3,500 billion VND traffic project in Quang Ngai struggles due to land clearance problems

VIÊN NGUYỄN |

Quang Ngai - Slow site clearance and not seamless handover areas have caused many difficulties in the construction progress of the Hoang Sa - Doc Soi road project.

The Hoang Sa - Doc Soi road project has a route length of 26.88 km with a total investment of VND 3,500 billion, of which the central budget is VND 1,300 billion and the provincial budget is VND 2,200 billion (from land use fee revenue), invested by the Quang Ngai Traffic Construction Investment Project Management Board. The implementation period is from 2022 to 2027. This is a key traffic project of Quang Ngai province.

According to the investor's report, the planned area of the main route is 172.16 hectares, passing through the following localities: Binh Son commune (35.51 ha), Van Tuong commune (22.52 ha), Dong Son commune (51.39 ha), Tho Phong commune (16.88 ha), Tinh Khe commune (19.21 ha) and Truong Quang Trong ward (26.64 ha). The project invests in the construction of 10 resettlement areas with 648 plots of land, 01 burial area; at the same time, using 25 plots of land in Lien Hiep I Resettlement Area (expanded), Truong Quang Trong Ward to arrange resettlement.

Tien do thi cong cham tre do dien tich mat bang ban giao con thap, chua lien mach. Hien nay, nha thau chu yeu chi co the trien khai thi cong tai cac vi tri cau, cong ngang. Anh: Vien Nguyen
The construction progress is delayed due to the low handover area and not being seamless. Currently, contractors can mainly only implement construction at bridge and cross-culvert locations. Photo: Vien Nguyen

Regarding site clearance (GPMB) for the main route, up to now, 44 plans have been approved for 48.1/172.16 hectares, reaching 27.9%; more than 56/172.16 hectares, reaching 32.6%. Corresponding to the handed-over site, the construction value reached about 528/2,350 billion VND, equal to 22.5% of the construction volume.

The biggest difficulty at present is compensation and slow site clearance, the handover area to the construction unit is still small, not seamless, affecting the construction progress and capital disbursement.

At the end of August 2025, the leaders of the Provincial People's Committee requested the Provincial Land Fund Development Center and the People's Committees of relevant communes and wards to focus on coordination, speed up progress, and complete site clearance for agricultural and non-agricultural land areas. The Department of Agriculture and Rural Development and the Department of Finance urgently provide specific instructions on the plan to determine land prices for areas outside the planning, as well as mechanisms, policies, authority and responsibility in implementing land acquisition.

The leaders of the Provincial People's Committee also requested the People's Committees of communes and wards where the project passes through to promptly complete all documents and confirmation procedures so that the Provincial Land Fund Development Center can promptly publicly post, submit for appraisal and approve the compensation plan for the following installments.

For households that have not received money according to the approved compensation plan, the locality is required to continue to guide people to complete inheritance and authorization procedures to receive money; at the same time, promote propaganda, mobilization, and create consensus in handing over the site for investors to implement the project to ensure progress.

VIÊN NGUYỄN
RELATED NEWS

3,000 workers work through the September 2 Ceremony for the progress of the Quang Ngai - Hoai Nhon Expressway project

|

Whether it is a normal day or a holiday or Tet holiday, for more than 2 years, thousands of workers, engineers... have been working tirelessly at the Quang Ngai - Hoai Nhon expressway construction site, determined to complete the project on schedule by the end of 2025.

Workers work through the September 2 ceremony to ensure the progress of Quang Ngai Expressway

|

The Quang Ngai - Hoai Nhon Expressway project mobilized 3,000 human resources, constructing through the September 2 ceremony, striving to complete the project by the end of 2025.

Promoting investment in social housing in Quang Ngai

|

Quang Ngai - Accelerate the development of social housing, aiming to complete 8,500 units by 2030, creating a sustainable housing fund for low-income people and workers.

Special features of Vietnam Night in Ho Chi Minh City

|

Ho Chi Minh City - The Vietnam Night Art Program is a welcome from Ho Chi Minh City to friends from 5 continents, a city with a new look, new space, new potential.

The success of the parade and march reflects the endless growth of the Army

|

According to General Phan Van Giang, the success of the parade and march reflects the maturity and constant growth of the heroic Vietnam People's Army.

The Ministry of Construction requests to tighten management after the fire at the Vinh Tuy bridge underpass

|

The Ministry of Construction has just requested a review of the management and use of road safety corridors after the fire at the parking lot under Vinh Tuy Bridge.

The brilliant A80 roses return to Ho Chi Minh City after completing their mission

|

HCMC - On the afternoon of September 3, the female pilots performing the A80 mission boarded a flight from Hanoi back to HCMC in the arms of the people and the joy and pride of the people.

The Politburo gives opinions on the personnel plan for the Party Congresses of An Giang and Lam Dong provinces

|

The Politburo worked with the Standing Committees of the An Giang and Lam Dong Provincial Party Committees to give opinions on the draft documents and personnel plans to submit to the Party Congresses of the two provinces.

3,000 workers work through the September 2 Ceremony for the progress of the Quang Ngai - Hoai Nhon Expressway project

Viên Nguyễn |

Whether it is a normal day or a holiday or Tet holiday, for more than 2 years, thousands of workers, engineers... have been working tirelessly at the Quang Ngai - Hoai Nhon expressway construction site, determined to complete the project on schedule by the end of 2025.

Workers work through the September 2 ceremony to ensure the progress of Quang Ngai Expressway

Viên Nguyễn |

The Quang Ngai - Hoai Nhon Expressway project mobilized 3,000 human resources, constructing through the September 2 ceremony, striving to complete the project by the end of 2025.

Promoting investment in social housing in Quang Ngai

VIÊN NGUYỄN |

Quang Ngai - Accelerate the development of social housing, aiming to complete 8,500 units by 2030, creating a sustainable housing fund for low-income people and workers.