600 billion VND road project connecting National Highway 6 is still under construction but not completed

Minh Nguyễn |

Phu Tho - The road connecting Tran Hung Dao street with National Highway 6 is under construction due to site clearance problems and lack of materials.

The project has a starting point intersecting with Tran Hung Dao street (Hoa Binh ward) and an ending point connecting to National Highway 6 through Thong Nhat ward.

The Project Management Board for Investment and Construction of Transport Works of Hoa Binh province (now the Project Management Board for Investment in Hoa Binh Region) is entrusted to manage the project.

The project belongs to group B, started in March 2022, expected to be completed in December 2024. However, up to now, 4 years have passed, the project is still stagnant, with no deadline for completion.

Records at the construction site at the end of March show that some bridge and road positions have basically taken shape, but many sections are still messy and there are no signs of construction.

Along the route, many temporary barriers, construction materials gathered along the road, and the road surface in some sections have not been completed, making it difficult for people and vehicles to travel, especially during peak hours.

Nhiều vị trí thi công dang dở. Ảnh: Minh nguyễn
Many unfinished construction sites. Photo: Minh Nguyen

Living near the construction area, Ms. Nguyen Thi Huong (Hoa Binh ward) said that travel is difficult: "Dusty roads on sunny days, muddy when it rains, vehicles passing by are very difficult. People hope the project will be completed soon to make travel more convenient.

Meanwhile, Mr. Nguyen Dan Thanh (Thong Nhat ward) shared: "Many sections are under construction, materials are gathered along the road, causing traffic obstruction. People expect the obstacles to be removed soon so that the road can be cleared soon.

According to the Hoa Binh Regional Investment Project Management Board, the project has a total investment of 600 billion VND from local and central budgets, implemented in the period 2021-2026.

Accumulated to the end of 2025, 323.311 billion VND has been allocated and disbursed, reaching 100% of the previous capital plan. In 2026, the project was allocated 111.839 billion VND, but only 1.9 billion VND has been disbursed, reaching about 4%.

The total capital allocated to date reached 435.15 billion VND, and nearly 110 billion VND has not been disbursed.

Tuyến đường thi công dang dở. Ảnh: Minh Nguyễn
Unfinished construction road. Photo: Minh Nguyen

Regarding the construction progress, the 4.36 km long road currently only reached about 205.6/385.514 billion VND, equivalent to 53.3% of the volume.

The contractor has basically completed 2/2 bridges on the route; roadbed construction reached about 2 km; crushed stone base reached 0.6 km along with drainage system.

Due to the lack of embankment soil materials and inconsistent ground, the construction unit is focusing on installing curbs in some sections where ground has been cleared.

The source of embankment soil material is also facing problems when the surplus soil mine licensed for exploitation of 388,000 m3 has expired, and the contractor is completing procedures to extend it after relevant agencies inspect the site.

Notably, the estimated site clearance cost increased to 300 billion VND, about 120 billion VND higher than the initial approval, leading to the risk of having to adjust the total investment of the project.

Người dân di chuyển trên dự án. Ảnh: Minh Nguyễn
People moving on the project. Photo: Minh Nguyen

Also according to the Hoa Binh Regional Investment Project Management Board, to date, the project has recovered 21.7 hectares of land from 340 households; has paid to 243 households with about 50 billion VND.

The handed-over site is 2.5/4.36 km (64%) but there is still a "precarious" situation. About 80 households in the resettlement area have not been arranged because the resettlement areas have not completed land allocation procedures.

The remaining site area of about 1.6 km is expected to be handed over in the second quarter of 2026. There is still 1 power pole on the route that has not been relocated.

The biggest difficulty currently is the site clearance obstacle with about 1.86 km remaining, due to difficulty determining the origin of the land, lack of documents, disputes, and some households have not received compensation money.

Ngổn ngang vật liệu tại dự án. Ảnh: Minh Nguyễn
Messy materials at the project. Photo: Minh Nguyen

In addition, there are still problems with collective housing areas that do not have land use right certificates and are slow to issue land acquisition notices.

The investor has proposed to the Phu Tho Provincial People's Committee to consider allowing an adjustment of the total investment, and soon extend the surplus land exploitation license.

At the same time, directing localities to accelerate site clearance, complete resettlement areas, relocate cemeteries and technical infrastructure to ensure project progress.

Minh Nguyễn
RELATED NEWS

Truck loses control and overturns on National Highway 6

|

Phu Tho - Functional agencies are clarifying the cause of a traffic accident on National Highway 6 that injured 1 person.

Phu Tho accelerates the progress of the 450 billion VND road connecting National Highway 6

|

Phu Tho - The road with a total investment of 450 billion VND connecting to National Highway 6 is gradually being formed.

National Highway 6 expansion project: Inviting the Inspectorate to the commune to work to verify the origin of land

|

Hanoi - Phu Nghia commune is expected to invite the City Inspectorate to work to verify the origin of land in some areas within the scope of the National Highway 6 expansion project.

Strongly punish to prevent dangers at railway intersections

|

Hanoi - After the fine level increased sharply according to Decree 81/2026, the situation of crossing barriers and running red lights at railway intersections has decreased significantly.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

Truck loses control and overturns on National Highway 6

Minh Nguyễn |

Phu Tho - Functional agencies are clarifying the cause of a traffic accident on National Highway 6 that injured 1 person.

Phu Tho accelerates the progress of the 450 billion VND road connecting National Highway 6

Minh Chuyên |

Phu Tho - The road with a total investment of 450 billion VND connecting to National Highway 6 is gradually being formed.

National Highway 6 expansion project: Inviting the Inspectorate to the commune to work to verify the origin of land

SÓNG HỮU |

Hanoi - Phu Nghia commune is expected to invite the City Inspectorate to work to verify the origin of land in some areas within the scope of the National Highway 6 expansion project.