National Highway 50 coal investor stuck in land clearance, Binh Chanh district speaks out

MINH QUÂN |

HCMC - Binh Chanh District affirmed that it has completed site clearance for the project to upgrade and expand National Highway 50.

The project to upgrade and expand National Highway 50 will start construction at the end of 2022, with a total investment of nearly 1,500 billion VND. The project is nearly 7 km long, starting from the intersection of Nguyen Van Linh Avenue (Binh Chanh District) to the end point bordering Long An Province.

The road is expanded from 8 m to 34 m, including 6 lanes. Of which, more than 4 km is a new parallel route, the rest is to expand the existing route.

According to the report sent to the Ho Chi Minh City People's Committee on April 23, the People's Committee of Binh Chanh District confirmed that the site clearance work for the National Highway 50 expansion project has been completed.

However, on May 7, the Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Board) sent a document to the People's Committee of Binh Chanh District, stating that there are still 3 locations that have not been handed over the site, including: the parallel road section of National Highway 50, the existing National Highway 50 section and the Ong Thin bridge area.

Explaining this issue at a regular press conference on the afternoon of May 15, Mr. Nguyen Huu Tri - Deputy Head of the Compensation and Site Clearance Board of Binh Chanh District - said that the reason comes from the investor's delay in receiving the site or slow construction, causing people to change their intentions and hinder construction.

According to Mr. Nguyen Huu Tri, at the parallel road of National Highway 50, a household with a land area of 627.4 m2 in the project invested by Khang Phuc Housing Investment and Trading Company Limited, of which 615 m2 is within the boundary of the National Highway 50 upgrade project.

This household has handed over the site since April 11, 2025. The Compensation and Site Clearance Board has notified the Traffic Board to receive the vacant site, however, it was not until May 9 that the investor took over this position.

Doan song hanh Quoc lo 50 giao duong Trinh Quang Nghi duoc ban giao mat bang. Anh: Anh Tu
The parallel section of National Highway 50 intersecting with Trinh Quang Nghi Street was handed over the site. Photo: Anh Tu

In the existing National Highway 50 area, a household was affected with an area of 1,259.1 m2 in the Garbage Project Zone II (of which 201 m2 is within the National Highway 50 project boundary). The Compensation Board has completed compensation, support and resettlement policies.

Although this household agreed to hand over the site in early April 2025, due to construction delays, they changed their minds. Thanks to the mobilization of local authorities, the household later agreed to continue construction.

At Ong Thin bridge area, the last household to demolish houses and works and hand over the site from April 10, 2024. However, the construction is not taking place continuously, causing frustration among the people. After the contact and mobilization process of the government, this household also agreed to resume construction.

"We affirm that up to now, the entire site for the construction of the National Highway 50 expansion project has been 100% handed over" - Mr. Nguyen Huu Tri emphasized.

According to the Traffic Department, the parallel route of National Highway 50 has completed about 90% of the volume, the entire project has reached about 67%.

The Traffic Department is committed to speeding up the progress of the remaining part after having enough land, completing the entire project by the end of this year.

MINH QUÂN
RELATED NEWS

1,500 billion VND project to expand the southern gateway of Ho Chi Minh City after more than 2 years of construction

|

HCMC - The project to expand National Highway 50 through Binh Chanh District has reached 67% of the volume, and there are still some site clearance problems affecting the construction progress.

Ho Chi Minh City gateway expansion project: The district has completed site reporting, the investor says there are still problems

|

HCMC - The National Highway 50 expansion project reported by Binh Chanh District has completed site clearance, but the investor said there are still 3 areas that have not been handed over.

Live football Arsenal vs Bournemouth in Premier League

|

The match between Arsenal and Bournemouth takes place at 6:30 p.m. on April 11 (Vietnam time).

Update on gasoline and oil prices on April 11: World oil prices reverse sharply

|

Update on gasoline and oil prices on April 11: In today's trading session, world oil prices reversed to decrease.

Live Nam Dinh vs Hoang Anh Gia Lai in round 18 of V.League 2025-2026

|

Live football match between Nam Dinh and Hoang Anh Gia Lai in round 18 of V.League 2025-2026 at 6:00 p.m. today (April 11).

Ring Road 2.5, Dich Vong - Duong Dinh Nghe section is expected to open to traffic in September

|

Hanoi - Ring Road 2.5, Dich Vong - Duong Dinh Nghe section is expected to be technically opened to traffic in early September if the site is handed over on schedule.

Explaining why the 72 billion VND irrigation project has not been handed over after many pipe bursts

|

Dak Lak - The Provincial Department of Agriculture and Environment has explained the reason for not being able to hand over the 72 billion VND irrigation project after many pipe bursts.

US declares Iran has no cards left at the negotiating table

|

US-Iran negotiations in Pakistan face many obstacles as disagreements on preconditions have not been resolved.

1,500 billion VND project to expand the southern gateway of Ho Chi Minh City after more than 2 years of construction

Anh Tú |

HCMC - The project to expand National Highway 50 through Binh Chanh District has reached 67% of the volume, and there are still some site clearance problems affecting the construction progress.

Ho Chi Minh City gateway expansion project: The district has completed site reporting, the investor says there are still problems

MINH QUÂN |

HCMC - The National Highway 50 expansion project reported by Binh Chanh District has completed site clearance, but the investor said there are still 3 areas that have not been handed over.

TPHCM mở rộng Quốc lộ 50 khơi thông cửa ngõ về miền Tây

MINH QUÂN |

TPHCM - Dự án mở rộng Quốc lộ 50 dài gần 7 km với 6 làn xe giúp giảm ùn tắc giao thông và tăng kết nối TPHCM với các tỉnh miền Tây.