600 billion VND road project connecting National Highway 6 is still under construction but not completed

Minh Nguyễn |

Phu Tho - The road connecting Tran Hung Dao street with National Highway 6 is under construction due to site clearance problems and lack of materials.

The project has a starting point intersecting with Tran Hung Dao street (Hoa Binh ward) and an ending point connecting to National Highway 6 through Thong Nhat ward.

The Project Management Board for Investment and Construction of Transport Works of Hoa Binh province (now the Project Management Board for Investment in Hoa Binh Region) is entrusted to manage the project.

The project belongs to group B, started in March 2022, expected to be completed in December 2024. However, up to now, 4 years have passed, the project is still stagnant, with no deadline for completion.

Records at the construction site at the end of March show that some bridge and road positions have basically taken shape, but many sections are still messy and there are no signs of construction.

Along the route, many temporary barriers, construction materials gathered along the road, and the road surface in some sections have not been completed, making it difficult for people and vehicles to travel, especially during peak hours.

Nhiều vị trí thi công dang dở. Ảnh: Minh nguyễn
Many unfinished construction sites. Photo: Minh Nguyen

Living near the construction area, Ms. Nguyen Thi Huong (Hoa Binh ward) said that travel is difficult: "Dusty roads on sunny days, muddy when it rains, vehicles passing by are very difficult. People hope the project will be completed soon to make travel more convenient.

Meanwhile, Mr. Nguyen Dan Thanh (Thong Nhat ward) shared: "Many sections are under construction, materials are gathered along the road, causing traffic obstruction. People expect the obstacles to be removed soon so that the road can be cleared soon.

According to the Hoa Binh Regional Investment Project Management Board, the project has a total investment of 600 billion VND from local and central budgets, implemented in the period 2021-2026.

Accumulated to the end of 2025, 323.311 billion VND has been allocated and disbursed, reaching 100% of the previous capital plan. In 2026, the project was allocated 111.839 billion VND, but only 1.9 billion VND has been disbursed, reaching about 4%.

The total capital allocated to date reached 435.15 billion VND, and nearly 110 billion VND has not been disbursed.

Tuyến đường thi công dang dở. Ảnh: Minh Nguyễn
Unfinished construction road. Photo: Minh Nguyen

Regarding the construction progress, the 4.36 km long road currently only reached about 205.6/385.514 billion VND, equivalent to 53.3% of the volume.

The contractor has basically completed 2/2 bridges on the route; roadbed construction reached about 2 km; crushed stone base reached 0.6 km along with drainage system.

Due to the lack of embankment soil materials and inconsistent ground, the construction unit is focusing on installing curbs in some sections where ground has been cleared.

The source of embankment soil material is also facing problems when the surplus soil mine licensed for exploitation of 388,000 m3 has expired, and the contractor is completing procedures to extend it after relevant agencies inspect the site.

Notably, the estimated site clearance cost increased to 300 billion VND, about 120 billion VND higher than the initial approval, leading to the risk of having to adjust the total investment of the project.

Người dân di chuyển trên dự án. Ảnh: Minh Nguyễn
People moving on the project. Photo: Minh Nguyen

Also according to the Hoa Binh Regional Investment Project Management Board, to date, the project has recovered 21.7 hectares of land from 340 households; has paid to 243 households with about 50 billion VND.

The handed-over site is 2.5/4.36 km (64%) but there is still a "precarious" situation. About 80 households in the resettlement area have not been arranged because the resettlement areas have not completed land allocation procedures.

The remaining site area of about 1.6 km is expected to be handed over in the second quarter of 2026. There is still 1 power pole on the route that has not been relocated.

The biggest difficulty currently is the site clearance obstacle with about 1.86 km remaining, due to difficulty determining the origin of the land, lack of documents, disputes, and some households have not received compensation money.

Ngổn ngang vật liệu tại dự án. Ảnh: Minh Nguyễn
Messy materials at the project. Photo: Minh Nguyen

In addition, there are still problems with collective housing areas that do not have land use right certificates and are slow to issue land acquisition notices.

The investor has proposed to the Phu Tho Provincial People's Committee to consider allowing an adjustment of the total investment, and soon extend the surplus land exploitation license.

At the same time, directing localities to accelerate site clearance, complete resettlement areas, relocate cemeteries and technical infrastructure to ensure project progress.

Minh Nguyễn
RELATED NEWS

Truck loses control and overturns on National Highway 6

|

Phu Tho - Functional agencies are clarifying the cause of a traffic accident on National Highway 6 that injured 1 person.

Phu Tho accelerates the progress of the 450 billion VND road connecting National Highway 6

|

Phu Tho - The road with a total investment of 450 billion VND connecting to National Highway 6 is gradually being formed.

Hanoi accelerates 10 drainage projects, handles 220 flooded points before the 2026 rainy season

|

Hanoi accelerates 10 urgent drainage projects, handles 220 flooded points, ensuring completion before the 2026 rainy season.

Russian military transport plane crashes in Crimea, all 29 people killed

|

The Russian Ministry of Defense said 6 crew members and 23 passengers were killed in the crash of a Russian military transport plane in Crimea.

Italy national team absent for the third consecutive World Cup

|

In the early morning of April 1st (Vietnam time), Italy lost to Bosnia Herzegovina in a penalty shootout in the 2026 World Cup play-off final.

Canal pollution through two wards in Ho Chi Minh City

|

Ho Chi Minh City - The situation of waste and black water pollution in the canal through Tan Son Nhi and Tay Thanh wards is affecting the lives of Ho Chi Minh City residents.

Base salary expected to increase, preschool teachers are both excited and worried about prices

|

The proposal to increase the base salary from July 1, 2026 makes many kindergarten teachers excited, but also worried that living costs may increase accordingly.

Ho Chi Minh City to deploy a series of projects to rescue traffic jams at the Northwest gateway

|

Ho Chi Minh City - Ho Chi Minh City - Moc Bai expressway, expansion of National Highway 22, Nguyen Van Bua street, Phan Van Hon parallel road,... help reduce traffic jams at the Northwest gateway.

Truck loses control and overturns on National Highway 6

Minh Nguyễn |

Phu Tho - Functional agencies are clarifying the cause of a traffic accident on National Highway 6 that injured 1 person.

Phu Tho accelerates the progress of the 450 billion VND road connecting National Highway 6

Minh Chuyên |

Phu Tho - The road with a total investment of 450 billion VND connecting to National Highway 6 is gradually being formed.

Dự án mở rộng Quốc lộ 6: Mời Thanh tra về xã làm việc để xác minh nguồn gốc đất đai

SÓNG HỮU |

Hà Nội - Xã Phú Nghĩa dự kiến mời Thanh tra TP về làm việc để xác minh nguồn gốc đất đai một số khu vực trong phạm vi Dự án mở rộng Quốc lộ 6.