Reservoir project worth nearly 500 billion VND in Lam Dong deformed due to landslides

LAM HỒNG |

Lam Dong - The Dong Thanh reservoir project has an investment capital of nearly 500 billion VND but was under construction when it suffered a serious landslide, and has not yet been repaired.

The Dong Thanh reservoir project in Nam Ban Lam Ha commune (Lam Dong province) was once highly anticipated.

However, up to now, the project is facing many challenges regarding landslides and completing related procedures.

Hang muc cong trinh bi hu hong. Anh: Lam Hong
The construction items were damaged. Photo: Lam Hong

According to documents, the Dong Thanh Reservoir Project will start construction in 2022. The total area of the project is over 48 hectares, with a total investment of nearly 500 billion VND.

The project is expected to be completed and put into use in 2024, providing irrigation water for 700 hectares of cultivated land and domestic water for 7,500 households.

However, in July 2023, during the construction process, the project area experienced serious subsidence and landslides.

Cong trinh bi sat truot. Anh: Lam Hong
The project was eroded. Photo: Lam Hong

According to records, the landslide has caused many reinforced concrete items of the project to be seriously deformed and damaged.

Specifically, the flood discharge of the project was cracked and deviated from the original location. The connection between the two concrete blocks was separated, causing the outer soil to be seriously eroded by rainwater.

The landslide not only affected the project but also affected many households in Dong Anh village, Nam Ban Lam Ha commune.

One of the affected households said that the 10cm thick concrete roadbed was cracked, with an opening of nearly 20cm.

Notably, after 2 years of landslides, the villa worth more than 3 billion VND of Mr. Nguyen Van Thang's family became dilapidated and deserted.

Can nha bi anh huong do sat truot. Anh: Lam Hong
The house was affected by the landslide. Photo: Lam Hong

Many items of the house are gradually cracking and collapsing. A local resident said that Mr. Thang's family had not completed and moved to a new house until recently when the Dong Thanh reservoir area had sunk.

Mr. Thang has now moved to another place to live to ensure safety.

According to the leader of the People's Committee of Nam Ban Lam Ha commune (Lam Dong), the locality has installed landslide warning signs at many locations in the project area.

At the same time, local authorities are coordinating with relevant agencies to complete documents and procedures, and implement resettlement areas for affected households.

Regarding the above project, in April 2024, Lam Dong Provincial Inspectorate announced the inspection conclusion, pointing out many violations.

Accordingly, the project has not been completed according to the set target. The competent authority (old Lam Ha District People's Committee) has not yet approved the resettlement land price. This project has not yet completed land procedures...

LAM HỒNG
RELATED NEWS

Wastewater reservoir in the center of Quang Ngai is revived after ten years of causing pollution and flooding

|

Quang Ngai - The Bau Ca Lake and Song Dao Canal dredging project aims to increase water capacity, treat odors, reduce flooding, improve the environment and urban beauty.

Avoiding flooding thanks to an artificial reservoir worth over VND730 billion in Son La

|

Son La - After nearly 4 years of operation, the Mong village reservoir in Son La has been effective in cutting floodwaters, preventing floods and regulating irrigation water for downstream areas.

Investing 570 billion VND to build a reservoir in Phu Tho

|

Phu Tho - Thuc Luyen Reservoir Project, Phu Tho province with a total investment of 570 billion VND has begun to find contractors to construct the construction package.

Western tourists are excited to watch the 2.9 parade with the people

|

Foreign tourists eagerly watched the parade and parade before the 80th anniversary of National Day on September 2.

President Zelensky sets out conditions to meet President Putin

|

Ukrainian President Volodymyr Zelensky said his meeting with President Vladimir Putin could take place after security guarantees are agreed upon.

Setting up fences, fixing landslides on the main artery in Thai Nguyen

|

Thai Nguyen - After reporting the landslide on the route connecting Phuong Tien commune - Cho Moi commune, the management unit has set up barriers and raised warnings to ensure safety.

Dismantling a virtual currency capital mobilization ring that appropriated more than 200 billion VND

|

Hanoi City Police have just dismantled a group of subjects mobilizing virtual currency capital, appropriating about 200 billion VND from more than 3,000 investors.

Air Force squadron practices parade in Hanoi sky

|

This morning (8.21), the air force of Mi-17 and L-39NG helicopters practiced parading in the sky of Hanoi.

Wastewater reservoir in the center of Quang Ngai is revived after ten years of causing pollution and flooding

VIÊN NGUYỄN |

Quang Ngai - The Bau Ca Lake and Song Dao Canal dredging project aims to increase water capacity, treat odors, reduce flooding, improve the environment and urban beauty.

Avoiding flooding thanks to an artificial reservoir worth over VND730 billion in Son La

TRƯỜNG SƠN |

Son La - After nearly 4 years of operation, the Mong village reservoir in Son La has been effective in cutting floodwaters, preventing floods and regulating irrigation water for downstream areas.

Investing 570 billion VND to build a reservoir in Phu Tho

Tô Công |

Phu Tho - Thuc Luyen Reservoir Project, Phu Tho province with a total investment of 570 billion VND has begun to find contractors to construct the construction package.