Ensuring the operation of the entire Bien Hoa - Vung Tau expressway from December 2025

Thành An |

HCMC - The National Assembly Delegation requested the entire Bien Hoa - Vung Tau expressway to be exploited in December 2025 according to plan.

On August 12, Working Group No. 2 of the Ho Chi Minh City National Assembly Delegation, led by Mr. Pham Trong Nhan - Vice Chairman of the Ho Chi Minh City Labor Federation, conducted a field survey at the Bien Hoa - Vung Tau Expressway Component 3 project (phase 1), in the former Ba Ria - Vung Tau province.

Reporting to the working group, the Traffic Project Management Board of the region and the Department of Agriculture of Ba Ria - Vung Tau province - the project investor - said that component project 3 is about 19.5 km long, with a total investment of VND 7,216 billion, a scale of 4 complete expressway lanes, 2 emergency lanes... Up to now, the project has completed 100% of the site clearance work in the first phase. Currently, inventory and document preparation are being carried out, and it is expected to hand over the site from September 2025 for some additional items.

The road has basically completed the asphalt concrete surface, painted markings, median strips and fences; lighting system, traffic safety under construction... Of the total 11 bridges on the route, 9 bridges have been completed, the remaining 2 bridges will be completed in September 2025. By the first quarter of 2026, it is expected to start the project to supplement the My Xuan - Ngai Giao - Hoa Binh DT991 intersection.

The construction of additional intersections will not affect the exploitation and operation of the project. According to the investor, it is expected that by December, the entire route will be technically open to traffic in sync with component projects 1 and 2 in Dong Nai. At the same time, it is proposed to allow the use of the former resettlement land fund of Phu My City (about 1,000 lots) to arrange for households within the scope of the additional intersection.

The working group listened to the opinions and recommendations of the investor, and at the same time acknowledged the advantages and difficulties in the project implementation process. Regarding the resettlement proposal, the delegation said it would receive and report, and recommend competent authorities to consider and resolve.

The delegation also requested the investor to ensure the progress of the two bridges under construction; ensure traffic safety when constructing other items. At the same time, it is recommended that the investor propose recommendations so that the entire Bien Hoa - Vung Tau expressway can be exploited in December 2025 according to plan, not just component project 3.

Thành An
RELATED NEWS

Overcoming landslides on Noi Bai - Lao Cai Expressway

|

The initial cause of the landslide on the Noi Bai - Lao Cai Expressway was prolonged heavy rain causing water to penetrate deeply, causing loss of connection between the soil and rock structure at the positive slope.

Approving the project to expand more than 20 km of Ho Chi Minh City - Long Thanh expressway, connecting Long Thanh airport

|

Dong Nai - Vietnam Expressway Corporation (VEC) has just decided to approve the project to expand the Ho Chi Minh City - Long Thanh expressway section.

From August 19, toll collection at the Ring Road 3 intersection with Ho Chi Minh City - Long Thanh - Dau Giay Expressway

|

HCMC - From August 19, Ring Road 3 Station officially collected tolls for the HCMC - Long Thanh - Dau Giay expressway, applying ETC technology, without incurring additional costs.

Ring Road 4 parallel road project: Many bidding packages are about to be completed

|

Hanoi - The bidding packages for the Ring Road 4 parallel road project are ensuring the set progress, including one bidding package that will be completed in March.

Chairman of Vietnam General Confederation of Labour presents Tet gifts at Ha Bac Fertilizer and Chemical Joint Stock Company

|

VGCL President Nguyen Dinh Khang wishes Tet and gives gifts to union members and employees of Ha Bac Fertilizer and Chemical Joint Stock Company (Bac Ninh).

Plan to handle forgotten headquarters and a school in Hue City

|

HUE - Headquarters and a school are abandoned, seriously degraded, garbage and flood mud are encroaching. There needs to be a handling plan to avoid waste.

Military Region 5 prepares to establish Central Military Junior High School

|

The preparation for the establishment of the Central Military School (peacetime) under Military Region 5 was thoroughly discussed.

Tran Temple seal is expected to be distributed to people from 2 am on March 3rd

|

Ninh Binh - It is expected to distribute Tran Temple seals to people and tourists from 2 am on March 3rd (ie, January 15th of the lunar calendar).

Overcoming landslides on Noi Bai - Lao Cai Expressway

Bảo Nguyên |

The initial cause of the landslide on the Noi Bai - Lao Cai Expressway was prolonged heavy rain causing water to penetrate deeply, causing loss of connection between the soil and rock structure at the positive slope.

Approving the project to expand more than 20 km of Ho Chi Minh City - Long Thanh expressway, connecting Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - Vietnam Expressway Corporation (VEC) has just decided to approve the project to expand the Ho Chi Minh City - Long Thanh expressway section.

From August 19, toll collection at the Ring Road 3 intersection with Ho Chi Minh City - Long Thanh - Dau Giay Expressway

Anh Tú |

HCMC - From August 19, Ring Road 3 Station officially collected tolls for the HCMC - Long Thanh - Dau Giay expressway, applying ETC technology, without incurring additional costs.