The Dung Quat - Sa Huynh coastal road project is about 100km long, with 7 sections, with a starting point at Km 23+500 and the end point connected to the coastal route of Binh Dinh province through Km125+645 (excluding 23 , 5km belonging to the transport infrastructure planning of Dung Quat Economic Zone, connecting to Chu Lai airport, Quang Nam province). The project is invested by the Management Board of Traffic Construction Investment in Quang Ngai province
According to the investor, after many years of construction, the province has put into operation for more than 32km. Currently, more than 25 km from Km56 - Km69 - Km76+230 with a total investment of nearly VND 2,100 billion. Project construction progress reaches about 80%.
In the course of implementation, there are some certain difficulties related to compensation and site clearance, especially after the new land law takes effect, partly affecting the general progress of the attendance. sentence. However, with high determination, the province is focusing on leading and directing to complete the entire route under construction and put into operation in 2025. invest. In particular, the paragraph from Km76+230 - Km82 has completed construction design documents.
However, this section has overlapped with the boundary of Titan mineral exploration and exploitation approved by the Prime Minister. Therefore, the province must pause and are waiting for the opinion of the Ministry of Natural Resources and Environment to serve as a basis for implementing the next steps.
For the route from Km82 - Km107+200 and Km119+500 connected to Binh Dinh province, the construction investment has not been implemented due to the lack of capital. Particularly, the section of Km107+200 - Km119+500 goes to the National Highway 1 because it is impossible to walk along the coast because passing through the special national monument area of Sa Huynh culture.
On 9.2, during the scene inspection trip at the coastal road project of Dung Quat - Sa Huynh of the Prime Minister Pham Minh Chinh, the leader of Quang Ngai province proposed the Prime Minister to direct the Ministry of Natural Resources and Environment The unified opinion allows the province to deploy the Km76+230 - Km82+000 route according to the previous recommendation to comply with the mineral planning in the Prime Minister's Decision No. 333.
For the remaining route that has not been invested, the leaders of Quang Ngai province proposed the Central Government to consider supporting the funding source of nearly VND 2,500 billion for the province to have funds to complete the project in the medium -term period of 2026 - 2030.
Through listening to the report and recommendations of Quang Ngai province, the Prime Minister Pham Minh Chinh asked the research ministries to propose and remove obstacles to invest in completing the project. "For the locality, it is necessary to continue implementing the project as quickly as possible. Where the ground is constructed there, construction of rolling.