Project to bring electricity to the North and South of Phu Quoc Island has land acquisition problems

ĐẠT PHAN |

Kien Giang - The 110kV project to bring electricity to the North and South of Phu Quoc Island is expected to be completed in 2024 but is still facing land acquisition problems.

Electricity waiting for the ground

According to the report of the Southern Power Corporation (EVNSPC), from 2014 to present, EVNSPC has been investing in the construction of many power grid projects in Kien Giang province with a total investment of more than 7,600 billion VND. In the period of 2015-2023, many important power projects have been put into operation such as: 220kV Kien Binh - Phu Quoc line, 110kV Ha Tien - Tinh Bien line, 110kV Vinh Thuan - An Xuyen line; projects to bring national grid electricity to island communes of Kien Giang province such as: Hon Tre, Lai Son, Hon Nghe, Son Hai, Tien Hai...

The completion of the 220kV Kien Binh-Phu Quoc transmission line has contributed to ensuring the supply of electricity from the mainland to Phu Quoc City. Photo: EVNSPC

Mr. Doan Duc Hung - Deputy General Director of EVNSPC - said that up to now, 100% of communes, wards and towns in Kien Giang province have electricity; 99.73% of rural households have electricity. Currently, there are 3 island communes (An Son, Nam Du and Tho Chu) that do not have national grid electricity, currently using local diesel and renewable energy sources.

Mr. Le Van Trang - Chairman of EVNSPC Board of Directors - said: Determining that "electricity is one step ahead", in recent years, EVNSPC has proactively allocated resources and implemented many electricity projects to meet the high growth rate of the province's load, especially Phu Quoc City. However, up to now, many projects are still facing difficulties in compensation and site clearance; including long-standing problems that have not been completely resolved, affecting the project progress as well as the electricity supply in the area.

Notably, the Phu Quoc - South Phu Quoc 110kV Transmission Line project is scheduled to be energized in 2024, but currently only 35/79 tower locations have been handed over; the Phu Quoc - North Phu Quoc 110kV Transmission Line project is scheduled to be energized in 2024, but currently only 7/72 tower locations have been handed over; the Phu Quoc 220kV Transformer Station project is scheduled to start construction in the fourth quarter of 2024, but currently there is no site for the station. In other districts and cities of Kien Giang province, there are 6 projects that are also facing difficulties and problems.

Clearly define responsibilities

Recently, at the working session on October 26 to remove difficulties and obstacles of power projects, EVNSPC leaders proposed that the Provincial Party Committee, People's Council, and People's Committee of Kien Giang province continue to direct departments, branches, sectors, and local authorities at all levels to remove difficulties and obstacles of projects, especially projects to ensure electricity supply for Phu Quoc city.

Cac cong trinh dua dien ra dao gop phan phat trien KTXH, giu vung an ninh quoc phong tren dia ban tinh Kien Giang. Anh: EVNSPC
Projects to bring electricity to the island contribute to socio-economic development and maintain national security and defense in Kien Giang province. Photo: EVNSPC

Acknowledging the efforts of EVNSPC in ensuring electricity supply in the area, Mr. Giang Thanh Khoa - Vice Chairman of Kien Giang Provincial People's Committee - said that the Provincial People's Committee will have specific instructions for each relevant department, branch, and locality to resolve problems for each project.

Speaking at the meeting, Mr. Do Thanh Binh - Member of the Party Central Committee, Secretary of Kien Giang Provincial Party Committee - shared: Looking back 10 years ago, Kien Giang province still faced many difficulties. However, with determination and correct policies in investing in building infrastructure of "electricity, roads, schools, stations", in which electricity is at the forefront, up to now, Kien Giang has had remarkable development.

Regarding the difficulties in site clearance for power projects, Mr. Binh emphasized the need to resolve them. For each project, the Secretary of the Kien Giang Provincial Party Committee requested that the responsibilities of each agency, unit, and sector be clearly defined; at the same time, timelines must be set and closely followed for implementation. Mr. Binh also requested that EVNSPC and departments, branches, and sectors of Kien Giang province need to coordinate more closely in the process of resolving difficulties to speed up the progress of power projects.

