Chairman of Dong Nai Provincial People's Committee criticizes 3 units with very low public investment disbursement rates

HÀ ANH CHIẾN |

Dong Nai - The Provincial People's Committee has just praised and criticized the disbursement results of public investment capital (from October 9, 2025 to October 28, 2025).

Accordingly, by October 28, 2025, the disbursement of the capital plan assigned by the Prime Minister in Dong Nai province reached 43.43%; the disbursement of the capital plan allocated by the Provincial People's Committee in 2025 reached 37.52%.

The Chairman of the Provincial People's Committee commended the Bien Hoa Branch Land Fund Development Center for its high disbursement rate, consecutive with accumulated disbursement from September 10, 2025 to October 28, 2025; 5 units with a high disbursement rate of over 80% according to accumulated disbursement from October 9, 2025 - October 28, 2025, including: Department of Finance, Department of Justice, Project Management Board of Region 7; Project Management Board of Bu Dop area; Project Management Board of Region 1.

The Chairman of the Provincial People's Committee also criticized and corrected 3 units with very low public investment disbursement rates, consecutively according to the accumulated disbursement rate from September 10, 2025 to October 28, 2025, affecting the overall results of the province including: Department of Industry and Trade (disbursement rate of 1.6%); Land Fund Development Center of Cam My branch (disbursement rate of 2.0%); Land Fund Development Center of Dong Nai province (disbursement rate of 6.0%).

The Chairman of the Provincial People's Committee requested agencies, units, localities, and investors to urgently speed up the project implementation progress and disbursement according to regulations to ensure the disbursement rate by December 31, 2025 reaches 100%.

HÀ ANH CHIẾN
RELATED NEWS

Minister of Finance: Many projects have money but cannot be disbursed

|

Explaining to the National Assembly, the Minister of Finance admitted that investment procedures are still cumbersome, many projects have money but cannot be disbursed.

Low public investment disbursement, Ca Mau adjusts capital for a series of projects

|

Ca Mau - On November 13, at the 4th session (special session), the People's Council of Ca Mau province passed a resolution to adjust the capital of a series of projects.

Reasons for Cao Bang's slow disbursement of public investment capital for many years

|

Cao Bang - According to Chairman of the Provincial People's Committee Le Hai Hoa, only a change in thinking can bring good results in public investment disbursement.

Deadline for supporting businesses affected by US counterpart taxes

|

The Prime Minister requested that specific support plans for businesses affected by US countervailing tax policies be completed in November.

New survey results on President Trump's support rate

|

President Donald Trump's support rate is affected by the handling of the investigation into the proxy billionaire Jeffrey Epstein.

The current status of the project has lasted for nearly 2 decades, affecting nearly 1,000 investors in Quang Ninh

|

Quang Ninh - Many people have invested in the project but have not received red books for nearly 2 decades, despite many meetings and directives.

River water rises rapidly, many areas in Dak Lak are at risk of flash floods

|

Dak Lak - The water level of major rivers in the province continues to rise, possibly above alert level 3, with the risk of causing flash floods and landslides on a large scale.

Preschool teacher in mountainous Nghe An, struggling to double

|

Nghe An - In the mountainous area of Nhon Mai, teachers of Mai Son Kindergarten still attend classes, encouraging each student to return to school.

Minister of Finance: Many projects have money but cannot be disbursed

CAO NGUYÊN |

Explaining to the National Assembly, the Minister of Finance admitted that investment procedures are still cumbersome, many projects have money but cannot be disbursed.

Low public investment disbursement, Ca Mau adjusts capital for a series of projects

NHẬT HỒ |

Ca Mau - On November 13, at the 4th session (special session), the People's Council of Ca Mau province passed a resolution to adjust the capital of a series of projects.

Reasons for Cao Bang's slow disbursement of public investment capital for many years

Tân Văn |

Cao Bang - According to Chairman of the Provincial People's Committee Le Hai Hoa, only a change in thinking can bring good results in public investment disbursement.