thailand

|

Cambodia temporarily suspended all border crossings with Thailand on December 13.

The weightlifting story of the 33rd MMA SEA Games champion

|

Tran Ngoc Luong went through a stressful weight loss when he had to lose nearly 3.6kg right before the MMA final at the 33rd SEA Games.

Resolutely resolve the land acquisition of a supermarket project in Phu Tho

|

After many years of being "stuck" in a supermarket project, dozens of plots of land of people in Phu Tho are about to be returned when the relevant parties get involved.

SEA Games 33 Medal Schedule on December 13

|

Updated total medal table of the 33rd SEA Games on December 13.

Overview of Long Thanh airport 1 week before the first flight

HÀ ANH CHIẾN |

Dong Nai - On December 19, Long Thanh airport will officially welcome the first flight after more than 2 years of construction of the passenger terminal.

Bảo vệ tuyệt đối an toàn sự kiện chuyến bay đầu tiên tại sân bay Long Thành

HÀ ANH CHIẾN |

Đồng Nai - Chủ tịch UBND tỉnh đề nghị bảo vệ tuyệt đối an toàn sự kiện khánh thành, khởi công các dự án trọng điểm, chuyến bay đầu tiên sân bay Long Thành.

Long Thanh airport runway No. 1 lights up to prepare for the first flight

HÀ ANH CHIẾN |

Dong Nai - Long Thanh Airport lights up to prepare for the technical flight on December 19.