At the meeting, leaders of Kien Giang province and EVNSPC also discussed the investment policy for the project of supplying electricity from the national grid to the island communes of Nam Du and An Son (Kien Hai district).

According to EVNSPC, in the first 9 months of 2024, the commercial electricity output of Kien Giang province reached 2,436.9 million kWh, an increase of 9.43% over the same period in 2023. In Phu Quoc city alone, the total electricity consumption in the first 9 months of 2024 was 552.97 million kWh, 10.85% higher than the same period in 2023. According to forecasts, the average annual load growth rate of Phu Quoc city in the period of 2026-2030 is 10%.

ĐẠT PHAN
TIN LIÊN QUAN

Forecast of super typhoon Man-yi's intensity after entering the East Sea

|

After entering the East Sea, Typhoon Man-yi will gradually weaken to level 12 intensity, gusting to level 14.

Hour 9: Surrogacy - Part 2

|

Hour 9 - A couple longs to have a child, but the wife has suffered multiple miscarriages. As a last resort, they seek a surrogate mother and meet an unexpected end.

LPB Ninh Binh won 3rd place in the 2024 national volleyball tournament

|

On the evening of November 16, LPB Ninh Binh defeated Long Son Thanh Hoa Cement with a score of 3-1 to win 3rd place overall at the 2024 National Volleyball Championship.

Yen Bai Secretary participates in tug of war at Great Solidarity Festival

|

On the afternoon of November 16, Secretary of the Provincial Party Committee and Chairman of the People's Committee of Yen Bai province Tran Huy Tuan came to celebrate the Great Unity Day of Ethnic Groups with the people of Quyet Tien village.

Why is Ky Duyen's entry into the top of Miss Universe considered a success?

|

With the fierce competition of Miss Universe 2024, Ky Duyen's entry into the final round is considered a success. Why?

Thanh Oai land auction: The highest lot is 11.6 billion VND, 17 times higher than the starting price

|

Hanoi - At around 5:00 p.m. on November 16, the auction of 25 land plots in Thanh Oai district ended.

Require Green Pearl investor to supply water to people

|

Vinh Tuy Ward People's Committee requested Green Pearl investor to provide water for residents, ensure social security, order and security, and fire prevention and fighting in the area.

EVNSPC kêu gọi đoàn viên, CNLĐ tham gia công trình đường dây 500kV mạch 3

Đạt Phan |

Ngày 7.6, Ban Tổng Giám đốc và Công đoàn Tổng Công ty Điện lực Miền Nam (EVNSPC) chính thức gửi thư kêu gọi toàn thể cán bộ, đoàn viên, công nhân lao động (CNLĐ) và các đơn vị thành viên đăng ký tham gia thi công xây dựng hoàn thành các dự án đường dây 500kV mạch 3 Quảng Trạch - Phố Nối.

Hơn 3.600 tỉ đồng đầu tư lưới điện cho Phú Quốc đến 2024

NGUYÊN ANH |

Đến năm 2024, ngành điện đã ưu tiên thực hiện đầu tư lưới điện trên địa bàn TP Phú Quốc với tổng vốn đầu tư hơn 3.650 tỉ đồng, chiếm gần 75% trong tổng kế hoạch đầu tư các công trình điện toàn tỉnh Kiên Giang.

Đóng điện công trình đường dây 220kV Kiên Bình-Phú Quốc dài nhất Đông Nam Á

NGUYÊN ANH |

Kiên Giang – Công trình Đường dây 220kV Kiên Bình - Phú Quốc là công trình đường dây vượt biển trên không cấp điện áp 220kV dài nhất khu vực Đông Nam Á, được triển khai lần đầu tiên tại Việt Nam, có tổng mức đầu tư trên 2.200 tỉ đồng.