Nguyen Canh Di street in Hanoi is changing its coat

SÓNG HỮU |

Hanoi - 600m of Nguyen Canh Di extended road (Dinh Cong ward) is being renovated and upgraded, when completed, it will contribute to synchronizing traffic infrastructure in the South.

Nguyen Canh Di extended road (Dinh Cong ward, Hanoi) is being "put on a new coat" after a long period of degradation, causing no small impact on people's travel and daily life.

Previously, on November 25, 2025, the Hanoi Department of Construction issued document No. 1358/TB-SXD on traffic diversion and organization to serve the construction of 600m of Nguyen Canh Di road extending from Song Lu bridge to Dinh Cong bridge, time from November 25, 2025 to April 30, 2026.

This is a road belonging to the technical infrastructure project of Bac Dai Kim new urban area expansion, invested by Hanoi Housing and Urban Development Business Joint Stock Company.

a
a
a
Nguyen Canh Di extended road has been paved with asphalt concrete 1/2 of the cross-section. Photo: Song Huu

Nguyen Canh Di extended road is about 600m long, an important traffic route connecting Dinh Cong ward residential area with major roads in the area such as Ring Road 2.5, Giai Phong...

For a long time before that, Nguyen Canh Di street surface appeared many potholes and craters, making traffic for vehicles difficult. Especially on rainy days, water stagnation and slipperiness pose a risk of traffic unsafety.

Lao Dong's records in the last days of February show that up to now, half of the road surface has been asphalted newly, the surface is flat, creating favorable conditions for people to move.

The remaining road surface is being urgently deployed by the construction unit, expected to be completed in the near future.

a
a
Vehicles move conveniently on the route. Photo: Song Huu

The renovation and upgrading of 600m of Nguyen Canh Di extended road has received the consensus and support of people living in the area.

Many people said that the prolonged damage in the past not only made travel difficult but also affected the living environment, causing dust in the dry season and mud in the rainy season.

Ms. Nguyen Thi Hanh (resident in Dinh Cong ward) said that previously, this road section was seriously degraded, and traveling was very difficult. Many traffic accidents have occurred here.

Now seeing that the road is being paved with asphalt concrete, we are very excited. Hopefully, when completed, travel will be more convenient and safer" - Ms. Hanh said.

a
1/2 of the remaining cross-section has not been completed. Photo: Song Huu
a
a
a
a
Danger warning signs are placed at manholes. Photo: Song Huu
a
a
People collect garbage at the end of the route, causing unsightliness and environmental pollution. Photo: Song Huu

Mr. Tran Van Minh (35 years old, a resident living in Dinh Cong ward) is also excited that the road section is about to be completed.

The road being repaired is like putting on a new coat. We people have been waiting for this for a long time" - Mr. Minh said.

Upgrading the extended Nguyen Canh Di street not only contributes to improving traffic conditions, reducing the risk of congestion, but also creates motivation to promote socio-economic development in the locality, gradually completing urban infrastructure in the Southern Hanoi area in particular and the Capital in general.

SÓNG HỮU
RELATED NEWS

Nguyen Canh Di street in Dinh Cong ward is under construction and waiting for site clearance

|

Hanoi - While some projects in the area are speeding towards the finish line, Nguyen Canh Di street is both under construction and waiting for the government to hand over the site.

Hanoians are about to escape the misery when traveling through Nguyen Canh Di Street

|

Hanoi - The Department of Construction has just announced the traffic organization for the construction of Nguyen Canh Di Street, which will be extended from now until the end of April next year.

Reasons why Nguyen Canh Di Street, Hanoi has been muddy for many years but has not been repaired

|

A representative of Hanoi Housing and Urban Development Trading Joint Stock Company explained the reason why Nguyen Canh Di Street has been degraded for many years but has not been repaired or upgraded.

Nguyen Canh Di Street, Hanoi can be completed in 2-3 months

|

Hanoi - The investor said that the construction of Nguyen Canh Di Street (Dinh Cong Ward) will be completed within 2-3 months if the site is fully received.

Fire in Bo De ward, column of smoke rises tens of meters high

|

Hanoi - A fire suddenly broke out in alley 405 Bac Cau street, Bo De ward.

Officially opening the Tam Chuc Pagoda Spring Festival in 2026

|

Ninh Binh - February 28th, officially opens Tam Chuc Pagoda Spring Festival Binh Ngo 2026 with the theme "Dawn of the Buddhist realm - Tam Chuc Spring Opening".

Iran announces situation of President Pezeshkian after US airstrike

|

Iran confirms President Masoud Pezeshkian is still safe after a series of airstrikes by the US and Israel.

Two 8th grade female students in Nghe An "arrested" to get married

|

Nghe An - Although the school propagated and prevented it, two 8th grade female students in Na Loi commune were still organized to "take wives" according to local customs.

Nguyen Canh Di street in Dinh Cong ward is under construction and waiting for site clearance

SÓNG HỮU |

Hanoi - While some projects in the area are speeding towards the finish line, Nguyen Canh Di street is both under construction and waiting for the government to hand over the site.

Hanoians are about to escape the misery when traveling through Nguyen Canh Di Street

HỮU CHÁNH |

Hanoi - The Department of Construction has just announced the traffic organization for the construction of Nguyen Canh Di Street, which will be extended from now until the end of April next year.

Reasons why Nguyen Canh Di Street, Hanoi has been muddy for many years but has not been repaired

SÓNG HỮU |

A representative of Hanoi Housing and Urban Development Trading Joint Stock Company explained the reason why Nguyen Canh Di Street has been degraded for many years but has not been repaired or upgraded.

Nguyen Canh Di Street, Hanoi can be completed in 2-3 months

HỮU CHÁNH |

Hanoi - The investor said that the construction of Nguyen Canh Di Street (Dinh Cong Ward) will be completed within 2-3 months if the site is fully received.