Long Thanh Bridge is bustling with construction, accelerating the expansion of the expressway connecting Long Thanh airport

Anh Tú |

After more than two months of construction, the Ho Chi Minh City - Long Thanh expressway expansion project is accelerating construction, in which Long Thanh bridge is considered a key item.

After more than two months of construction, the Ho Chi Minh City - Long Thanh expressway expansion project is entering the peak construction phase. According to Lao Dong, the working atmosphere along the route is urgent all day and night, especially vibrant in Dong Nai - where the site has been basically completed.

 Cac nha thau dang tap trung may moc, thiet bi tai cau Long Thanh de mo rong cau hien huu tu 4 len 8 lan xe. Ảnh: Nham Nguyen
Contractors are focusing on machinery and equipment at Long Thanh bridge to expand the existing bridge from 4 to 8 lanes. Photo: Nham Nguyen
  Tai cong truong, cac nha thau dang khoan coc va do be tong mong tru giua long song. Day la buoc ky thuat dau tien cua hang muc mo rong cau. Ảnh: Nham Nguyen
At the construction site, contractors are drilling piles and pouring concrete for the foundation in the middle of the river. This is the first technical step of the bridge expansion project. Photo: Nham Nguyen

On the Dong Nai River, barges, cranes and drilling machines are operating continuously to construct the new Long Thanh bridge piers, the item that determines the progress of the entire project. On shore, engineers and workers take turns working, focusing on drilling piles, pouring foundations, and supervising techniques.

  Cong truong phia bo Dong Nai tap nap thi cong, nha thau tranh thu trien khai song song nho quy dat giai doan 1 da san sang. Cac mong tru cua duong dan cau Long Thanh phia Dong Nai dang dan thanh hinh. Anh: Anh Tu.
The construction site on the Dong Nai bank is bustling with construction, the contractor is taking advantage of the parallel implementation thanks to the ready land fund for phase 1. The foundations of the Long Thanh bridge approach road on the Dong Nai side are gradually taking shape. Photo: Anh Tu.

According to the Southern Expressway Project Management Board (SEPMU, under VEC), Long Thanh Bridge is the "gasoline" item of the entire route, prioritized for top-notch construction. Contractors are mobilizing maximum human resources and equipment to expand the existing bridge from 4 to 8 lanes. Five large equipment clusters including barges, cranes and drilling machines were deployed simultaneously under the Dong Nai River. Thanks to the land fund for phase 1, Dong Nai can construct many items in parallel.

 Trong khi do, tai cong truong phia TPHCM, dien tich mat bang sach it hon. Nha thau da tap ket may moc, nguyen vat lieu ve cong truong nhung phai thi cong cam chung do mat bang chat hep. Ảnh: Nham Nguyen
Meanwhile, at the construction site on the Ho Chi Minh City side, the clean site area is less. The contractor has gathered machinery and materials for the construction site but has to construct slowly due to the limited site. Photo: Nham Nguyen

Meanwhile, Ho Chi Minh City is facing difficulties due to land clearance problems.Despite the gathering of enough machinery, materials and human resources, the progress is still slow.The representative of the XL1 package contractor said that the unit has just been handed over a 56 m wide land plot, while the construction corridor needs to be 1720 m.

Currently, the XL1 package has reached about 80% of the plan, the XL2 package nearly 40%.Most of the activities are concentrated around the Long Thanh bridge area.The XL1 package mobilizes more than 650 workers and 120 equipment; the XL2 package has more than 230 personnel and 100 machines, mainly for construction of service roads and bored piles.Many items are still slow due to the lack of detailed construction drawings for the relocation of electricity, fiber optic cables, and water supply.

