The project to expand Hanoi's central road to 21m is delayed to the end of 2026

SÓNG HỮU |

Hanoi - The Nguyen Tuan Street expansion project, with an investment capital of nearly 400 billion VND, is expected to be completed in March 2026 instead of 2025 as originally planned.

The project to renovate and expand Nguyen Tuan Street was approved by the People's Committee of the old Thanh Xuan District in 2018, with a total investment of nearly 400 billion VND.

The project is 720m long, starting at the intersection with Nguyen Trai Street, ending at Lane 162 Nguyen Tuan, with a cross-section of 21m, including a 15m wide roadway and 3m wide sidewalks on both sides.

To implement the project to renovate and expand Nguyen Tuan Street, Thanh Xuan District must reclaim and clear 14,334m2 of land from 11 organizations and 160 households and individuals.

However, the above traffic project could not be implemented according to the original plan because many households did not agree to hand over the site.

After many propaganda and mobilization campaigns, it was not until November 2024 that the site clearance for the Nguyen Tuan Street expansion project was basically completed.

The local government has since handed over most of the site to the contractor to implement the project, aiming to complete the project in 2025.

From July 1, after operating the two-level government, the Nguyen Tuan Street expansion project was transferred to Thanh Xuan Ward People's Committee as the investor.

Den nay doan tu ngo 162 duong Nguyen Tuan den nut giao duong Nguyen Huy Tuong da co ban hoan thanh mo rong. Anh: Song Huu
Up to now, the section from lane 162 Nguyen Tuan street to the intersection of Nguyen Huy Tuong street (Thanh Xuan ward, Hanoi) has been basically completed. Photo: Song Huu
Mat cat ngang duoc mo rong len 21m. Anh: Song Huu
The cross-section is expanded to 21m. Photo: Song Huu
Mot doan duong Nguyen Tuan duoc mo rong giup nguoi dan di lai thuan loi. Anh: Song Huu
A section of Nguyen Tuan Street has been expanded to help people travel conveniently. Photo: Song Huu
Vat lieu, trang thiet bi xay dung
Construction materials and equipment are scattered along the route. Photo: Song Huu

According to records, up to now, the Nguyen Tuan Street expansion project has completed the C19 raw grain asphalt concrete section for the road surface to renew the section from alley 162 Nguyen Tuan to Nguyen Huy Tuong intersection.

At this section, the construction unit has removed the corrugated iron fence, expanded the technical system, and ensured ventilation to serve the 80th Anniversary of National Day on September 2.

Speaking to Lao Dong Newspaper reporter, Mr. Dang Hoang Linh (Director of the Investment - Infrastructure Project Management Board of Thanh Xuan Ward) said that the construction unit is currently implementing the installation of sewers and accelerators for the water supply and drainage system; at the same time, constructing the installation of a pipeline system for communication and lighting.

Hien doan tu nut giao duong Nguyen Huy Tuong den dau tuyen dang duoc thi cong. Anh: Song Huu
The section from the intersection of Nguyen Huy Tuong Street to the beginning of the route is under construction and expansion. Photo: Song Huu
Cong truong du an mo rong duong Nguyen Tuan chieu 14.8. Anh: Song Huu
Construction site of the Nguyen Tuan Street expansion project on the afternoon of August 14. Photo: Song Huu
Mot cong trinh tren tuyen chua duoc giai phong mat bang. Anh: Song Huu
A project on the route has not been cleared. Photo: Song Huu
Ha tang ky thuat phia trai tuyen chua duoc di doi. Anh: Song Huu
The technical infrastructure on the left side of the route has not been relocated. Photo: Song Huu

However, according to the Director of the Thanh Xuan Ward Infrastructure Investment Project Management Board, the project implementation process still faces some difficulties and problems.

Accordingly, in the process of converting local government at 2 levels, it is necessary to change investors and bidding processes, so some bidding packages do not ensure the progress as originally planned (package for relocating power systems, information systems...).

Regarding compensation and site clearance, Mr. Dang Hoang Linh said that there is currently a case at address 35A Nguyen Tuan Street of 6 households in an old 2-storey apartment building that does not have a specific land price to calculate compensation when the state reclaims land to implement the project.

Due to the need to resolve some shortcomings as well as difficulties and problems, the completion progress of the entire project was postponed to March 2026, instead of 2025 as originally planned.

SÓNG HỮU
RELATED NEWS

Clearing a series of constructions, preparing to expand Nguyen Tuan street

|

Hanoi - It is expected that in December, Thanh Xuan district will complete the clearance of construction works to expand Nguyen Tuan street, 720m long, with a capital of nearly 400 billion VND.

Controlling a fire at a company in Ho Chi Minh City, a column of black smoke tens of meters high

|

HCMC - In Tan Hiep ward, a company fire broke out, with a column of black smoke rising tens of meters high.

American man dies while dating an AI chatbot

|

Meta's AI Chatbot claimed to be a real person, provided the apartment address and invited this man to meet in New York (USA).

Ms. Paetongtarn explains the discussion with Mr. Hun Sen as negotiation technique

|

Ms. Paetongtarn Shinawatra affirmed that the contents of the conversation with Mr. Hun Sen were part of her negotiation technique.

Duc Tien's wife gives reasons for remaining silent during the litigation of real estate assets with her mother-in-law

|

Miss Binh Phuong - Duc Tien's wife said that recently, Binh Phuong chose to remain silent in the property lawsuit with her mother-in-law for her own reasons.

Scene of the boiler explosion at a company in Ho Chi Minh City

|

HCMC - The explosion of the glass boiler at a company in Tan Son Nhi ward caused part of the factory to collapse, fortunately there were no casualties.

Closing the hundred-billion-dong dike that caused people to suffer: 8 households were granted land to live in

|

Phu Tho - After Lao Dong's reflection, 8 households that lost land to the project in Dieu Luong commune, the old Cam Khe district (now Dong Luong commune) were granted residential land.

28 enterprises will be honored as "Outstanding Enterprises for Workers"

|

The "Outstanding Enterprise for Workers" Award is scheduled to take place at 7:30 p.m. on August 15.

Ì ạch thi công mở rộng đường Nguyễn Tuân, Hà Nội

HỮU CHÁNH |

Hà Nội - Hoạt động thi công diễn ra ì ạch trên công trường mở rộng đường Nguyễn Tuân dù mặt bằng đã được bàn giao cách đây gần 3 tháng.

Clearing a series of constructions, preparing to expand Nguyen Tuan street

HỮU CHÁNH |

Hanoi - It is expected that in December, Thanh Xuan district will complete the clearance of construction works to expand Nguyen Tuan street, 720m long, with a capital of nearly 400 billion VND.

Tiến độ dự án 400 tỉ đồng mở rộng, cải tạo đường Nguyễn Tuân

Tuấn Anh |

Dự án mở rộng đường Nguyễn Tuân (Thanh Xuân, Hà Nội) đang hoàn thiện giải phóng mặt bằng và chuẩn bị khởi công nhằm xóa điểm đen về ùn tắc tại khu vực này.