The second runway at Long Thanh airport must be basically completed before December 19, 2025

HÀ ANH CHIẾN |

Dong Nai - Minister of Construction Tran Hong Minh requested ACV to complete the road connecting Long Thanh airport. The second runway will be basically completed before December 19.

On November 2, Minister of Construction Tran Hong Minh and the working delegation inspected the actual progress of the Bien Hoa - Vung Tau expressway project and Long Thanh airport.

Project Management Board 85 (Ministry of Construction) is the investor of Component Project 2 - Bien Hoa - Vung Tau Expressway and said: The entire section of the route, over 18 km long, has achieved more than 70% of the contract value.

The volume of K95 soil filling reached 84%, K98 filling reached 69%, crushed stone aggregate reached over 54%, cement reinforcement reached nearly 43%, and the asphalt concrete layer was deployed at about 20%. Along with that, the bridge system on the route also recorded positive changes with 96% of bored piles completed and 97% of pillar abutments completed; all 708 girder piles were cast.

Bo truong Bo Xay dung Tran Hong Minh lam viec voi lanh dao tinh Dong Nai va cac don vi lien quan ve tien do thi cong Du an Duong cao toc Bien Hoa - Vung Tau. Anh: HAC
Minister of Construction Tran Hong Minh worked with leaders of Dong Nai province and related units on the construction progress of the Bien Hoa - Vung Tau Expressway Project. Photo: HAC

Mr. Nguyen Van Long - Deputy Director in charge of Project Management Board 85 - said: To achieve the goal of opening the project's technical traffic before December 19, 2025 at the request of the Prime Minister, in the past, the investor has requested contractors to increase the maximum human resources and equipment to work overtime, "working day and night".

Mr. Nguyen Linh - Deputy Director of the Dong Nai Province Construction Investment Project Management Board (investor of Bien Hoa - Vung Tau Expressway Component 1 project) - also said: The contractor has used tarpaulin to construct on rainy days but the efficiency is not high. Currently, the investor units have requested the units to focus on sufficient material resources so that when the weather conditions are favorable, they must speed up construction to compensate for progress.

Bo truong Bo Xay dung Tran Hong Minh tai cong truong du an san bay Long Thanh. Anh: HAC
Minister of Construction Tran Hong Minh at the Long Thanh airport project site. Photo: HAC

Regarding the Long Thanh Airport Project, Mr. Nguyen Tien Viet - Deputy General Director in charge of Vietnam Airports Corporation (ACV) - said: The progress of the packages is currently basically meeting the progress. In particular, the construction of technical lines (underground works built underground to contain cables and technical pipelines) is a complex construction item that has now completed about 19.7 km out of a total of about 21.7 km of the entire project. Along with that, the construction progress of installing equipment at the passenger terminal is also being implemented synchronously.

Speaking at the construction site of projects when inspecting them, Minister of Construction Tran Hong Minh requested investors and contractors to focus to ensure the progress of projects; contractors must absolutely keep their commitment to complete projects on schedule; Accumulate enough raw materials and construction materials, especially construction stone for the construction of the Bien Hoa - Vung Tau Expressway Project.

For the Long Thanh Airport project, Minister of Construction Tran Hong Minh requested ACV to focus on completing the approach road from T1 route to the passenger terminal area as well as the two runways and landing routes of Long Thanh Airport, ensuring aesthetics.

The second runway must also be basically completed before December 19, 2025.

According to information from Vietnam Airports Corporation (ACV), package 4.12 - construction of the second runway at the Long Thanh airport project is being mobilized by the contractor consortium with more than 283 engineers and workers with 127 motorbikes and equipment for construction.

Package 4.12 started on May 30, 2025 by the ACC - Truong Son - Vinaconex - Vinadic - ACJC647 - Khanh Thien - VTG consortium.

HÀ ANH CHIẾN
RELATED NEWS

Reclaiming more than 134 hectares of land from 3 communes to upgrade and expand the road adjacent to Long Thanh airport

|

Dong Nai - The project to upgrade and expand provincial road 769, nearly 30km long, connecting to Long Thanh airport in Dau Giay, Binh An, Long Thanh communes.

Long Thanh airport is about to operate, ACV recruits hundreds of workers to help operate effectively

|

Dong Nai - Long Thanh Airport is operating in mid-2026, needing to recruit hundreds of workers to help the airport operate effectively.

Long Thanh Bridge is bustling with construction, accelerating the expansion of the expressway connecting Long Thanh airport

|

After more than two months of construction, the Ho Chi Minh City - Long Thanh expressway expansion project is accelerating construction, in which Long Thanh bridge is considered a key item.

The largest red carp village in Thanh land is rushing before the day of Ong Cong and Ong Tao

|

Thanh Hoa - Before the day of Ong Cong Ong Tao, in the largest red carp village in Thanh land, people are rushing to pull nets to harvest fish to supply to the market.

Busy bus stations and airports in Ho Chi Minh City, people rush home to celebrate Tet early

|

Ho Chi Minh City - On February 8th (ie December 21st of the lunar calendar), the atmosphere at bus stations and airports has begun to become bustling.

Z121 fireworks inflated prices on social networks

|

Near the Lunar New Year, the appeal of Z121 fireworks is increasing. On groups and "online markets", the price is 3 times higher.

Request to transfer principal after overcharging, teachers revise exam papers

|

Gia Lai - Department of Education and Training proposes to transfer the Principal of Nguyen Van Cu Primary School after reflecting overcharging, teachers arbitrarily amend students' exam papers.

Buses and Metro Line 1 in Ho Chi Minh City free of tickets during Lunar New Year

|

Ho Chi Minh City - Buses and Metro Line No. 1 (Ben Thanh - Suoi Tien) will be free of tickets during some Tet peak days, to serve the travel and entertainment needs of people.

Reclaiming more than 134 hectares of land from 3 communes to upgrade and expand the road adjacent to Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The project to upgrade and expand provincial road 769, nearly 30km long, connecting to Long Thanh airport in Dau Giay, Binh An, Long Thanh communes.

Long Thanh airport is about to operate, ACV recruits hundreds of workers to help operate effectively

HÀ ANH CHIẾN |

Dong Nai - Long Thanh Airport is operating in mid-2026, needing to recruit hundreds of workers to help the airport operate effectively.

Long Thanh Bridge is bustling with construction, accelerating the expansion of the expressway connecting Long Thanh airport

Anh Tú |

After more than two months of construction, the Ho Chi Minh City - Long Thanh expressway expansion project is accelerating construction, in which Long Thanh bridge is considered a key item.