Du an mo rong cao toc TPHCM – Long Thanh ky vong hoan thanh vao cuoi nam 2026, mo rong cua ngo giao thuong khu vuc phia Nam. Anh: Nham Nguyen
The Ho Chi Minh City - Long Thanh Expressway expansion project is expected to be completed by the end of 2026, expanding the southern area's trade gateway. Photo: Nham Nguyen

The Ho Chi Minh City - Long Thanh Expressway expansion project is 21.92 km long, invested by VEC, with a total capital of more than VND 14,945 billion. The route starts at the Ring Road 2 intersection (HCMC) and ends at the Bien Hoa - Vung Tau Expressway (Dong Nai) with the main axis leading to the future Long Thanh International Airport.

According to the design, the section from Ring Road 2 to Ring Road 3 will be expanded from 4 to 8 lanes; the section from Ring Road 3 to Bien Hoa - Vung Tau Expressway will be expanded from 4 to 10 lanes. Long Thanh Bridge alone will build an additional parallel bridge 23.75 m wide, with 5 lanes and an emergency lane.

The project is an emergency project, started on August 19, 2025, expected to be basically completed by the end of 2026, in line with the progress of phase 1 of Long Thanh airport. Long Thanh Bridge will be closed in December 2026 and fully completed in March 2027.

In early October, VEC proposed that the Ministry of Construction, the People's Committee of Ho Chi Minh City and the People's Committee of Dong Nai province speed up site clearance, ensure progress, and soon complete the main expressway connecting Ho Chi Minh City with Long Thanh airport and the key economic region in the South.

Anh Tú
RELATED NEWS

More than 2,100 households in Ho Chi Minh City are about to receive compensation to give up land to build a highway

|

Ho Chi Minh City will start paying compensation to more than 2,100 households in November to reclaim land for the construction of the Ho Chi Minh City - Moc Bai Expressway.

A series of key expressways are at risk of being delayed in reaching the finish line, the Ministry of Construction issued urgent instructions

|

The Ministry of Construction requires immediate resolution of problems to soon reach the finish line of Tuyen Quang - Ha Giang, Dong Dang (Lang Son) - Tra Linh (Cao Bang) and Huu Nghi - Chi Lang expressways.

Land clearance problems, Ho Chi Minh City - Long Thanh Expressway expansion project at risk of being delayed

|

After more than 2 months of construction, the Ho Chi Minh City - Long Thanh Expressway expansion project has not yet had many clear changes due to land clearance problems.

Man United changes when Bruno Fernandes changes

|

In the series of 3 consecutive victories in the Premier League recently, Bruno Fernandes has contributed a lot even though he has not always scored as before.

Little-known things about Truong Ngoc Anh

|

In the film industry, Truong Ngoc Anh was once a passionate and ambitious person.

Dual benefits of Blackpink and G-Dragon concerts in Vietnam

|

The appeal of Blackpink and G-Dragon concerts in Vietnam shows a new lever for Vietnam's tourism and cultural industry.

Gold prices enter accumulation phase, investors wait for new signal

|

After strong fluctuations, the precious metal market is stabilizing again. December gold futures edged up slightly to $4,021.40 an ounce, while silver fell slightly.

Long Thanh Bridge is bustling with construction, accelerating the expansion of the expressway connecting Long Thanh airport

|

After more than two months of construction, the Ho Chi Minh City - Long Thanh expressway expansion project is accelerating construction, in which Long Thanh bridge is considered a key item.

More than 2,100 households in Ho Chi Minh City are about to receive compensation to give up land to build a highway

MINH QUÂN |

Ho Chi Minh City will start paying compensation to more than 2,100 households in November to reclaim land for the construction of the Ho Chi Minh City - Moc Bai Expressway.

A series of key expressways are at risk of being delayed in reaching the finish line, the Ministry of Construction issued urgent instructions

Khánh Linh |

The Ministry of Construction requires immediate resolution of problems to soon reach the finish line of Tuyen Quang - Ha Giang, Dong Dang (Lang Son) - Tra Linh (Cao Bang) and Huu Nghi - Chi Lang expressways.

Land clearance problems, Ho Chi Minh City - Long Thanh Expressway expansion project at risk of being delayed

Thảo Bích |

After more than 2 months of construction, the Ho Chi Minh City - Long Thanh Expressway expansion project has not yet had many clear changes due to land clearance problems.