The Western Gateway of Ho Chi Minh City is about to escape traffic jams thanks to 5 major projects

MINH QUÂN |

Expanding National Highway 1, building an overpass at Bon Xa intersection, expanding Phan Anh and Vinh Loc streets, and completing Ba Hom bridge to help relieve traffic jams at the western gateway of Ho Chi Minh City.

Expanding National Highway 1

The largest of these projects is the expansion of National Highway 1 (Binh Chanh district), from Kinh Duong Vuong street to the Long An border.

National Highway 1 is the main route connecting Ho Chi Minh City with the Western provinces, but currently the road surface is only 20-25m wide with 4-6 lanes, not enough to meet the increasing traffic volume.

Quoc lo 1 doan qua huyen Binh Chanh thuong xuyen un tac.  Anh: Minh Quan
National Highway 1 through Binh Chanh District is often congested. Photo: Minh Quan

According to the plan, this road section will be expanded to 52m with 8 lanes, with a total investment of nearly 12,900 billion VND, of which nearly 7,700 billion VND will be spent on site clearance.

The Ho Chi Minh City Department of Transport is preparing a pre-feasibility study report to implement the project under the BOT (build-operate-transfer) model. The project is expected to start construction at the end of 2025 and be completed in 2028.

Expanding Vinh Loc road

Vinh Loc Street is an important arterial road at the western gateway of Ho Chi Minh City, connecting Binh Chanh District, Binh Tan District and Hoc Mon District. However, with the current road width of only 7-8m, traffic jams often occur, especially during rush hour.

Duong Vinh Loc se duoc mo rong len 30m. Anh: Anh Tu
Vinh Loc Street will be widened to 30m. Photo: Anh Tu

The Ho Chi Minh City Department of Transport has proposed a project to widen Vinh Loc Street to 30m, with a total investment of VND4,344 billion, using the city's budget.

In addition to the expansion, the project also includes upgrading the Vinh Loc - Tran Van Giau intersection to facilitate easier traffic movement. If approved, the project will be implemented in phases from 2024 to 2027.

Overpass at Bon Xa intersection

Bon Xa Intersection (located between Binh Tan and Tan Phu districts) is the intersection of 6 major roads, including: Binh Long, Thoai Ngoc Hau, Hoa Binh, Phan Anh, Huong Lo 2 and Le Van Quoi. The volume of vehicles moving through this area is very high, leading to serious congestion.

Nut giao nga tu Bon Xa se duoc xay cau vuot de giam un tac. Anh: Anh Tu
The Bon Xa intersection will have an overpass built to reduce traffic congestion. Photo: Anh Tu

To solve this problem, the Ho Chi Minh City Department of Transport has proposed building a two-way overpass in the direction of Le Van Quoi - Hoa Binh.

The overpass is expected to be 280m long and 12m wide, with a total investment of nearly VND2,400 billion, of which land clearance costs account for VND2,091 billion. The project is proposed to be prioritized for implementation in the 2024-2028 period.

Phan Anh Street Expansion

Phan Anh Street, the route connecting Hoa Binh and Ba Hom streets, is also on the list of routes that need to be widened to reduce congestion. Currently, this route is 2km long, but the narrow road surface makes traveling difficult, especially during rush hour.

Duong Phan Anh se duoc mo rong len 30m. Anh: Anh Tu
Phan Anh Street will be widened to 30m. Photo: Anh Tu

The project to widen Phan Anh Street to 30m with a total investment of VND1,750 billion has been proposed by the Department of Transport of Ho Chi Minh City to the People's Committee of Ho Chi Minh City. If approved, the project will be implemented in the period of 2024 - 2030.

Ba Hom Bridge

Ba Hom Bridge is located on Provincial Road 10 in Binh Tan District, 425m long, of which the main bridge is 93m long and 18m wide. The project started in 2018 with a total investment of about 374 billion VND.

