Da Nang removes suspended university planning

Nguyễn Linh |

Da Nang - After 27 years of waiting, nearly 800 billion VND has just been approved to definitively clear the remaining area of the Da Nang University Village project.

The University Village Project in Hoa Quy - Dien Ngoc was approved for planning by the Prime Minister in 1997. The project has a total area of 300ha, including 110ha belonging to Hoa Quy ward, Ngu Hanh Son district (now Ngu Hanh Son ward) and 190ha belonging to Dien Ngoc commune, Dien Ban district (now Dien Ban Dong ward).

Up to now, in Ngu Hanh Son ward, compensation and site clearance (GPMB) have been completed for 78.95ha (reaching more than 71%). Meanwhile, the entire area of 190ha located in Dien Ban Dong ward has not yet been compensated.

Da Nang Department of Construction said that on October 14, 2024, the Ministry of Education and Training issued Decision No. 2829/QD-BGDDT approving the investment policy for the compensation, site clearance and construction of technical infrastructure for the remaining 31.05ha area in Ngu Hanh Son ward.

The total investment for this part is expected to be 794.6 billion VND, implemented in the period 2025 - 2028. Currently, the city has approved and implemented resettlement areas to serve the relocation of the University Village from local funding.

The City People's Committee has also proactively supplemented the land fund from the Southwest Resettlement Area of Non Nuoc Stone Craft Village to meet the resettlement needs of this project.

Currently, Da Nang City People's Committee is continuing to work with Da Nang University to propose to the Ministry of Finance and the Ministry of Education and Training to consider prioritizing supplementing the capital plan. The highest goal is to soon complete the remaining 31.05ha in the city, eliminating the situation of " leopard skin" in planning, causing difficulties for management and people's lives.

Nguyễn Linh
RELATED NEWS

20-year slow project in Da Nang

|

Dozens of households in Cam Le ward, Da Nang city have lived in degraded houses for 20 years because the Hoa Cam Industrial Park (IP) project is slow to implement. Despite having land, they cannot build, while their children have to rent houses.

Da Nang hands over "Quang Trung Campaign" houses to 9 households in Ha Nha commune

|

Da Nang - Ha Nha Commune People's Committee handed over Quang Trung Campaign houses to 9 households.

Da Nang must repair National Highway 14G, 14D in April 2026

|

Da Nang - Da Nang requests to complete the overcoming of landslides on National Highway 14G and 14D before April 30, 2026.

Hanoi Party Secretary requests drastic removal of urban bottlenecks

|

Hanoi - Hanoi Party Secretary Nguyen Duy Ngoc requests the Construction sector to thoroughly handle congestion, flooding, and urban bottlenecks.

Live football U23 Korea vs U23 Australia in the U23 Asian Cup quarter-finals

|

Live broadcast of the match between U23 Korea and U23 Australia in the quarter-finals of the 2026 AFC U23 Championship, taking place at 10:30 PM today (January 17).

Live football Man United vs Man City in the Premier League

|

Live football match Man United - Man City in round 22 of the Premier League, taking place at 7:30 PM on January 17 (Vietnam time).

15-year traffic jam at the eastern gateway of Ho Chi Minh City is about to be removed

|

Ho Chi Minh City - The bottleneck on National Highway 1, the section of the new Mien Dong Bus Station - Tan Van, is expected to be expanded from the end of 2026, helping to eliminate traffic jams at the eastern gateway.

Excavation of an ancient tomb nearly 2,000 years old in Quang Ninh

|

Quang Ninh - During the excavation of an ancient tomb nearly 2,000 years old in Vang Danh, Quang Ninh province, many important artifacts were discovered.

20-year slow project in Da Nang

Nguyễn Linh |

Dozens of households in Cam Le ward, Da Nang city have lived in degraded houses for 20 years because the Hoa Cam Industrial Park (IP) project is slow to implement. Despite having land, they cannot build, while their children have to rent houses.

Da Nang hands over "Quang Trung Campaign" houses to 9 households in Ha Nha commune

Trần Thi |

Da Nang - Ha Nha Commune People's Committee handed over Quang Trung Campaign houses to 9 households.

Da Nang must repair National Highway 14G, 14D in April 2026

Nguyễn Linh |

Da Nang - Da Nang requests to complete the overcoming of landslides on National Highway 14G and 14D before April 30, 2026.