647m of Nhon - Hanoi Railway Station urban railway tunnel has been drilled

Minh Hạnh |

Hanoi – The Urban Railway Management Board (MRB) said that the Nhon – Hanoi Railway Station urban railway project has reached 80.32% of the overall progress.

On the afternoon of January 2, Mr. Nguyen Ba Son - Deputy Head of MRB said that the pilot urban railway project in Hanoi, Nhon - Hanoi station section, has reached 80.32% of the overall progress. Of which, the 8.5km elevated section, from station S1 to station S8, has been completed and put into commercial operation on August 8, 2024.

For the underground section (CP03 package), the progress reached 50.54%. Of which, TBM No. 1 has been in operation since July 30, 2024, and has so far drilled 647m, installing 431 tunnel lining rings. TBM No. 2 is expected to start construction in January 2025.

Regarding the project to build urban railway line No. 2, Nam Thang Long - Tran Hung Dao section, on December 16, 2024, the Prime Minister approved the adjustment of the investment policy. Currently, MRB is mobilizing consultants to complete the project adjustment dossier and submit it to the Hanoi People's Committee for approval.

Regarding land clearance, the depot area with an area to be recovered is 17.58ha, so far the agricultural land has been cleared. The land for agencies, defense land, and residential land is being counted.

For the elevated station, the investor and local authorities have cleared about 92% of the area. For the underground station, about 79% of the area has been cleared.

On June 21, 2024, MRB coordinated with the Railway Project Management Board (Ministry of Transport) to receive documents and files for Line 1 (Ngoc Hoi - Yen Vien).

The Standing Committee of the City Party Committee agreed on the policy of cooperation in researching the extended route 2A (Ha Dong - Xuan Mai) with China Railway Group 6 Limited Company.

For line 3.2 (Hanoi station - Hoang Mai), the Ministry of Planning and Investment has issued a document reporting that it is eligible for the Prime Minister to approve the proposal to use ODA capital. The Board is completing the procedures for selecting contractors for the technical assistance project.

Regarding route No. 5 (Van Cao - Hoa Lac), after the 2024 Capital Law takes effect, the Ministry of Planning and Investment will transfer the Pre-Feasibility Study Report to the city to continue implementation according to its authority.

Minh Hạnh
TIN LIÊN QUAN

Hanoi is about to build 15 urban railway lines with a total length of 616km

|

Hanoi aims to have an urban railway network of 15 routes/sections with a total length of more than 616km by 2065.

New information on the progress of the Nam Thang Long urban railway project

|

Hanoi has completed and submitted to the Prime Minister an adjustment to the investment policy for the Nam Thang Long - Tran Hung Dao urban railway project.

Decentralization and complete decentralization when building urban railways

|

On December 5, Politburo member, Prime Minister Pham Minh Chinh, Head of the State Steering Committee for important national projects and works, key to the transport sector, chaired a meeting of the Government Standing Committee with the Ministry of Transport, the People's Committees of Hanoi and Ho Chi Minh City and relevant ministries and branches on the urban railway system project in Hanoi and Ho Chi Minh City.

Department Director, Commune Chairman in Quang Ngai write retirement application

|

Although he still has many years of work left, the Department Director and Commune Chairman in Quang Ngai wrote a letter requesting early retirement.

Colonel Nguyen Duc Hai appointed Director of Dong Nai Provincial Police

|

The Ministry of Public Security has appointed Colonel Nguyen Duc Hai to the position of Director of Dong Nai Provincial Police.

The Ministry of Home Affairs and the Ministry of Labor, Invalids and Social Affairs will streamline their staff when merging

|

Minister Pham Thi Thanh Tra requested to review and streamline the payroll after merging with the Ministry of Labor, War Invalids and Social Affairs.

Emergency helicopter takes patient from An Bang island to mainland

|

HCMC - The patient was in critical condition, the cause of the illness was not yet determined, so he was quickly taken by helicopter to the mainland for treatment.

Nam Dinh banana cake cart sells hundreds of cakes a day thanks to Xuan Son

|

Nam Dinh - When the image of football player Xuan Son buying banana cakes went viral, cake vendors in Nam Dinh City sold more, especially during the 2024 ASEAN Cup.

Hanoi is about to build 15 urban railway lines with a total length of 616km

Anh Tuấn |

Hanoi aims to have an urban railway network of 15 routes/sections with a total length of more than 616km by 2065.

New information on the progress of the Nam Thang Long urban railway project

PHẠM ĐÔNG |

Hanoi has completed and submitted to the Prime Minister an adjustment to the investment policy for the Nam Thang Long - Tran Hung Dao urban railway project.

Decentralization and complete decentralization when building urban railways

Hà Vinh |

On December 5, Politburo member, Prime Minister Pham Minh Chinh, Head of the State Steering Committee for important national projects and works, key to the transport sector, chaired a meeting of the Government Standing Committee with the Ministry of Transport, the People's Committees of Hanoi and Ho Chi Minh City and relevant ministries and branches on the urban railway system project in Hanoi and Ho Chi Minh City.