On September 1, according to information from the People's Committee of Long Thanh district, at the Bien Hoa - Vung Tau expressway project, the district has so far approved and publicized compensation plans for 2,718 cases, reaching a rate of 97.63%.
Authorities have also considered granting resettlement to 1,587 cases, of which 1,321 cases have been approved.
In particular, 9 communes and towns of Long Thanh district have mobilized households to hand over 42.5 hectares of land for component project 1 (reaching 54.39%) and 115.13 hectares of land for component project 2 (reaching 75.95%), bringing the total to 158 hectares/230 hectares of land for the expressway project handed over.
The Bien Hoa - Vung Tau Expressway construction investment project, phase 1, through Long Thanh district, has a total length of about 28 km with a total recovered area of nearly 230 hectares/2,593 land plots/2,784 cases.
Long Thanh district leaders requested that the district's functional branches urgently coordinate with departments and branches of Dong Nai province to completely resolve land issues of organizations and enterprises; urgently approve, pay money, consider granting resettlement for the remaining cases and communes and towns actively mobilize households to hand over the entire site of the expressway project, by September 15, 2024 all work must be completed.