Speed up the progress of Phuoc Khanh bridge, an important bottleneck of Ben Luc - Long Thanh expressway

Anh Tú |

HCMC - Phuoc Khanh Bridge across Long Tau River is urgently under construction, speeding up progress to complete the Ben Luc - Long Thanh Expressway project by 2026.

These days, at the Phuoc Khanh bridge construction site across the Long Tau River, hundreds of engineers and workers are working urgently, machinery is operating day and night. The first tangled cables were stretched at pillars P15 (Can Gio side) and P16 (Nhon Trach side), marking an important step forward for the project.

Toan canh cau Phuoc Khanh nhin tu thuong luu song Long Tau. Ảnh: Anh Tu
Panorama of Phuoc Khanh Bridge seen from the upper reaches of Long Tau River. Photo: Danh Quynh
Den nay, tru chinh P15 (phia Can Gio) va P16 (phia Nhon Trach) da duoc lien nha thau len bo cap day vang dau tien
Up to now, the main pillars P15 (Can Gio side) and P16 (Nhon Trach side) have been strengthened by the joint contractor with the first cable-stayed cable. Photo: Danh Quynh

At Nhon Trach shore, teams installed steel piles, prepared concrete pumps for the bridge deck and burned girders. Right at the foot of the bridge, the waterway concrete pumping station is operating continuously, bringing the concrete flow to an altitude of hundreds of meters. On both sides of the river, dozens of bridge piers have been basically completed, many sections are waiting for asphalt paving, installing railings, lighting and drainage systems.

May moc hang nang hoat dong lien tuc tren cong truong. Ảnh: Danh Quynh
Machinery is operating continuously at the construction site. Photo: Danh Quynh
Nha thau lap dat cot thep tai tru P16 (bo Nhon Trach), chuan bi bom be tong cho ban mat cau va dot dam G2. Ảnh: Danh
The contractor installed steel piles at pillar P16 (Nhon Trach beach), prepared concrete pumps for the bridge deck and burned the G2 girder. Photo: Danh Quynh
Tram bom be tong duong thuy duoi chan cau, san sang van hanh bom vat lieu len cao phuc vu thi cong. Ảnh: Danh Quynh
The waterway concrete pumping station at the foot of the bridge is ready to pump materials up high to serve the construction. Photo: Danh Quynh

The J3-1 package is undertaken by the joint venture of North-South Infrastructure Construction Joint Stock Company - Freyssinet Vietnam Co., Ltd., with a contract value of more than VND 635 billion and a construction period of 450 days. The main items include the main girder, bridge deck, cable car system, asphalt concrete, railings, median strip and lighting system.

Previously, the Phuoc Khanh bridge construction package was signed by VEC with the Sumitomo Mitsui - Cienco 4 consortium in 2016, but had to stop from 2020 when it had reached over 80% of the volume due to capital problems. After that, the new project was restarted in May 2023.

  Cac hang tru cau, duong dan o hai ben bo Can Gio va Nhon Trach da hoan thanh truoc do. Ảnh: Danh Quynh
The bridge piers and approach roads on both sides of Can Gio and Nhon Trach were completed earlier. Photo: Danh Quynh

Phuoc Khanh Bridge is more than 3 km long, nearly 22 m wide, designed with a cable-stayed approach, with an clearance of 55 m - the highest among cable-stayed bridges in Vietnam. This is one of the two largest bridges on the Ben Luc - Long Thanh Expressway, connecting Can Gio (HCMC) and Nhon Trach (Dong Nai).

Cau Phuoc Khanh la mot trong hai cay cau lon nhat tren cao toc Ben Luc - Long Thanh. Ảnh: Danh Quynh
Phuoc Khanh Bridge is one of the two largest bridges on the Ben Luc - Long Thanh Expressway. Photo: Danh Quynh

The acceleration of the progress of Phuoc Khanh bridge along with the official completion of Binh Khanh bridge and successful load testing are key steps to connect the entire nearly 58 km long Ben Luc - Long Thanh expressway. When completed in 2026, the 4-lane route, with a maximum speed of 100 km/h, will become a strategic traffic axis, connecting the East - Southwest, reducing traffic pressure for Ho Chi Minh City and creating momentum for socio-economic development for the whole region.

Cau Binh Khanh da hoan thanh, thu tai thanh cong voi xe tai nang. Ảnh: Danh Quynh
Binh Khanh Bridge has been completed and successfully tested for heavy trucks. Photo: Danh Quynh
Anh Tú
RELATED NEWS

HCMC is about to build 2 bridges worth over VND30,000 billion, ending the problem of ferry accidents

|

Ho Chi Minh City is about to build Cat Lai Bridge and Can Gio Bridge with a total capital of more than 30,000 billion VND, helping people escape the situation of ferry accidents for decades.

Binh Khanh Bridge closed, removing bottlenecks on the progress of Ben Luc - Long Thanh Expressway

|

Ho Chi Minh City - Binh Khanh Bridge has just been closed, expected to be completed by the end of August 2025.

Image of the two largest bridges on the Ben Luc - Long Thanh Expressway after nearly 10 years of construction

|

HCMC - The two largest cable-stayed bridges on the Ben Luc - Long Thanh Expressway are being accelerated to open the route in time for 2026.

Israel assassinates Hamas leader in Qatar

|

Israel carried out an assassination attack on a Hamas leader in Qatar on September 9.

From September 9, pilot implementation of the cryptocurrency asset market in Vietnam

|

The Government has just issued Resolution No. 5/2025/NQ-CP, piloting the cryptocurrency asset market in Vietnam from September 9.

U23 Vietnam enters the 2026 U23 Asian Cup finals

|

On the evening of September 9, U23 Vietnam beat U23 Yemen 1-0 in the final match of Group C of the 2026 U23 Asian qualifiers.

Results of the inspection of the case of a father and son in 2 different hamlets but the electricity bill is the same

|

Thai Nguyen - During the August electricity bill, a household reported that there was a situation where the bills of a father and son in two different neighborhoods were identical.

HCMC is about to build 2 bridges worth over VND30,000 billion, ending the problem of ferry accidents

MINH QUÂN |

Ho Chi Minh City is about to build Cat Lai Bridge and Can Gio Bridge with a total capital of more than 30,000 billion VND, helping people escape the situation of ferry accidents for decades.

Binh Khanh Bridge closed, removing bottlenecks on the progress of Ben Luc - Long Thanh Expressway

Anh Tú |

Ho Chi Minh City - Binh Khanh Bridge has just been closed, expected to be completed by the end of August 2025.

Image of the two largest bridges on the Ben Luc - Long Thanh Expressway after nearly 10 years of construction

Anh Tú |

HCMC - The two largest cable-stayed bridges on the Ben Luc - Long Thanh Expressway are being accelerated to open the route in time for 2026.