New developments in the case of a 50 billion clean water plant that is stalled due to lack of pipelines

Tân Văn |

Cao Bang - The Department of Agriculture and Environment has just sent an official dispatch to the Provincial People's Committee Office regarding the Tra Linh town clean water plant.

On April 3, the Department of Agriculture and Environment of Cao Bang province issued Official Letter No. 577/SNNMT-QLMT to the Provincial People's Committee Office on publicizing the content of the Report proposing to grant an Environmental License for the Tra Linh Town Clean Water Supply Plant Project, Trung Khanh District.

Accordingly, on March 24, 2025, the Department of Agriculture and Environment received a complete dossier requesting an Environmental License for the project.

Based on current regulations, the Department of Agriculture and Environment requests the Provincial People's Committee Office to coordinate in posting information and taking the next steps according to regulations.

Regarding the above clean water project, Lao Dong Newspaper has had many articles reflecting. The project was approved by the Cao Bang People's Committee in May 2021, with the Cao Bang Economic Zone Management Board as the investor, with a total cost of 50 billion VND.

Since the end of 2023, the investor has completed the construction, this project is responsible for providing domestic water for people in Tra Linh town and the Tra Linh International Border Gate area. However, due to lack of pipelines and many reasons and problems, the project has not yet been put into use.

According to the investor's representative, in the first quarter of 2025, the People's Committee of Cao Bang province approved the investment in a level II pipeline and a water supply network for border gate areas, towns and neighboring communes with a budget of about 14.5 billion VND.

The project is expected to start construction at the end of the second quarter of 2025 and supply water by the end of 2025. Thus, according to the plan, it will take another year for the Tra Linh town clean water plant to officially operate.

Tân Văn
TIN LIÊN QUAN

Lack of pipelines, water plants in Cao Bang have to wait for completion

|

The clean water project in Tra Linh town (Trung Khanh district, Cao Bang province) has been completed, but cannot be operated due to lack of pipelines.

Traffic jam lasted 2 km on Phu My bridge due to a series of accidents

|

HCMC - A series of vehicles lined up for about 2 km on Phu My bridge (District 7) after a series of accidents on the evening of April 10.

Visitation ceremony for the late Prime Minister Vo Van Kiet's wife in Ho Chi Minh City

|

HCMC - The funeral service for Prof. Dr. Phan Luong Cam, wife of the late Prime Minister Vo Van Kiet, was solemnly held at the Southern National Funeral Home (HCMC).

20h News: Vinh Long people are miserable because of foul-smelling domestic water with dirty waste

|

20h News on 10.4: Domestic gasoline prices have all dropped sharply; Clean water is dirty, many people in Vinh Long are having trouble...

Cao Bang is at the bottom in many indicators

|

Cao Bang - In the past 10 years, although there have been some positive signals, that is not enough to help Cao Bang province escape the bottom group in the indicators.

Highway construction unit encroaches on people's land, authorities take action to consider compensation

|

Dak Lak - A household has just filed a complaint against the expressway construction unit for encroaching on uncompensated land. Local authorities are taking action to handle the situation.

The plan to arrange 171 commune-level administrative units in Quang Ninh has not been finalized

|

Quang Ninh - The Department of Home Affairs of Quang Ninh province has submitted to the Provincial People's Committee a number of plans on the arrangement of commune-level administrative units.

Ba hộ dân đòi tiền tỉ đền bù, nhà máy nước sạch chậm trễ

Nhóm PV |

Cao Bằng - Suốt 2 năm, nhà máy nước sạch duy nhất của thị trấn Pắc Miầu không thể hoàn thiện và đưa vào sử dụng vì 3 hộ dân quyết không thuận phương án đền bù.

Lack of pipelines, water plants in Cao Bang have to wait for completion

Tân Văn |

The clean water project in Tra Linh town (Trung Khanh district, Cao Bang province) has been completed, but cannot be operated due to lack of pipelines.

Vướng mắc đền bù, dự án nước sạch vùng biên chậm tiến độ

Nhóm PV |

Cao Bằng - Vì vướng mắc đền bù thiệt hại do nổ mìn, dự án xây dựng nhà máy cấp nước sạch thị trấn Pác Miầu đang bị chậm tiến độ.