The project to renovate and upgrade National Highway 6, Ha Dong - Xuan Mai section, started in December 2023.
The project has a length of 21.7 km, a cross-section scale of 50-60m. This is a key traffic project of the city, of particular importance in completing the radial traffic axis in the Southwest of the Capital.
The project includes 5 construction packages; synchronous investment in foundation, road surface, bridges, drainage system, technical trenches, technical infrastructure and auxiliary works.




The project has a total area to be recovered of about 105.13 ha in wards and communes, including: Kien Hung, Duong Noi, Phu Luong, Yen Nghia, Chuong My, Xuan Mai and Phu Nghia.
Up to now, some localities have completed site clearance and handed it over to investors such as Kien Hung, Duong Noi, Phu Luong wards, and Phu Nghia commune.
In Chuong My ward, by the end of June 30, the ward had completed site clearance and handed over 20.03 hectares to the investor, reaching 99.71% of the recovered area, equivalent to 804/814 land plots.
Currently, there are still 9 households with 10 land plots, an area of about 0.166 hectares, who have not agreed to hand over the site. These cases are mainly related to agricultural land self-converted for land use purposes, residential land and a part of the area belonging to Phuong Bai Church.
For the remaining cases, Mr. Phi Minh Hai - Secretary of the Party Committee, Chairman of the People's Council of Chuong My ward requested the Steering Committee, working groups and related forces to continue to stick to the area, strengthen propaganda, mobilization, and dialogue to remove each obstacle, striving to complete the site clearance work as soon as possible.



Regarding the construction progress of the project to renovate and upgrade National Highway 6, Ha Dong - Xuan Mai section, the actual value to date reached 349.5/2.265.37 billion VND, equivalent to 15.43% of the construction contract value.
Some bridge items achieved good progress: Dong Tru bridge reached about 94.89%; Tan Truong bridge reached about 86%.





Inspecting the site at the project to renovate and upgrade National Highway 6, Ha Dong - Xuan Mai section on June 28, Politburo member, Secretary of the Hanoi Party Committee Tran Duc Thang requested that the demolition of the works must be completed in July 2026 to hand over the clean site to the construction contractor.
Contractors when handed over a clean site need to mobilize sufficient manpower and vehicles to accelerate progress to resolutely implement technical traffic opening before the Lunar New Year Dinh Mui 2027 and complete the entire project in the first quarter of 2027.