Cau Ba Hom du kien thong xe cuoi thang 11 nam nay. Anh: Anh Tu
Ba Hom Bridge is expected to open to traffic at the end of November this year. Photo: Anh Tu

After many years of stagnation due to problems in site clearance, the project was restarted in October 2023. According to plan, Ba Hom Bridge will be opened to traffic at the end of November this year, contributing to reducing traffic congestion in this area.

MINH QUÂN
TIN LIÊN QUAN

Đường 6 làn xe cửa ngõ TPHCM nguy cơ trễ hẹn vì tắc mặt bằng

MINH QUÂN |

TPHCM – Dự án nâng cấp và mở rộng đường Dương Quảng Hàm (quận Gò Vấp) đang đứng trước nguy cơ không hoàn thành đúng tiến độ do vướng mặt bằng.

Cầu xây lâu và đội vốn ở khu Nam TPHCM sắp hoàn thành

MINH QUÂN |

TPHCM - Sau hơn 4 năm khởi công và đội vốn thêm 350 tỉ đồng, cầu Phước Long nối Quận 7 với huyện Nhà Bè dự kiến hoàn thành vào cuối năm 2024.

28 tuyến đường, cây cầu, hầm chui ở TPHCM sắp thông xe

MINH QUÂN |

TPHCM - 28 tuyến đường, cầu, hầm chui sẽ hoàn thành trong năm nay giúp giảm ùn tắc, khơi thông các tuyến huyết mạch cửa ngõ thành phố.

Bàn giao túi vàng bỏ quên trong thùng từ thiện gửi vùng lũ

Đinh Đại |

Lào Cai - Tối 22.9, thông tin từ Công an huyện Bảo Thắng, Công an xã Xuân Quang đã tổ chức bàn giao túi đồ trang sức bằng vàng bỏ quên trong thùng đồ từ thiện.

Thanh Hóa di dời khẩn cấp hơn 200 học sinh ra khỏi điểm sạt lở

QUÁCH DU |

Thanh Hóa - Mưa lớn khiến sạt lở đất vào khu ký túc xá học sinh, ngay sau đó lực lượng chức năng đã di dời khẩn cấp hơn 200 học sinh đến nơi an toàn.

Thể Công Viettel thắng ngược Hà Nội FC tại sân Mỹ Đình

NHÓM PV |

Tối 22.9, Thể Công Viettel đã đánh bại Hà Nội FC với tỉ số 2-1 tại vòng 2 LPBank V.League 2024-2025.

Áo mưa miễn phí ấm lòng người lao động giữa mùa mưa ở TPHCM

NHƯ QUỲNH |

TPHCM - Những chiếc áo mưa được anh Đỗ Thanh Long phát miễn phí cho người lao động khiến mọi người cảm thấy ấm lòng giữa mùa mưa bão.

Tái diễn nạn lang thang ở Cần Thơ, giải pháp nào để tháo gỡ?

Phong Linh - Ngân Tâm |

Trung tâm Bảo trợ xã hội TP Cần Thơ đề xuất giải pháp giúp giảm tình trạng nạn lang thang, ăn xin ở thành phố.

6-lane road at the gateway to Ho Chi Minh City is at risk of being delayed due to land congestion

MINH QUÂN |

HCMC – The project to upgrade and expand Duong Quang Ham Street (Go Vap District) is facing the risk of not being completed on schedule due to land acquisition problems.

Long-standing and over-funded bridge in southern HCMC nears completion

MINH QUÂN |

HCMC - After more than 4 years of construction and an additional capital increase of 350 billion VND, Phuoc Long bridge connecting District 7 with Nha Be district is expected to be completed by the end of 2024.

28 roads, bridges, and underpasses in Ho Chi Minh City are about to open to traffic

MINH QUÂN |

HCMC - 28 roads, bridges, and underpasses will be completed this year to help reduce traffic congestion and clear the city's gateway arteries.