Project worth nearly 3,838 billion VND in Can Tho is slow, facing a series of difficulties

Tạ Quang |

Can Tho - The Western Ring Road project with a total capital of nearly 3,838 billion VND is behind schedule due to a series of difficulties.

The Western Ring Road project of Can Tho City (National Highway 91 - National Highway 61C) has a total investment of nearly 3,838 billion VND, implementation time from 2021 - 2026, is one of the key projects of the city.

The project is divided into 7 construction packages. Currently, 4 packages are being implemented, including packages 16, 17, 19 and 20. The remaining three packages (15, 18, 21) have not been bid because they are waiting for the adjustment of the total investment.

Dự án đường Vành đai phía Tây TP Cần Thơ (Quốc lộ 91 – Quôc lộ 61C) ảnh tư liệu 2024. Ảnh: Tạ Quang
Can Tho City Western Ring Road Project (National Highway 91 – National Highway 61C) (file photo 2024). Photo: Ta Quang

Mr. Mai Van Tan - Director of Can Tho City Department of Construction said that so far, the project has handed over over over 50% of the construction site, but the site is not continuous, so it cannot be deployed synchronously. From January 2024, this work was stopped due to exceeding the total investment.

The total realized value of 4 bidding packages (16, 17, 19 and 20) reached approximately 960.939/2. 162.053 billion VND, equivalent to 44.44% of the contract value.

Regarding the capital plan for 2026, as of March 13, 2026, the Department of Construction was assigned 124 billion VND and has disbursed 3,571 billion VND, reaching 2.9%.

Công nhân thi công Dự án đường Vành đai phía Tây TP Cần Thơ (ảnh tư liệu 2024). Ảnh: Tạ Quang
Workers constructing the Western Ring Road Project of Can Tho City (file photo 2024). Photo: Ta Quang

Site clearance work is currently temporarily suspended due to exceeding the total investment. Although the site clearance cost has been disbursed reaching 99.76% compared to the approved cost, in fact only about more than 50% of affected cases have been handled. From the beginning of 2024 to now, compensation cannot continue, leading to land division, and contractors are only constructing sparingly on the handed-over area.

In addition, resettlement work does not meet the conditions for handover. Some resettlement areas are in the process of completing infrastructure, there is no land price, so it is not possible to hand over land to people. Phong Dien currently does not have a resettlement area to serve the project. This slows down the relocation progress, leading to slow land handover.

The relocation of technical infrastructure is also facing difficulties due to the incomplete dossiers and procedures as a basis for compensation and support. Medium and low voltage electricity, water supply and drainage, and telecommunications items are in the process of completing procedures, so the relocation cannot be implemented, directly affecting the construction progress.

The project is lacking sand for foundation filling. The demand for sand is about 1.77 million m3, but only about 0.3 million m3 has been implemented, and nearly 1.5 million m3 have not been identified for supply. The current sand source is concentrated for expressway projects, the price is high compared to the contract price, reducing the roadbed construction capacity and risking prolonging the progress.

The western ring road project of Can Tho City has the starting point intersecting with National Highway 91 (at Km20+370) and intersecting with Provincial Road 922, the ending point intersecting with National Highway 61C (at Km1+400 National Highway 61C), which was started by the Prime Minister on November 17, 2022. The project has a total investment of nearly 3,838 billion VND.

The project has a total length of more than 19 km. According to the project design, the cross-section of the route is invested in 2 units, each side 16.5m (of which the road surface is 11m), the design speed is from 50 - 60 km/h. Project implementation time is from 2021 - 2026.

Tạ Quang
RELATED NEWS

Causes of garbage congestion for many days in Can Tho central ward

|

Can Tho - Garbage accumulates for many days in the central ward of Can Tho due to changes in collection units, causing disruption and affecting people's lives.

Project of over 31,200 billion VND in Can Tho lacks millions of cubic meters of sand

|

Can Tho - The Chau Doc - Can Tho - Soc Trang expressway project is facing a shortage of materials as the amount of sand brought to the construction site does not meet construction needs.

Can Tho requests no mechanics in the implementation of National Highway 91 project

|

Can Tho - Chairman of Can Tho City People's Committee requests all levels and sectors not to be mechanical or evade responsibility in implementing the project to upgrade and expand National Highway 91.

Live volleyball VTV Binh Dien Long An vs Hoa Chat Duc Giang Lao Cai

|

Live match between VTV Binh Dien Long An and Hoa Chat Duc Giang Lao Cai at the 2026 National Volleyball Championship, taking place at 12:00 PM today (April 13).

Recall of grade 3 textbooks containing unsafe links in Hue

|

HUE - Hue University Publishing House recalls "Informatics Worksheet 3" containing unsafe links, stops issuing, refunds and coordinates with functional agencies for handling.

World Cup 2026 copyright prices in Southeast Asian countries

|

The story of World Cup 2026 television rights in Southeast Asia shows the disparity between markets.

There is no "safe zone" for the leader if leadership is relaxed

|

Head of the Central Propaganda and Mass Mobilization Commission Trinh Van Quyet clearly stated that there is no "safe zone" for the head if leadership is relaxed.

Piloting the delegation of power from higher levels to the Party Committee of grassroots Party committees directly under communes and wards

|

Regulation No. 20-QD/TW has supplemented the regulation on piloting the delegation of powers from higher levels to the Party committees of grassroots Party committees directly under the Party committees of communes, wards, and special zones.

Causes of garbage congestion for many days in Can Tho central ward

Tạ Quang |

Can Tho - Garbage accumulates for many days in the central ward of Can Tho due to changes in collection units, causing disruption and affecting people's lives.

Project of over 31,200 billion VND in Can Tho lacks millions of cubic meters of sand

Tạ Quang |

Can Tho - The Chau Doc - Can Tho - Soc Trang expressway project is facing a shortage of materials as the amount of sand brought to the construction site does not meet construction needs.

Can Tho requests no mechanics in the implementation of National Highway 91 project

Tạ Quang |

Can Tho - Chairman of Can Tho City People's Committee requests all levels and sectors not to be mechanical or evade responsibility in implementing the project to upgrade and expand National Highway 91.