Planned spending of nearly 8.5 billion VND to demolish the remaining section of Phong Chau bridge

Tô Công |

Phu Tho - The Department of Transport estimates a budget of nearly 8.5 billion VND to demolish the remaining spans and pillars of Phong Chau bridge, which is at risk of collapsing.

Recently, the Department of Transport of Phu Tho province issued document No. 3347/PA-SGTVT, outlining a plan to demolish the remaining spans and pillars of Phong Chau bridge (mainly the part belonging to Phung Nguyen commune, Lam Thao district).

Doan cau Phong Chau con lai o thoi diem hien tai. Anh: To Cong.
The remaining section of Phong Chau bridge at present. Photo: To Cong

According to the document, after preparing the demolition site, based on the actual situation, it is expected to mobilize many means of transportation and dismantling such as: 7-10 excavators with pliers, hydraulic hammers, 2 160-ton cranes; many types of specialized hand-held machines...

Regarding human resources, it is expected to mobilize from 30 to 40 people to organize 2 construction teams (team 1 on Lam Thao district side to handle span 1-5, team 2 on Tam Nong district side to handle span 8). Depending on the actual conditions of the demolition, more human resources will be mobilized to ensure progress.

Theo nhan dinh cua mat cau nhip so 5 (N5) da bi nghieng ra ngoai phia long song Hong (co dau hieu tru T6 bi sut lun). Cac nhip cau so 4, 3, 2 co dau hieu bi van, nghieng theo chieu dong chay cua song Hong, cac khe co gian (noi giua cac nhip cau) bi gian ra nhieu so voi thiet ke ban dau
There will be 7 construction steps to demolish the remaining structures of Phong Chau bridge. Photo: To Cong

In terms of time, the total expected construction progress from site preparation to completion of site clearance, acceptance and handover of completed demolition work at the site is about 45 days.

Ong Nguyen Chi Loi - Pho Giam doc So Giao thong van tai tinh Phu Tho (ben trai ngoai cung) chi dao cong tac pha do, truc vot ket cau cau Phong Chau duoi song. Anh: To Cong.
Mr. Nguyen Chi Loi - Deputy Director of the Department of Transport of Phu Tho province (left, far right) - directed the demolition and salvage of the Phong Chau bridge structure, the part submerged under the river. Photo: To Cong

The estimated implementation cost is nearly 8.5 billion VND, calculated based on the estimated implementation time; implementation volume; number of human resources, machinery, and equipment actually deployed at the site according to the prescribed norms and unit prices, and some estimated norms proposed by Truong Son Construction Corporation. The implementation value is determined based on the demolition estimate plan approved by the competent authority and the approved final settlement value of the project.

Tô Công
RELATED NEWS

Proposal to stop searching for missing victims at Phong Chau bridge

|

Phu Tho - The search for missing people at Phong Chau bridge is facing many difficulties due to the large amount of mud, sand, trash, fast-flowing water, and limited visibility in the river...

Besides Phong Chau bridge, Phu Tho has many weak bridges

|

Phu Tho - Many bridges on provincial roads are old and weak but have not been repaired for many years, and still carry countless series of heavy-duty trucks every day.

Close-up of the remaining Phong Chau bridge section at risk of collapsing

|

Phu Tho - The Department of Transport needs to urgently research plans and solutions to dismantle the remaining part of Phong Chau bridge, which is currently at risk of collapsing.

Official information on the case of a teacher suspected of "locking up" students in a class in Son La

|

Son La - Local authorities have just officially announced the case of a teacher suspected of "locking up" students in a classroom in Nam Lau commune.

Gold ring prices slow down, many people take advantage of buying year-end gifts

|

On February 11, the price of plain gold rings did not fluctuate compared to yesterday morning. In Hanoi, many people took the opportunity to queue to buy.

Peach blossoms bloom early, small traders throw away branches exposed on the sidewalk

|

Thanh Hoa - Because some peach trees bloomed early and there were no buyers, small traders cut down branches and left them exposed on the sidewalk.

US unexpectedly changes strategy, opening the door for Venezuelan oil and gas

|

The US Treasury Department officially licensed the export of oil and gas technology and equipment to Venezuela, marking a noteworthy move to ease sanctions.

Passenger car loses control on Cam Lam - Vinh Hao expressway, traffic jams prolonged

|

Khanh Hoa - A passenger car with license plate from Gia Lai province lost control on the Cam Lam - Vinh Hao expressway, crashing into a hard median strip, causing hundreds of vehicles to be congested.

Proposal to stop searching for missing victims at Phong Chau bridge

Tô Công |

Phu Tho - The search for missing people at Phong Chau bridge is facing many difficulties due to the large amount of mud, sand, trash, fast-flowing water, and limited visibility in the river...

Besides Phong Chau bridge, Phu Tho has many weak bridges

Bài và Ảnh: Tô Công |

Phu Tho - Many bridges on provincial roads are old and weak but have not been repaired for many years, and still carry countless series of heavy-duty trucks every day.

Close-up of the remaining Phong Chau bridge section at risk of collapsing

Tô Công |

Phu Tho - The Department of Transport needs to urgently research plans and solutions to dismantle the remaining part of Phong Chau bridge, which is currently at risk of collapsing.