Quang Ngai coastal road project is difficult because of overlapping planning

VIÊN NGUYỄN |

A section at the Dung Quat - Sa Huynh coastal road project in Quang Ngai overlapped with the boundary of Titan mineral exploration and exploitation.

The Dung Quat - Sa Huynh coastal road project is about 100km long, with 7 sections, with a starting point at Km 23+500 and the end point connected to the coastal route of Binh Dinh province through Km125+645 (excluding 23 , 5km belonging to the transport infrastructure planning of Dung Quat Economic Zone, connecting to Chu Lai airport, Quang Nam province). The project is invested by the Management Board of Traffic Construction Investment in Quang Ngai province

According to the investor, after many years of construction, the province has put into operation for more than 32km. Currently, more than 25 km from Km56 - Km69 - Km76+230 with a total investment of nearly VND 2,100 billion. Project construction progress reaches about 80%.

In the course of implementation, there are some certain difficulties related to compensation and site clearance, especially after the new land law takes effect, partly affecting the general progress of the attendance. sentence. However, with high determination, the province is focusing on leading and directing to complete the entire route under construction and put into operation in 2025. invest. In particular, the paragraph from Km76+230 - Km82 has completed construction design documents.

However, this section has overlapped with the boundary of Titan mineral exploration and exploitation approved by the Prime Minister. Therefore, the province must pause and are waiting for the opinion of the Ministry of Natural Resources and Environment to serve as a basis for implementing the next steps.

For the route from Km82 - Km107+200 and Km119+500 connected to Binh Dinh province, the construction investment has not been implemented due to the lack of capital. Particularly, the section of Km107+200 - Km119+500 goes to the National Highway 1 because it is impossible to walk along the coast because passing through the special national monument area of ​​Sa Huynh culture.

On 9.2, during the scene inspection trip at the coastal road project of Dung Quat - Sa Huynh of the Prime Minister Pham Minh Chinh, the leader of Quang Ngai province proposed the Prime Minister to direct the Ministry of Natural Resources and Environment The unified opinion allows the province to deploy the Km76+230 - Km82+000 route according to the previous recommendation to comply with the mineral planning in the Prime Minister's Decision No. 333.

For the remaining route that has not been invested, the leaders of Quang Ngai province proposed the Central Government to consider supporting the funding source of nearly VND 2,500 billion for the province to have funds to complete the project in the medium -term period of 2026 - 2030.

Through listening to the report and recommendations of Quang Ngai province, the Prime Minister Pham Minh Chinh asked the research ministries to propose and remove obstacles to invest in completing the project. "For the locality, it is necessary to continue implementing the project as quickly as possible. Where the ground is constructed there, construction of rolling.

VIÊN NGUYỄN
TIN LIÊN QUAN

Quang Ngai needs to focus on developing social housing

|

It was the direction of the Prime Minister Pham Minh Chinh at the meeting with the Standing Committee of Quang Ngai Provincial Party Committee on the afternoon of 9.2.

The Prime Minister checked two key projects in Quang Ngai

|

Prime Minister Pham Minh Chinh praised the spirit of work through the ceremony and New Year of officials, engineers and workers who are constructing Quang Ngai - Hoai Nhon highway, and requires the contractor to make efforts to put the route into operation. Before December 31, 2025.

The first steel arch bridge in Quang Ngai is about to be completed

|

Tra Khuc 3 bridge with the first steel arch design in Quang Ngai has constructed the construction value of the whole project reaching over 90%. Expected destination in the second quarter/2025.

8pm News: Unsuccessful mediation in lawsuit over torn lottery ticket worth 2 billion VND

|

8pm News on February 13: Domestic gasoline prices increase simultaneously; Unsuccessful mediation in lawsuit over torn lottery ticket worth 2 billion VND...

Vietnam supports efforts to reconcile and end the conflict in Ukraine

|

Vietnam supports the mediation efforts of the international community to seek a lasting peaceful solution to the conflict in Ukraine.

3 former volleyball players expected to return in 2025

|

Nguyen Thi Ngoc Hoa, Nguyen Linh Chi and Bui Thi Nga are three former volleyball players expected to return in 2025.

Photographer and garden owner earn hundreds of millions of dong during plum blossom season

|

Son La - The white plum blossom season in Moc Chau is considered the "harvest season" of many accompanying services such as photography, makeup, long-term accommodation...

Queuing up to register for tutoring business

|

Dak Lak - Many people in Buon Ma Thuot city registered their tutoring businesses before Circular 29 of the Ministry of Education and Training took effect.

Quang Ngai needs to focus on developing social housing

VIÊN NGUYỄN |

It was the direction of the Prime Minister Pham Minh Chinh at the meeting with the Standing Committee of Quang Ngai Provincial Party Committee on the afternoon of 9.2.

The Prime Minister checked two key projects in Quang Ngai

VIÊN NGUYỄN |

Prime Minister Pham Minh Chinh praised the spirit of work through the ceremony and New Year of officials, engineers and workers who are constructing Quang Ngai - Hoai Nhon highway, and requires the contractor to make efforts to put the route into operation. Before December 31, 2025.

The first steel arch bridge in Quang Ngai is about to be completed

VIÊN NGUYỄN |

Tra Khuc 3 bridge with the first steel arch design in Quang Ngai has constructed the construction value of the whole project reaching over 90%. Expected destination in the second quarter/2025.