1.6km of Ring Road 2.5 risks missing handover deadline in March 2026

HỮU CHÁNH |

Hanoi - If the relevant parties do not promptly remove obstacles in site clearance, 1.6km of Ring Road 2.5 will miss the handover deadline in March 2026.

The Ring Road 2.5 construction investment project, Dam Hong - National Highway 1A section, was technically opened to traffic on February 10, 2026, after 12 years of people's expectations.

The project was started in 2014 with a length of 1.6km, total investment of about 1,317 billion VND under the BT (build - transfer) contract form, expected to be completed in 2017.

However, the project progress was delayed due to problems in site clearance and waiting for BT contract extension.

A
Ring Road 2.5, Dam Hong section - National Highway 1A technically opened to traffic on the 10th. 2. Photo: Song Huu

By 2020, when only about 40% of the workload was completed, the project had to be temporarily suspended.

After 5 years of suspension, by the end of May 2025, Hoang Mai - Hanoi Construction Investment Co., Ltd. (project enterprise) will organize the Groundbreaking Ceremony for the 2.5 Ring Road project, Dam Hong - National Highway 1A section.

By February 10, 2026, the project will basically complete the items for technical traffic opening. According to the plan, by March 31 at the latest, the Ring Road 2.5 project, Dam Hong - National Highway 1A section will complete all construction items, ensuring synchronization and sufficient conditions for handover and commissioning in accordance with regulations.

However, the project is facing the risk of not being able to hand over on schedule due to site clearance issues.

A
59.3m2 of land belonging to the project of Hanoi Housing Investment and Development Corporation has not been handed over to the Ring Road 2.5 project. Photo: Song Huu
A
Business activities are still taking place at the location where land is recovered. Photo: Song Huu

Mr. Le Thanh Tung, Deputy Director of Hoang Mai Construction Investment Co., Ltd. - Hanoi, said that in Phuong Liet ward, there are 2 households with land clearance areas of 59.3m2 (1 household recovered 6.1m2/129.8m2 and 1 household recovered 53.2m2/110.9m2) belonging to the project of Hanoi Housing Investment and Development Corporation but located within the sidewalk area of Ring Road 2.5 project that has not been cleared.

According to Mr. Tung, Hanoi City People's Committee has assigned the Department of Agriculture and Environment together with relevant units, including Phuong Liet Ward People's Committee, Hanoi Housing Investment and Development Corporation to deploy site clearance work.

However, so far it has only stopped at planting boundary markers and painting lines in the field.

The time is extremely rushed, if the relevant units do not get involved decisively, it will affect the overall progress of the project, while the City Party Committee and the City People's Committee direct that the project must be handed over and put into use no later than March 31st" - Mr. Le Thanh Tung said.

A
59.3m2 of land area is the biggest remaining bottleneck of the Ring Road 2.5 project but has not been completely resolved. Photo: Song Huu
A
A
Construction cannot be deployed due to site clearance issues. Photo: Song Huu

It is known that on January 27, 2026, Phuong Liet Ward People's Committee sent a document to Hanoi Housing Investment and Development Corporation to coordinate and sign land clearance contracts for the above 2 households.

Talking to Lao Dong Newspaper, Vice Chairman of Phuong Liet Ward People's Committee Nguyen Kim Son said that the ward has deployed and completed relevant procedures, and the remaining task is for Hanoi Housing Investment and Development Corporation.

I have urged and reminded the Hanoi Housing Investment and Development Corporation. When they transfer dossiers, the ward will coordinate to deploy investigation and inventory" - Mr. Son said.

It can be seen that the early completion of handover of the remaining area is an urgent requirement to ensure the overall progress and put the 2.5 Ring Road project, Dam Hong - National Highway 1A section into synchronous and planned operation.

If delays continue, it will not only affect the acceptance deadline and putting the project into use, but also reduce investment efficiency, waste resources and affect the aesthetics and travel of people in the area.

HỮU CHÁNH
RELATED NEWS

Positive signals about land acquisition and site clearance for Ring Road 2.5

|

Hanoi - 2 sections of Ring Road 2.5 through Cau Giay ward recorded many positive results in land acquisition and site clearance.

Hanoi recovers about 96,500m2 of land to build Ring Road 2.5

|

Hanoi - About 96,500m2 of land in Cau Giay, Yen Hoa and Thanh Xuan wards will be recovered for the construction of 3 sections of Ring Road 2.5.

Hanoi starts construction of the last pieces of Ring Road 2.5

|

Hanoi - 3 sections of Ring Road 2.5 with a length of 2.26km started construction this morning with a total investment of about 8,402 billion VND, expected to be completed in 2026.

Dong Ha bypass road at risk of delay due to site clearance problems, calculating coercive measures

|

Quang Tri - The Dong Ha bypass road project is at risk of continuing to be delayed. The locality is looking for solutions and considering coercive measures to clear the site.

Quat Lam beach deserted before revival plan

|

Ninh Binh - Before the plan to develop marine tourism, the Quat Lam area is deserted, many accommodation establishments are degraded, and tourism activities are quiet.

Messi scores his 901st goal, Inter Miami dramatically wins back

|

On the morning of March 23 (Vietnam time), Lionel Messi scored from the free kick, helping Inter Miami CF defeat New York City FC 3-2 in MLS 2026.

Man City wins Carabao Cup

|

In the early morning of February 23 (Vietnam time), Man City defeated Arsenal 2-0 to win the Carabao Cup championship in the 2025-2026 season.

Hungary forecasts Ukraine runs out of money, forced to reopen the Druzhba oil pipeline in April

|

Hungary forecasts that Ukraine will soon be forced to resume oil flow through Druzhba, because this country will run out of money before Hungary runs out of oil.

Positive signals about land acquisition and site clearance for Ring Road 2.5

SÓNG HỮU |

Hanoi - 2 sections of Ring Road 2.5 through Cau Giay ward recorded many positive results in land acquisition and site clearance.

Hanoi recovers about 96,500m2 of land to build Ring Road 2.5

HỮU CHÁNH |

Hanoi - About 96,500m2 of land in Cau Giay, Yen Hoa and Thanh Xuan wards will be recovered for the construction of 3 sections of Ring Road 2.5.

Hanoi starts construction of the last pieces of Ring Road 2.5

HỮU CHÁNH |

Hanoi - 3 sections of Ring Road 2.5 with a length of 2.26km started construction this morning with a total investment of about 8,402 billion VND, expected to be completed in 2026.