Road expansion project to 53m in Hanoi completes after 15 years

SÓNG HỮU |

Hanoi - The project to renovate and upgrade National Highway 1A, Van Dien - Ngoc Hoi section (Km185 - Km189) 3.8km long, with a capital of 887 billion VND, has been completed after 15 years of construction.

The project to renovate and upgrade National Highway 1A, Van Dien - Ngoc Hoi section (Km185 - Km189), Hanoi City is a group B project, level I project.

The project has a total length of 3.8km, a cross-section of 46-53m, including renovation and upgrading of the foundation, road surface, drainage, technical trenches, lighting, sidewalks, green trees, and traffic organization.

The project has a total investment of 887.735 billion VND (of which construction costs are 297.614 billion VND).

Project implementation time: 2011 - Q1/2026.

Regarding the capital plan, the Hanoi Traffic Construction Investment Project Management Board said that the accumulated disbursement to the beginning of April 2026 is 774.074 billion VND. Capital has not been allocated in 2026.

Regarding the implementation situation, the project was completed in the first quarter of 2026 in accordance with the direction of the Hanoi Party Secretary in Notice No. 144-TB/TU dated December 22, 2025.

SÓNG HỮU
RELATED NEWS

Clearing a series of works to hand over land for the construction of Tu Lien bridge

|

Hanoi - Many projects in alley 310 Nghi Tam are being urgently demolished and handed over land to serve the construction of Tu Lien bridge across the Red River.

Progress of road expansion project to 60m, capital of more than 9,590 billion VND in Hanoi

|

Hanoi - The construction of bridges and roads under the National Highway 6 expansion project, Ba La - Xuan Mai section, is being implemented by contractors.

National Highway 1A overpass project in Hanoi gradually appears after 1.5 years of construction

|

Hanoi - Duong Truc Nguyen overpass across National Highway 1A and the North-South railway has a total investment of 283 billion VND, expected to be completed in 2026.

US-Iran negotiations encounter difficulties, cargo ship turns around in front of the Hormuz Strait

|

Global energy market shakes as oil tanker turns back from the Strait of Hormuz after US-Iran negotiations collapse.

Gold price update at the closing session 12. 4: Heavy losses after a week of spending money

|

Gold price update closing session 12. 4: Domestic gold buyers lose up to 5.1 million VND/tael after a week of spending money.

Typhoon Sinlaku is about to strengthen into a super typhoon in the next 24 hours, gusting above level 17

|

Forecast for the next 24 hours, Typhoon Sinlaku is likely to strengthen into a super typhoon; maximum intensity level 16-17, gusts above level 17/

Live Vietnam futsal team vs Australia, 3rd place match in Southeast Asian Championship

|

Live football match of Vietnam futsal team against Australia in the 3rd place match of the 2026 Southeast Asian Futsal Championship at 5:00 PM today (April 12).

Fire scene at a wood exhibition area in Ha Tinh, a smoke column tens of meters high

|

Ha Tinh - A large fire occurred at a wood exhibition area in Thanh Sen ward in the middle of the day, black smoke was billowing, functional forces controlled the scene.

Clearing a series of works to hand over land for the construction of Tu Lien bridge

SÓNG HỮU |

Hanoi - Many projects in alley 310 Nghi Tam are being urgently demolished and handed over land to serve the construction of Tu Lien bridge across the Red River.

Progress of road expansion project to 60m, capital of more than 9,590 billion VND in Hanoi

SÓNG HỮU |

Hanoi - The construction of bridges and roads under the National Highway 6 expansion project, Ba La - Xuan Mai section, is being implemented by contractors.

National Highway 1A overpass project in Hanoi gradually appears after 1.5 years of construction

SÓNG HỮU |

Hanoi - Duong Truc Nguyen overpass across National Highway 1A and the North-South railway has a total investment of 283 billion VND, expected to be completed in 2026.