On March 4, 2024, the People's Committee of Dak Nong province issued a Decision on the allocation of specific funds to units and localities to carry out the repair of 28 works and items damaged and affected by natural disasters and landslides. miss.
These are places where natural disasters and landslides will occur in 2023. The total implementation cost for these 28 works and projects is 230 billion VND.
However, by early July 2024, most units and localities were still slow in implementing the project. Units and localities have just started preparing and appraising project investment feasibility study reports or construction investment technical and economic reports for project approval. The steps to organize and select construction contractors are still slow.
For example, in Cu Jut district, there are problems in implementing the bridge and residential road project from U3 bon to Ngan Phuong field in Ea T'ling town.
According to Cu Jut District People's Committee, this is the current route. Local people have used it to transport goods since 1990. The demand for people using this route is huge. However, this route is not shown in the approved general planning of Ea T'ling urban area.
According to the leaders of the People's Committee of Dak Nong province, these are projects aimed at overcoming the consequences, that is, restoring the original situation, it will be easier to solve planning factors such as bauxite and urban areas. , traffic road.
Dak Nong province is determined to organize the implementation and disbursement of this capital no later than December 31. 2024 according to regulations. Recently, at a meeting with investors and related units, Vice Chairman of Dak Nong Provincial People's Committee Le Trong Yen requested departments, branches, and People's Committees of districts and cities. Gia Nghia urgently deploys and implements projects.
To do this, investors, relevant departments and branches need to increase coordination and flexibility in implementing and implementing projects.
The general principles that need to be ensured are timeliness, efficiency, openness, transparency, and the right audience. The implementation does not incur additional administrative procedures, ensuring compliance with investment and bidding regulations.